NTMWD BOARD MEETING April 23, 2020 Regional Service Through Unity - - PowerPoint PPT Presentation

ntmwd board meeting
SMART_READER_LITE
LIVE PREVIEW

NTMWD BOARD MEETING April 23, 2020 Regional Service Through Unity - - PowerPoint PPT Presentation

Regional Service Through Unity Meeting our Regions Needs Today and Tomorrow NTMWD BOARD MEETING April 23, 2020 Regional Service Through Unity Meeting our Regions Needs Today and Tomorrow RWPS Intake Tower Service Spillway


slide-1
SLIDE 1

Regional Service Through Unity… Meeting our Region’s Needs Today and Tomorrow

NTMWD BOARD MEETING

April 23, 2020

slide-2
SLIDE 2

Regional Service Through Unity… Meeting our Region’s Needs Today and Tomorrow

BOIS d’ARC LAKE UPDATE

NTMWD Board Meeting April 23, 2020 Steve Long

Intake Tower RWPS Labyrinth Weir Service Spillway

slide-3
SLIDE 3

CLICK TO EDIT MASTER TITLE STYLE

BOIS d’ARC LAKE UPDATE

Agenda

  • Covid-19 Impacts
  • Steps Prior to Impounding Water
  • Dam Schedule/Notch Closure
  • Original schedule October 29, 2020 Impounded
  • Archeology
  • Construction Status
  • RES
  • CMAR 3
  • CMAR 4
slide-4
SLIDE 4

BOIS D’ARC LAKE UPDATE

4

Covid 19 Impacts

  • Personnel – no impact
  • Schedule Impacts
  • Mitigation monitoring moved to May 2020
  • Archeologists work 2 to a 1 meter block
  • Equipment Delivery Impacts
  • TWPL Large diameter butterfly valves
slide-5
SLIDE 5

CLICK TO EDIT MASTER TITLE STYLE

BOIS D’ARC LAKE BOARD UPDATE

slide-6
SLIDE 6

BOIS D’ARC LAKE UPDATE

6

CMAR 1 Archer Western - Bois d’Arc Creek Notch Closure Status

  • March 3 started Phase II
  • Phase II - Closure at Bois d’Arc Creek
  • Removed care of water berms/excavating creek bed to reach good foundation
  • March 20 cofferdam overtopped
  • 7-8 inches of rain 11 consecutive days of measurable rainfall
  • March 27 – April 8 cofferdam rebuilt to 495
  • Recovery schedule submitted
  • Embankment is the critical path
  • AW (P&J) working double shifts starting April 20th
  • Expect double shifts to continue until end of summer 2020
  • AW (P&J) continuing to place concrete at Intake and Service Spillway
slide-7
SLIDE 7

CLICK TO EDIT MASTER TITLE STYLE

BOIS D’ARC LAKE BOARD UPDATE

Bois d’Arc Creek Notch April 12 https://youtu.be/kqGWFiEwZ4k

slide-8
SLIDE 8

CLICK TO EDIT MASTER TITLE STYLE

BOIS D’ARC LAKE EXECUTIVE COMMITTEE

Intake Tower Debris Boom (off to the side)

slide-9
SLIDE 9

CLICK TO EDIT MASTER TITLE STYLE

BOIS D’ARC LAKE EXECUTIVE BRIEFING

Service Spillway Chute Walls at Labyrinth

slide-10
SLIDE 10

BOIS D’ARC LAKE UPDATE

12

Archeology Mitigation

  • Site 114 SOW submitted – 4/16/2020
  • 25 archeologists working in the field
  • Schedule Impacts
  • Site 118 – July 15, 2020
  • Site 120 – July 15, 2020 (1 remaining burial)
  • Site 178 – July 15, 2020 (1 remaining burial)
  • Site 244 – conditional scope of work approved
  • Site 151 – early start/conditional scope of work approved
  • Covid-19 impacts

– Archeologists work 2 to a 1 meter block – Equipment sharing

slide-11
SLIDE 11

BOIS D’ARC LAKE UPDATE

13

Mitigation Full Service Provider Status

  • Plantings
  • 9,937 acres restored/enhanced
  • 4,372 acres remaining to be planted (includes Upper Bois d’Arc

Creek)

  • 1,400,000 trees planted (600 trees/ac new; 200 trees/ac replant)
  • Total of 3,000,000 trees planted
  • 1,376 acres Upper Bois d’Arc Creek property purchased
  • Cultural resources survey pending/ARC developing survey SOW
  • Streams
  • 75,609 feet of streams restored
  • 48,629 feet of streams remaining
  • Hydrology restored to streams in the WRP
slide-12
SLIDE 12

CLICK TO EDIT MASTER TITLE STYLE

MITIGATION FSP RES – PLANTING AREAS

slide-13
SLIDE 13

CLICK TO EDIT MASTER TITLE STYLE

MITIGATION FSP RES – RESTORED STREAMS

slide-14
SLIDE 14

BOIS D’ARC LAKE BOARD UPDATE

16

slide-15
SLIDE 15

CLICK TO EDIT MASTER TITLE STYLE

BOIS d’ARC LAKE UPDATE

CMAR 3 – Water Tank, Reclaimed Basins, Filters, West Chem, Clearwell, & HSPS

slide-16
SLIDE 16

CLICK TO EDIT MASTER TITLE STYLE

BOIS d’ARC LAKE UPDATE

Leonard WTP High Service Pump Station

slide-17
SLIDE 17

CLICK TO EDIT MASTER TITLE STYLE

BOIS d’ARC LAKE UPDATE

Leonard WTP Clearwell

slide-18
SLIDE 18

CLICK TO EDIT MASTER TITLE STYLE FM 897 BRIDGE – FINAL BEAM SET (300TH)

slide-19
SLIDE 19

CLICK TO EDIT MASTER TITLE STYLE

BOIS d’ARC LAKE UPDATE

CMAR 4 – Austin Bridge and Road (Site 2)

slide-20
SLIDE 20

CLICK TO EDIT MASTER TITLE STYLE

BOIS d’ARC LAKE UPDATE

CMAR 4 – Austin Bridge and Road (Site 3)

slide-21
SLIDE 21

CLICK TO EDIT MASTER TITLE STYLE

BOIS d’ARC LAKE CONSTRUCTION PHOTOS

CMAR 4 – Austin Bridge and Road (Lake Operations Center) Lake Operations Building & Maintenance Building

slide-22
SLIDE 22

CLICK TO EDIT MASTER TITLE STYLE

QUESTIONS?

BOIS d’ARC LAKE UPDATE