SLIDE 1 Regional Service Through Unity… Meeting our Region’s Needs Today and Tomorrow
NTMWD BOARD MEETING
April 23, 2020
SLIDE 2 Regional Service Through Unity… Meeting our Region’s Needs Today and Tomorrow
BOIS d’ARC LAKE UPDATE
NTMWD Board Meeting April 23, 2020 Steve Long
Intake Tower RWPS Labyrinth Weir Service Spillway
SLIDE 3 CLICK TO EDIT MASTER TITLE STYLE
BOIS d’ARC LAKE UPDATE
Agenda
- Covid-19 Impacts
- Steps Prior to Impounding Water
- Dam Schedule/Notch Closure
- Original schedule October 29, 2020 Impounded
- Archeology
- Construction Status
- RES
- CMAR 3
- CMAR 4
SLIDE 4 BOIS D’ARC LAKE UPDATE
4
Covid 19 Impacts
- Personnel – no impact
- Schedule Impacts
- Mitigation monitoring moved to May 2020
- Archeologists work 2 to a 1 meter block
- Equipment Delivery Impacts
- TWPL Large diameter butterfly valves
SLIDE 5
CLICK TO EDIT MASTER TITLE STYLE
BOIS D’ARC LAKE BOARD UPDATE
SLIDE 6 BOIS D’ARC LAKE UPDATE
6
CMAR 1 Archer Western - Bois d’Arc Creek Notch Closure Status
- March 3 started Phase II
- Phase II - Closure at Bois d’Arc Creek
- Removed care of water berms/excavating creek bed to reach good foundation
- March 20 cofferdam overtopped
- 7-8 inches of rain 11 consecutive days of measurable rainfall
- March 27 – April 8 cofferdam rebuilt to 495
- Recovery schedule submitted
- Embankment is the critical path
- AW (P&J) working double shifts starting April 20th
- Expect double shifts to continue until end of summer 2020
- AW (P&J) continuing to place concrete at Intake and Service Spillway
SLIDE 7
CLICK TO EDIT MASTER TITLE STYLE
BOIS D’ARC LAKE BOARD UPDATE
Bois d’Arc Creek Notch April 12 https://youtu.be/kqGWFiEwZ4k
SLIDE 8
CLICK TO EDIT MASTER TITLE STYLE
BOIS D’ARC LAKE EXECUTIVE COMMITTEE
Intake Tower Debris Boom (off to the side)
SLIDE 9
CLICK TO EDIT MASTER TITLE STYLE
BOIS D’ARC LAKE EXECUTIVE BRIEFING
Service Spillway Chute Walls at Labyrinth
SLIDE 10 BOIS D’ARC LAKE UPDATE
12
Archeology Mitigation
- Site 114 SOW submitted – 4/16/2020
- 25 archeologists working in the field
- Schedule Impacts
- Site 118 – July 15, 2020
- Site 120 – July 15, 2020 (1 remaining burial)
- Site 178 – July 15, 2020 (1 remaining burial)
- Site 244 – conditional scope of work approved
- Site 151 – early start/conditional scope of work approved
- Covid-19 impacts
– Archeologists work 2 to a 1 meter block – Equipment sharing
SLIDE 11 BOIS D’ARC LAKE UPDATE
13
Mitigation Full Service Provider Status
- Plantings
- 9,937 acres restored/enhanced
- 4,372 acres remaining to be planted (includes Upper Bois d’Arc
Creek)
- 1,400,000 trees planted (600 trees/ac new; 200 trees/ac replant)
- Total of 3,000,000 trees planted
- 1,376 acres Upper Bois d’Arc Creek property purchased
- Cultural resources survey pending/ARC developing survey SOW
- Streams
- 75,609 feet of streams restored
- 48,629 feet of streams remaining
- Hydrology restored to streams in the WRP
SLIDE 12
CLICK TO EDIT MASTER TITLE STYLE
MITIGATION FSP RES – PLANTING AREAS
SLIDE 13
CLICK TO EDIT MASTER TITLE STYLE
MITIGATION FSP RES – RESTORED STREAMS
SLIDE 14 BOIS D’ARC LAKE BOARD UPDATE
16
SLIDE 15
CLICK TO EDIT MASTER TITLE STYLE
BOIS d’ARC LAKE UPDATE
CMAR 3 – Water Tank, Reclaimed Basins, Filters, West Chem, Clearwell, & HSPS
SLIDE 16
CLICK TO EDIT MASTER TITLE STYLE
BOIS d’ARC LAKE UPDATE
Leonard WTP High Service Pump Station
SLIDE 17
CLICK TO EDIT MASTER TITLE STYLE
BOIS d’ARC LAKE UPDATE
Leonard WTP Clearwell
SLIDE 18
CLICK TO EDIT MASTER TITLE STYLE FM 897 BRIDGE – FINAL BEAM SET (300TH)
SLIDE 19
CLICK TO EDIT MASTER TITLE STYLE
BOIS d’ARC LAKE UPDATE
CMAR 4 – Austin Bridge and Road (Site 2)
SLIDE 20
CLICK TO EDIT MASTER TITLE STYLE
BOIS d’ARC LAKE UPDATE
CMAR 4 – Austin Bridge and Road (Site 3)
SLIDE 21
CLICK TO EDIT MASTER TITLE STYLE
BOIS d’ARC LAKE CONSTRUCTION PHOTOS
CMAR 4 – Austin Bridge and Road (Lake Operations Center) Lake Operations Building & Maintenance Building
SLIDE 22
CLICK TO EDIT MASTER TITLE STYLE
QUESTIONS?