ODOT Region 1 I-205: Johnson Creek Blvd to Glen Jackson Bridge Northbound Auxiliary Lane SE Powell Blvd to I-84 Northbound and Southbound Active Traffic Management (ATM) Project Map Schedule Advance Plans: May 31, 2018


  1. ODOT – Region 1 I-205: Johnson Creek Blvd to Glen Jackson Bridge Northbound Auxiliary Lane • SE Powell Blvd to I-84 • Northbound and Southbound • Active Traffic Management (ATM)

  2. Project Map

  3. Schedule Advance Plans: May 31, 2018 • Permits: Jul. 27, 2018 • Bid Opening: Nov. 29, 2018 • Construction: Oct. 31, 2019* • * HB2017 Trigger Project with a fixed end date

  4. Schedule

  5. Closure Restrictions Standard Ramp Closures • • Sunday - Friday morning 9:00 p.m. to 5:00 a.m. • Friday - Saturday morning: 10:00 p.m. to 7:00 a.m. • Saturday - Sunday morning: 10:00 p.m. to 8:00 a.m. • I-84 and Airport Way Ramp Closures • Sunday - Friday morning 10:00 p.m. to 5:00 a.m. • Friday - Saturday morning: 10:00 p.m. to 7:00 a.m. • Saturday - Sunday morning: 10:00 p.m. to 8:00 a.m. • Full Closure or Rolling Closure • Sunday night - Friday morning 11:00 p.m. to 4:30 a.m. • Friday night - Sunday morning: 11:00 p.m. to 6:00 a.m.

  6. Aux Lane Closure Options During Construction

  7. Close Existing Exit 21B I-84 WB Auxiliary Lane Exit 21A Glisan St. Division to Exit 20 Washington Start/Washington Auxiliary Lane Closed Improve Construction • Safety From Division St Improve Logistics • From Powell BLVD Northbound over capacity • during AM 3 hour peak

  8. Open Existing Exit 21B I-84 WB Auxiliary Lane Exit 21A Glisan St. Division to Exit 20 Stark/ Washington Washington Auxiliary Lane Open Maintain Traffic Operations • From Logistic Challenges • Division St From Reduced Safety • Powell BLVD Increased Construction • Time

  9. Paving Options

  10. Traditional Nighttime Closure Nighttime Lane and Ramp • Closures Exposure to Traffic • Less Efficient Paving • Potential Higher Cost • Longest Duration •

  11. Full Northbound Closure Weekend Closure • NB I-205 • Closed Foster to I-84 Improve Safety • Shortest Duration • Local Street Congestion and • Diversion

  12. Northbound Express One Month Closure • Two-Lane Express • Ramps Closed • Foster to I-84 Improve Safety • I-205 Capacity for longer trips • Limits Local Street Impacts

  13. Northbound System to System Express One Month Closure • Two-Lane Express • I-84 WB Exit Open • Some Improved Safety • I-205 Near Capacity • Limited Local Street Diversion •

  14. Northbound Two-Lane Full Access Over One Month Closure • Two-Lane Express • All Ramps Open • Limited Improved Safety • I-205 Over Capacity •

  15. Next Steps Questions • Follow-up items • Next meeting •

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.