Emerald Parkway Phase 8 Public Information Meeting October 27, 2010 6:30 pm to 8:00 pm Agenda Background Economic Development Impact Community Plan/Area Plan Review Project Details Questions Background Existing


slide-1
SLIDE 1

Emerald Parkway Phase 8 Public Information Meeting

October 27, 2010 6:30 pm to 8:00 pm

slide-2
SLIDE 2

Agenda

  • Background
  • Economic Development Impact
  • Community Plan/Area Plan Review
  • Project Details
  • Questions
slide-3
SLIDE 3

Background

Emerald Parkway Phase 8 Existing Emerald Parkway Existing Emerald Parkway

slide-4
SLIDE 4

Economic Development Impact

slide-5
SLIDE 5

2007 Dublin Community Plan 2007 Dublin Community Plan

Future Land Use Plan

slide-6
SLIDE 6

KEY ISSUES

  • Buffer existing residential
  • Greater open space and pedestrian connection
  • Improve traffic access/circulation
  • Preserve archaeological and natural features
  • Establish gateways into Dublin
  • Use CIP to encourage development
  • Expect high quality development

KEY ISSUES

  • Buffer existing residential
  • Greater open space and pedestrian connection
  • Improve traffic access/circulation
  • Preserve archaeological and natural features
  • Establish gateways into Dublin
  • Use CIP to encourage development
  • Expect high quality development

2007 Dublin Community Plan 2007 Dublin Community Plan

Bright Road Area Plan

PLANNING GOAL

..build upon and enhance the character of Bright Road while ensuring preservation efforts and high quality

  • ffice development that focuses on architecture and

site design that complements surrounding neighborhoods.

PLANNING GOAL

..build upon and enhance the character of Bright Road while ensuring preservation efforts and high quality

  • ffice development that focuses on architecture and

site design that complements surrounding neighborhoods.

slide-7
SLIDE 7

Bright Road Area Plan

2007 Dublin Community Plan 2007 Dublin Community Plan

Premium Office Premium Office Standard Office Standard Office Cul-de-sac Bright Rd. Cul-de-sac Bright Rd. Neighborhood Office Neighborhood Office Residential Residential Park Park Residential Residential

slide-8
SLIDE 8

I-270 N I-270 N

slide-9
SLIDE 9

Emerald Parkway – Phase 8

Emerald Parkway Phase 8 Existing Emerald Parkway Existing Emerald Parkway

slide-10
SLIDE 10

Project Details Overview

  • Multi-lane Roundabout with

brick truck apron at Bright Road intersection

  • Warm LED street lighting will

be installed

  • Medians and intersections

will be brick like existing Emerald Parkway

  • Speed limit will be 40 mph
  • Street trees will be planted
slide-11
SLIDE 11

Project Details Location

slide-12
SLIDE 12

Project Details Bright Road at Riverside Drive

For the existing intersection:

  • 12 crashes since

September 1, 2007

  • Crash rate = 0.34

(1 crash occurs for every 3 million vehicles that enter the intersection,

  • r about 1 every 3 months)
  • Severity ratio = 50%

(1 in 2 accidents results in injury)

slide-13
SLIDE 13

Project Details Utilities - Public

Sanitary sewer and waterline to be extended

slide-14
SLIDE 14

Project Details Utilities - Private

  • AEP electric will be

moved underground within the roundabout area

  • Towers were raised

in anticipation of this project

slide-15
SLIDE 15

Project Details Pedestrian & Bike Connections on Emerald Parkway

Median Right-of-Way 11’ 13’ 11’ 13’

slide-16
SLIDE 16

Project Details Pedestrian & Bike Connections to Tuller Road

slide-17
SLIDE 17

Project Details Property Acquisition

Individual meetings will be held with affected owners

slide-18
SLIDE 18

Project Details Cost & Funding

  • Programmed at

$9.5 million in the City’s 2011 – 2015 CIP Program

  • State of Ohio has

allocated $900,000

slide-19
SLIDE 19

Project Details Schedule

  • Design: 95% complete
  • Start construction: late 2011

» (depending on pace of property acquisitions)

  • Construction timeframe: 12-15 months
slide-20
SLIDE 20

Questions

Emerald Parkway Phase 8 Existing Emerald Parkway Existing Emerald Parkway