BOIS DARC LAKE Texas Water Conservation Association March 7, 2019 - - PowerPoint PPT Presentation

bois d arc lake
SMART_READER_LITE
LIVE PREVIEW

BOIS DARC LAKE Texas Water Conservation Association March 7, 2019 - - PowerPoint PPT Presentation

Regional Service Through Unity Meeting our Regions Needs Today and Tomorrow BOIS DARC LAKE Texas Water Conservation Association March 7, 2019 Tom Kula, NTMWD Executive Director Mike Rickman, NTMWD Deputy Director Operations &


slide-1
SLIDE 1

Regional Service Through Unity… Meeting our Region’s Needs Today and Tomorrow

BOIS D’ARC LAKE

Texas Water Conservation Association March 7, 2019 Tom Kula, NTMWD Executive Director Mike Rickman, NTMWD Deputy Director Operations & Maintenance

slide-2
SLIDE 2

OVERVIEW

  • Growing population
  • Existing & Future Supplies

– Conservation – Reuse – New Reservoir

  • Bois d’Arc Lake & Related

Projects

– Permitting – Mitigation – Construction Progress and Timeline

  • Keys to Success
  • Questions

2

slide-3
SLIDE 3

Water Essential for Economic Growth

Water supply infrastructure is the driving force of community and business vitality

The Star - Frisco Legacy West - Plano Craig Ranch - McKinney Watters Creek Convention Center – Allen

NTMWD Total Population Served: Historical and Projected

Year 1956 1961 1974 1994 2019 2040 2070 Population Served 32,000 60,000 200,000 800,000 1,700,000 2,500,000 3,700,000

slide-4
SLIDE 4

Existing & Planned Raw Water Supplies

Existing:

  • Lavon Lake
  • Lake Texoma
  • Lake Tawakoni
  • Chapman Lake
  • Reuse/Wetland

In Progress:

  • Bois d’Arc Lake
slide-5
SLIDE 5

WATER SUPPLY PLANNING: FUTURE SOURCES

Conservation and Reuse = 21% New Sources, Reservoirs = 25%

Current Supplies, 22%

5

Connect Existing Supplies, 32% Conservation& Reuse, 21% New Reservoirs, 25%

Chart represents NTMWD supplies in 2060 Source: 2016 Region C Water Plan

slide-6
SLIDE 6

CLICK TO EDIT MASTER TITLE STYLE BOIS D’ARC LAKE

  • Decade+ of planning, permitting
  • Surface Area: 16,641 acres
  • Supply: Firm Yield of 108 MGD
  • Average/Max Depth: 22/70 ft
  • Lake Elevation: 534 ft mean

sea level (MSL)

  • Owner & operator: NTMWD
  • Cost Estimate: $1.6B
  • Construction began May 2018
  • Impoundment expected Fall 2020
  • Water delivery expected Spring

2022 First major reservoir to be constructed in Texas in nearly 30 years

slide-7
SLIDE 7

7

Bois d’Arc Lake: Key Components & Related Infrastructure

  • 1. Dam and intake structure

for reservoir

  • 2. 35-mile raw water

pipeline

  • 3. $50 million road projects
  • 4. Mitigation area (over

17,000 acres)

  • 5. New water treatment

plant, pump station, terminal storage reservoir

  • 6. 25-mile treated water

pipeline

slide-8
SLIDE 8

PLANNING AND PERMITTING TIMELINE

8

December 2006

State Water Rights Permit Application

June 2008

USACE Section 404 Permit Application

February 2015

USACE Issues Draft Environmental Impact Statement

June 2015 State Water Rights Permit Received – Anticipating 404 Permit in Jan 2016 July 2015

USACE Requires HGM methodology for Mitigation – Delay in expected 404 permit

March 2017

USACE Issues Revised Draft Environmental Impact Statement

November 2017

USACE Issues Final Environmental Impact Statement

Feb 2018

USACE Section 404 Permit Received

slide-9
SLIDE 9

CLICK TO EDIT MASTER TITLE STYLE AQUATIC AND TERRESTRIAL MITIGATION

9

  • Environmental mitigation on

more than 17,000 acres – Largest permittee- responsible ecological mitigation project in nation – Over 8,500 acres of wetland restoration and enhancement – Planting approx. 5 million trees – Restoring or enhancing over 3,200 acres of native grasslands; 2,600 acres of forests – Improving over 70 miles of local streams

slide-10
SLIDE 10

CLICK TO EDIT MASTER TITLE STYLE

Trees Delivered and Stacked January 2019 Tree Planting Crew February 2019

RIVERBY RANCH MITIGATION SITE

Over 1.23 million trees planted to date (As of March 1)

slide-11
SLIDE 11

CLICK TO EDIT MASTER TITLE STYLE PERMITTING REFORM RECOMMENDATIONS

STREAMLINE PERMITTING

  • Unnecessary delays from changeover in

people, policies, concepts and procedures – process should only take 2-3 years

STATUTE OF LIMITATIONS TO PERMIT CHALLENGES

  • Should be shortened to 180 days vs. 5+ years

to avoid further delays of litigation

FEDERAL FUNDING FOR SUPPLY PROJECTS

  • Water supply lowest priority and lowest funded

program of USACE – need Congress to approve more funding and resources

ESTABLISHING PURPOSE & NEED

  • Population and demand projections

developed/approved by state should be sufficient

USE OF BEST AVAILABLE INFORMATION

  • Applicants shouldn’t be required to

develop new or updated information late in permitting process – recommend statutory deadline.

