bois d arc lake
play

BOIS DARC LAKE Texas Water Conservation Association March 7, 2019 - PowerPoint PPT Presentation

Regional Service Through Unity Meeting our Regions Needs Today and Tomorrow BOIS DARC LAKE Texas Water Conservation Association March 7, 2019 Tom Kula, NTMWD Executive Director Mike Rickman, NTMWD Deputy Director Operations &


  1. Regional Service Through Unity… Meeting our Region’s Needs Today and Tomorrow BOIS D’ARC LAKE Texas Water Conservation Association March 7, 2019 Tom Kula, NTMWD Executive Director Mike Rickman, NTMWD Deputy Director Operations & Maintenance

  2. OVERVIEW • Growing population • Existing & Future Supplies – Conservation – Reuse – New Reservoir • Bois d’Arc Lake & Related Projects – Permitting – Mitigation – Construction Progress and Timeline • Keys to Success • Questions 2

  3. Water Essential for Economic Growth Water supply infrastructure is the driving force of community and business vitality NTMWD Total Population Served: Historical and Projected Year 1956 1961 1974 1994 2019 2040 2070 Population 32,000 60,000 200,000 800,000 1,700,000 2,500,000 3,700,000 Served The Star - Frisco Legacy West - Plano Craig Ranch - McKinney Watters Creek Convention Center – Allen

  4. Existing & Planned Raw Water Supplies Existing: • Lavon Lake • Lake Texoma • Lake Tawakoni • Chapman Lake • Reuse/Wetland In Progress: • Bois d’Arc Lake

  5. WATER SUPPLY PLANNING: FUTURE SOURCES New Current Reservoirs, Supplies, 25% 22% Conservation and Reuse = 21% New Sources, Reservoirs = 25% Connect Conservation& Existing Reuse, 21% Supplies, 32% Chart represents NTMWD supplies in 2060 Source: 2016 Region C Water Plan 5

  6. BOIS D’ARC LAKE CLICK TO EDIT MASTER TITLE STYLE • Decade+ of planning, permitting • Surface Area: 16,641 acres • Supply: Firm Yield of 108 MGD • Average/Max Depth: 22/70 ft • Lake Elevation: 534 ft mean sea level (MSL) • Owner & operator: NTMWD • Cost Estimate: $1.6B • Construction began May 2018 • Impoundment expected Fall 2020 • Water delivery expected Spring 2022 First major reservoir to be constructed in Texas in nearly 30 years

  7. Bois d’Arc Lake: Key Components & Related Infrastructure 1. Dam and intake structure for reservoir 2. 35-mile raw water pipeline 3. $50 million road projects 4. Mitigation area (over 17,000 acres) 5. New water treatment plant, pump station, terminal storage reservoir 6. 25-mile treated water pipeline 7

  8. PLANNING AND PERMITTING TIMELINE December 2006 June 2008 State Water February 2015 Rights Permit USACE Application June 2015 Section 404 USACE Issues Permit Draft Application State Water Environmental Rights Permit Impact Received – Statement Anticipating 404 Permit in Jan 2016 July 2015 March 2017 USACE November 2017 Requires HGM USACE Issues methodology Feb 2018 Revised Draft for Mitigation – USACE Issues Environmental Final Delay in Impact USACE Environmental expected 404 Statement permit Impact Section Statement 404 Permit Received 8

  9. CLICK TO EDIT MASTER TITLE STYLE AQUATIC AND TERRESTRIAL MITIGATION • Environmental mitigation on more than 17,000 acres – Largest permittee- responsible ecological mitigation project in nation – Over 8,500 acres of wetland restoration and enhancement – Planting approx. 5 million trees – Restoring or enhancing over 3,200 acres of native grasslands; 2,600 acres of forests – Improving over 70 miles of local streams 9

  10. CLICK TO EDIT MASTER TITLE STYLE RIVERBY RANCH MITIGATION SITE Trees Delivered and Stacked Tree Planting Crew January 2019 February 2019 Over 1.23 million trees planted to date (As of March 1)

