SLIDE 1 Regional Service Through Unity… Meeting our Region’s Needs Today and Tomorrow
BOIS D’ARC LAKE
Texas Water Conservation Association March 7, 2019 Tom Kula, NTMWD Executive Director Mike Rickman, NTMWD Deputy Director Operations & Maintenance
SLIDE 2 OVERVIEW
- Growing population
- Existing & Future Supplies
– Conservation – Reuse – New Reservoir
- Bois d’Arc Lake & Related
Projects
– Permitting – Mitigation – Construction Progress and Timeline
- Keys to Success
- Questions
2
SLIDE 3
Water Essential for Economic Growth
Water supply infrastructure is the driving force of community and business vitality
The Star - Frisco Legacy West - Plano Craig Ranch - McKinney Watters Creek Convention Center – Allen
NTMWD Total Population Served: Historical and Projected
Year 1956 1961 1974 1994 2019 2040 2070 Population Served 32,000 60,000 200,000 800,000 1,700,000 2,500,000 3,700,000
SLIDE 4 Existing & Planned Raw Water Supplies
Existing:
- Lavon Lake
- Lake Texoma
- Lake Tawakoni
- Chapman Lake
- Reuse/Wetland
In Progress:
SLIDE 5 WATER SUPPLY PLANNING: FUTURE SOURCES
Conservation and Reuse = 21% New Sources, Reservoirs = 25%
Current Supplies, 22%
5
Connect Existing Supplies, 32% Conservation& Reuse, 21% New Reservoirs, 25%
Chart represents NTMWD supplies in 2060 Source: 2016 Region C Water Plan
SLIDE 6 CLICK TO EDIT MASTER TITLE STYLE BOIS D’ARC LAKE
- Decade+ of planning, permitting
- Surface Area: 16,641 acres
- Supply: Firm Yield of 108 MGD
- Average/Max Depth: 22/70 ft
- Lake Elevation: 534 ft mean
sea level (MSL)
- Owner & operator: NTMWD
- Cost Estimate: $1.6B
- Construction began May 2018
- Impoundment expected Fall 2020
- Water delivery expected Spring
2022 First major reservoir to be constructed in Texas in nearly 30 years
SLIDE 7 7
Bois d’Arc Lake: Key Components & Related Infrastructure
- 1. Dam and intake structure
for reservoir
pipeline
- 3. $50 million road projects
- 4. Mitigation area (over
17,000 acres)
plant, pump station, terminal storage reservoir
pipeline
SLIDE 8 PLANNING AND PERMITTING TIMELINE
8
December 2006
State Water Rights Permit Application
June 2008
USACE Section 404 Permit Application
February 2015
USACE Issues Draft Environmental Impact Statement
June 2015 State Water Rights Permit Received – Anticipating 404 Permit in Jan 2016 July 2015
USACE Requires HGM methodology for Mitigation – Delay in expected 404 permit
March 2017
USACE Issues Revised Draft Environmental Impact Statement
November 2017
USACE Issues Final Environmental Impact Statement
Feb 2018
USACE Section 404 Permit Received
SLIDE 9 CLICK TO EDIT MASTER TITLE STYLE AQUATIC AND TERRESTRIAL MITIGATION
9
- Environmental mitigation on
more than 17,000 acres – Largest permittee- responsible ecological mitigation project in nation – Over 8,500 acres of wetland restoration and enhancement – Planting approx. 5 million trees – Restoring or enhancing over 3,200 acres of native grasslands; 2,600 acres of forests – Improving over 70 miles of local streams
SLIDE 10
CLICK TO EDIT MASTER TITLE STYLE
Trees Delivered and Stacked January 2019 Tree Planting Crew February 2019
RIVERBY RANCH MITIGATION SITE
Over 1.23 million trees planted to date (As of March 1)
SLIDE 11 CLICK TO EDIT MASTER TITLE STYLE PERMITTING REFORM RECOMMENDATIONS
STREAMLINE PERMITTING
- Unnecessary delays from changeover in
people, policies, concepts and procedures – process should only take 2-3 years
STATUTE OF LIMITATIONS TO PERMIT CHALLENGES
- Should be shortened to 180 days vs. 5+ years
to avoid further delays of litigation
FEDERAL FUNDING FOR SUPPLY PROJECTS
- Water supply lowest priority and lowest funded
program of USACE – need Congress to approve more funding and resources
ESTABLISHING PURPOSE & NEED
- Population and demand projections
developed/approved by state should be sufficient
USE OF BEST AVAILABLE INFORMATION
- Applicants shouldn’t be required to
develop new or updated information late in permitting process – recommend statutory deadline.