  • Applicant and agencies should have

binding agreement on impact assessment methods required for evaluation.

COMPENSATORY MITIGATION

  • Environmental benefits of supply projects

should be considered as offsets to impacts

slide-12
SLIDE 12

BOIS D’ARC LAKE PROGRAM COMPONENTS

12

CMAR 1 – Dam and Reservoir Clearing/Terminal Storage Reservoir Program Component 2 – Full Service Provider Mitigation Project CMAR 3 – Leonard Water Treatment Plant and Pump Stations CMAR 4 – Roads and Bridges CMAR 5 – Raw Water and Treated Water pipelines

Major Components include several projects; projects were separated by type of work/infrastructure:

slide-13
SLIDE 13

CLICK TO EDIT MASTER TITLE STYLE CMAR 1 – DAM & TERMINAL STORAGE RESERVOIR (TSR) Goal:

By December 2020:

– Begin impounding water – Complete terminal storage reservoir at Leonard WTP

Scope:

  • Dam and Clearing
  • Intake Tower
  • 210 MG (420 MG

ultimate) terminal storage reservoir

  • Lake Bonham Dam

Improvements

Foundation Excavation for the Dam Footprint August 2018

slide-14
SLIDE 14

CLICK TO EDIT MASTER TITLE STYLE BOIS D’ARC LAKE DAM AND RESERVOIR

Dam Embankment February 2019

2-mile long, 90-ft tall dam

slide-15
SLIDE 15

CLICK TO EDIT MASTER TITLE STYLE

Intake Tower Slab Pour January 2019 Excavating the Intake Tower Conduit January 2019

BOIS D’ARC LAKE DAM AND RESERVOIR

Slab = 1,100 cubic yards of concrete Two 78-inch pipes from Intake Tower to Pump Station

slide-16
SLIDE 16

CLICK TO EDIT MASTER TITLE STYLE CMAR 3 – WATER TREATMENT PLANT & PUMP STATIONS Goal: Complete and

  • perational by First

Quarter of 2022 Scope:

  • Raw Water Pump Station

(RWPS) at the dam (90 MGD – 236 MGD ultimate)

  • 70 MGD Leonard Water

Treatment Plant (LWTP) (280 MGD ultimate)

  • High Service Pump Station

(HSPS) at WTP site (90 MGD – 330 MGD ultimate)

Raw Water Pump Station Excavation February 2019

slide-17
SLIDE 17

CLICK TO EDIT MASTER TITLE STYLE

December 2018 Looking North Raw Water Pump Station January 2019

LEONARD WATER TREATMENT PLANT SITE AND RAW WATER PS

Phase 1 = 210 MG terminal storage reservoir and 90 MGD high service pump station 9 pumps in a football field-sized building

slide-18
SLIDE 18

CLICK TO EDIT MASTER TITLE STYLE CMAR 4 – ROAD IMPROVEMENTS & BOAT RAMPS Goal:

Before impoundment, complete:

– FM 897 Improvements – Fannin County Road improvements – Boat ramps

Scope:

  • FM 897

– 6.2 miles of new FM roadway – 1.3 miles of new bridge

  • County roads

– Improvements at 9 locations – Bridge, culvert, and roadway embankment – Bridge/culvert demolition at 5 additional locations

FM 897 Columns and Bent Caps February 2019

slide-19
SLIDE 19

CLICK TO EDIT MASTER TITLE STYLE CMAR 5 – RAW AND TREATED WATER PIPELINES

Approximately 35 miles of raw water pipeline and 25 miles of treated water pipeline

slide-20
SLIDE 20

CLICK TO EDIT MASTER TITLE STYLE TIMELINE TO WATER DELIVERY IN 2022

20

slide-21
SLIDE 21

CLICK TO EDIT MASTER TITLE STYLE KEYS TO SUCCESS

21

  • Reservoirs are an absolute necessity and we’ve stayed focused on:

– PROTECTING ENVIRONMENT – SMART DEVELOPMENT – PROVIDING ESSENTIAL SERVICES TO NORTH TEXANS… WATER IS LIFE

  • Build relationships with state

and federal agencies early

  • Assemble dream team – get

right resources/expertise

  • Get support from elected
  • fficials – keep informed

along the way

  • Funded entire $1.6B project

with low interest SWIFT funding from TWDB… saving ~ $230 million Follow our progress at www.BoisdArcLake.org

slide-22
SLIDE 22

QUESTIONS? FOLLOW US @NTMWD www.BoisdArcLake.org