  11. PERMITTING REFORM RECOMMENDATIONS CLICK TO EDIT MASTER TITLE STYLE STREAMLINE PERMITTING ESTABLISHING PURPOSE & NEED • Unnecessary delays from changeover in • Population and demand projections people, policies, concepts and procedures – developed/approved by state should be process should only take 2-3 years sufficient STATUTE OF LIMITATIONS TO PERMIT USE OF BEST AVAILABLE CHALLENGES INFORMATION • Should be shortened to 180 days vs. 5+ years • Applicants shouldn’t be required to to avoid further delays of litigation develop new or updated information late in permitting process – recommend statutory deadline. FEDERAL FUNDING FOR SUPPLY PROJECTS • Applicant and agencies should have binding agreement on impact assessment • Water supply lowest priority and lowest funded methods required for evaluation. program of USACE – need Congress to approve more funding and resources COMPENSATORY MITIGATION • Environmental benefits of supply projects should be considered as offsets to impacts

  12. BOIS D’ARC LAKE PROGRAM COMPONENTS Major Components include several projects; projects were separated by type of work/infrastructure: CMAR 1 – Dam and Reservoir Clearing/Terminal Storage Reservoir Program Component 2 – Full Service Provider Mitigation Project CMAR 3 – Leonard Water Treatment Plant and Pump Stations CMAR 4 – Roads and Bridges CMAR 5 – Raw Water and Treated Water pipelines 12

  13. CLICK TO EDIT MASTER TITLE STYLE CMAR 1 – DAM & TERMINAL STORAGE RESERVOIR (TSR) Foundation Excavation for the Dam Footprint Goal: August 2018 By December 2020: Begin impounding water – – Complete terminal storage reservoir at Leonard WTP Scope: • Dam and Clearing • Intake Tower • 210 MG (420 MG ultimate) terminal storage reservoir • Lake Bonham Dam Improvements

  14. BOIS D’ARC LAKE DAM AND RESERVOIR CLICK TO EDIT MASTER TITLE STYLE Dam Embankment February 2019 2-mile long, 90-ft tall dam

  15. BOIS D’ARC LAKE DAM AND RESERVOIR CLICK TO EDIT MASTER TITLE STYLE Intake Tower Slab Pour Excavating the Intake Tower Conduit January 2019 January 2019 Slab = 1,100 cubic yards of concrete Two 78-inch pipes from Intake Tower to Pump Station

  16. CLICK TO EDIT MASTER TITLE STYLE CMAR 3 – WATER TREATMENT PLANT & PUMP STATIONS Goal: Raw Water Pump Station Excavation February 2019 Complete and operational by First Quarter of 2022 Scope: • Raw Water Pump Station (RWPS) at the dam (90 MGD – 236 MGD ultimate) • 70 MGD Leonard Water Treatment Plant (LWTP) (280 MGD ultimate) • High Service Pump Station (HSPS) at WTP site (90 MGD – 330 MGD ultimate)

  17. LEONARD WATER TREATMENT PLANT SITE AND RAW WATER PS CLICK TO EDIT MASTER TITLE STYLE Raw Water Pump Station December 2018 January 2019 Looking North Phase 1 = 210 MG terminal storage reservoir 9 pumps in a football field-sized building and 90 MGD high service pump station

  18. CMAR 4 – ROAD IMPROVEMENTS & BOAT RAMPS CLICK TO EDIT MASTER TITLE STYLE Goal: FM 897 Columns and Bent Caps February 2019 Before impoundment, complete: – FM 897 Improvements – Fannin County Road improvements – Boat ramps Scope: • FM 897 – 6.2 miles of new FM roadway – 1.3 miles of new bridge • County roads – Improvements at 9 locations – Bridge, culvert, and roadway embankment Bridge/culvert demolition at 5 – additional locations

  19. CMAR 5 – RAW AND TREATED WATER PIPELINES CLICK TO EDIT MASTER TITLE STYLE Approximately 35 miles of raw water pipeline and 25 miles of treated water pipeline

  20. CLICK TO EDIT MASTER TITLE STYLE TIMELINE TO WATER DELIVERY IN 2022 20

  21. KEYS TO SUCCESS CLICK TO EDIT MASTER TITLE STYLE • Reservoirs are an absolute necessity and we’ve stayed focused on: – PROTECTING ENVIRONMENT – SMART DEVELOPMENT – PROVIDING ESSENTIAL SERVICES TO NORTH TEXANS… WATER IS LIFE • Build relationships with state and federal agencies early • Assemble dream team – get right resources/expertise • Get support from elected officials – keep informed along the way • Funded entire $1.6B project with low interest SWIFT funding from TWDB… saving Follow our progress at www.BoisdArcLake.org ~ $230 million 21

  22. QUESTIONS? FOLLOW US @NTMWD www.BoisdArcLake.org

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend