Dave Lees (Bedford Pumps) Mellish Kett (Severn Trent) Largest - - PowerPoint PPT Presentation

dave lees bedford pumps
SMART_READER_LITE
LIVE PREVIEW

Dave Lees (Bedford Pumps) Mellish Kett (Severn Trent) Largest - - PowerPoint PPT Presentation

Presentation by Dave Lees (Bedford Pumps) Mellish Kett (Severn Trent) Largest Sewage Treatment Works in Severn Trent Extensive Process Modifications New Pumping Station Entire Works Flow to Full Treatment Settled Sewage Maximum Flow 12,400


slide-1
SLIDE 1

Presentation by Dave Lees (Bedford Pumps) Mellish Kett (Severn Trent)

slide-2
SLIDE 2

Largest Sewage Treatment Works in Severn Trent Extensive Process Modifications New Pumping Station Entire Works Flow to Full Treatment Settled Sewage Maximum Flow 12,400 l/s Approximate Head 3.5m

slide-3
SLIDE 3

Whole Life Cost Review Civil Cost M & E Cost Power Consumption Maintenance

Lineshaft/Volute Pumps £5M Archimedean Screw Pumps £5.48M Submersible Bowl (Canister) Pumps £4.12M

slide-4
SLIDE 4

Bedford Pumps invited to participate No formal Specification Non –Framework Free sharing of ideas Costing of various options Competitive tender reviews not required Ability to react to design changes

slide-5
SLIDE 5

Maximum Flow: 12,400 l/s Average Flow: 5,700 l/s Minimum Flow: 3,500 l/s Total Head (approx): 3.8m

slide-6
SLIDE 6

Design

5+1 Pumps: 2,480 l/s each Nine alternatives. Two subjected to WLC. Diurnal Flows considered. Final Pump selection made.

slide-7
SLIDE 7
slide-8
SLIDE 8

Open–top Canister Pump Arrangement: Ease of installation removal (H & S) Lowest friction loss No pipework or valves Clearly defined static lift

slide-9
SLIDE 9

Additional Return Flows: Maximum flow now 13,150 l/s Part gravity flows after two years Introduction of BNR (Biological Nutrient Removal) Plant, from 2012: Potential increase of 2m on the pump head Phase 1: 13,150 l/s at 2.8m Phase 2: 11,050 l/s at 2.8m Phase 3: 11,050 l/s at 5.1m Same Pump and Motor.

slide-10
SLIDE 10

Model Test commenced. Two sets of three pumps, so half station modelled. Minimum excavation required. Station designed to run at a relatively constant low sump

  • level. Benching required as shown to optimise inlet

conditions into the pump bellmouth.

slide-11
SLIDE 11

Discharge chamber also modelled. Original design was for 1.8m canister outlet diameter. This was changed to 2.4m diameter, to prevent splashover into adjacent units. Also resulted in a reduced “weir” over canister lip. Pump centre spacings now fixed.

slide-12
SLIDE 12

Flows finalised. Minor adjustments to levels and heads taken into account. Results of model test incorporated into design. Final tender submitted 25th October, following several estimates.

slide-13
SLIDE 13

Contract awarded in January. All six pumps given full Grade 1 works performance test. Both contract inverter and in-house inverter used. Guarantee pump efficiency 86.1%. Tested efficiency 88-89%. Pumps delivered December 2008, commissioned March 2009.

slide-14
SLIDE 14

Six Pumps (Five Duty, one Standby) Total station Flow: Max 13,150 l/s (2,630 l/s each) Maximum flow/Pump: 2,630 l/s Maximum Speed: 424 rpm Guarantee duty: 1,200 l/s each at 2.88m (5 units) Guarantee Efficiency: 86.1% Motors: ATB Morley 160 kW 14-pole Pump/motor weight: 6,100 kg

slide-15
SLIDE 15

Six Pumps , canisters, sitework, etc. Total contract Value: £650,000 Production man-hours: 7,000 Installation man-hours: 200 Castings: UK Machining: UK Testing: UK Canisters: UK Motors: UK

slide-16
SLIDE 16
slide-17
SLIDE 17

Change of Plan..

SSPS

ASP 7

BNR

Plan was to install 55,000m3 tank Replaced with advanced Liquor Treatment and increasing depth

  • f existing ASPs

Future duty reduced from 5.1m to 3.25m

slide-18
SLIDE 18

Best Laid Plans.. Remove and replace canister Was there a cheaper way? How are we actually going to do this with the walkway

  • bstruction?
slide-19
SLIDE 19

Ideas New Canister Difficult to remove and would require removal and disconnection of pump

slide-20
SLIDE 20

Ideas Adding to Top Difficult to manufacture 2.4m ring to join and seal

slide-21
SLIDE 21

Ideas Add to bottom Would have to remove Pump to add Coupling, unless… Split Coupling

slide-22
SLIDE 22

How it was done Week without rain Shut Penstocks to isolate one cell

slide-23
SLIDE 23

How it was done Pump down

slide-24
SLIDE 24

How it was done

  • Scaffold out
  • Lift in Couplings
  • Lift Canister
  • Bolt together
slide-25
SLIDE 25

OUTCOMES Collaboration Plan Ahead Plan Ahead More

slide-26
SLIDE 26

Questions?

slide-27
SLIDE 27

(Video)