- Applicant and agencies should have
binding agreement on impact assessment methods required for evaluation.
COMPENSATORY MITIGATION
- Environmental benefits of supply projects
should be considered as offsets to impacts
SLIDE 12 BOIS D’ARC LAKE PROGRAM COMPONENTS
12
CMAR 1 – Dam and Reservoir Clearing/Terminal Storage Reservoir Program Component 2 – Full Service Provider Mitigation Project CMAR 3 – Leonard Water Treatment Plant and Pump Stations CMAR 4 – Roads and Bridges CMAR 5 – Raw Water and Treated Water pipelines
Major Components include several projects; projects were separated by type of work/infrastructure:
SLIDE 13 CLICK TO EDIT MASTER TITLE STYLE CMAR 1 – DAM & TERMINAL STORAGE RESERVOIR (TSR) Goal:
By December 2020:
– Begin impounding water – Complete terminal storage reservoir at Leonard WTP
Scope:
- Dam and Clearing
- Intake Tower
- 210 MG (420 MG
ultimate) terminal storage reservoir
Improvements
Foundation Excavation for the Dam Footprint August 2018
SLIDE 14
CLICK TO EDIT MASTER TITLE STYLE BOIS D’ARC LAKE DAM AND RESERVOIR
Dam Embankment February 2019
2-mile long, 90-ft tall dam
SLIDE 15
CLICK TO EDIT MASTER TITLE STYLE
Intake Tower Slab Pour January 2019 Excavating the Intake Tower Conduit January 2019
BOIS D’ARC LAKE DAM AND RESERVOIR
Slab = 1,100 cubic yards of concrete Two 78-inch pipes from Intake Tower to Pump Station
SLIDE 16 CLICK TO EDIT MASTER TITLE STYLE CMAR 3 – WATER TREATMENT PLANT & PUMP STATIONS Goal: Complete and
Quarter of 2022 Scope:
(RWPS) at the dam (90 MGD – 236 MGD ultimate)
Treatment Plant (LWTP) (280 MGD ultimate)
- High Service Pump Station
(HSPS) at WTP site (90 MGD – 330 MGD ultimate)
Raw Water Pump Station Excavation February 2019
SLIDE 17
CLICK TO EDIT MASTER TITLE STYLE
December 2018 Looking North Raw Water Pump Station January 2019
LEONARD WATER TREATMENT PLANT SITE AND RAW WATER PS
Phase 1 = 210 MG terminal storage reservoir and 90 MGD high service pump station 9 pumps in a football field-sized building
SLIDE 18 CLICK TO EDIT MASTER TITLE STYLE CMAR 4 – ROAD IMPROVEMENTS & BOAT RAMPS Goal:
Before impoundment, complete:
– FM 897 Improvements – Fannin County Road improvements – Boat ramps
Scope:
– 6.2 miles of new FM roadway – 1.3 miles of new bridge
– Improvements at 9 locations – Bridge, culvert, and roadway embankment – Bridge/culvert demolition at 5 additional locations
FM 897 Columns and Bent Caps February 2019
SLIDE 19
CLICK TO EDIT MASTER TITLE STYLE CMAR 5 – RAW AND TREATED WATER PIPELINES
Approximately 35 miles of raw water pipeline and 25 miles of treated water pipeline
SLIDE 20 CLICK TO EDIT MASTER TITLE STYLE TIMELINE TO WATER DELIVERY IN 2022
20
SLIDE 21 CLICK TO EDIT MASTER TITLE STYLE KEYS TO SUCCESS
21
- Reservoirs are an absolute necessity and we’ve stayed focused on:
– PROTECTING ENVIRONMENT – SMART DEVELOPMENT – PROVIDING ESSENTIAL SERVICES TO NORTH TEXANS… WATER IS LIFE
- Build relationships with state
and federal agencies early
- Assemble dream team – get
right resources/expertise
- Get support from elected
- fficials – keep informed
along the way
- Funded entire $1.6B project
with low interest SWIFT funding from TWDB… saving ~ $230 million Follow our progress at www.BoisdArcLake.org
SLIDE 22
QUESTIONS? FOLLOW US @NTMWD www.BoisdArcLake.org