Public Information Meeting Public Information Meeting Route 15 - - PowerPoint PPT Presentation

public information meeting public information meeting
SMART_READER_LITE
LIVE PREVIEW

Public Information Meeting Public Information Meeting Route 15 - - PowerPoint PPT Presentation

Connecticut Department of Transportation State Project No. 167-108 State Project No. 167-108 Public Information Meeting Public Information Meeting Route 15 Wilbur Cross Parkway Route 15 Wilbur Cross Parkway Through West Rock Ridge Through


slide-1
SLIDE 1

Connecticut Department

  • f Transportation

Public Information Meeting Public Information Meeting

Route 15 Wilbur Cross Parkway Through West Rock Ridge

Town of Woodbridge, Town of Hamden & City of New Haven

Route 15 Wilbur Cross Parkway Through West Rock Ridge

Town of Woodbridge, Town of Hamden & City of New Haven

June 7, 2017, 7:00 PM New Haven Hall of Records 200 Orange Street, New Haven, CT

State Project No. 167-108 State Project No. 167-108

slide-2
SLIDE 2

Connecticut Department

  • f Transportation

Project Roles Project Roles

CTDOT Division of Bridges, Bridge Consultant Design Unit

  • Oversight/Liaison/Coordination of Design Consultant
  • Theodore Nezames, Manager of Bridges
  • Timothy Fields, Principal Engineer
  • David Cutler, Supervising Engineer
  • Derick Lessard, Project Engineer

CTDOT Office of Environmental Planning

  • Coordination/Review of Environmental Aspects
  • Kevin Fleming, Planner
  • Amanda Saul, Planner
  • Chris Samorajczyk, Planner
  • Scott Speal, NRS Archaeologist

CTDOT Division of Bridges, Bridge Consultant Design Unit

  • Oversight/Liaison/Coordination of Design Consultant
  • Theodore Nezames, Manager of Bridges
  • Timothy Fields, Principal Engineer
  • David Cutler, Supervising Engineer
  • Derick Lessard, Project Engineer

CTDOT Office of Environmental Planning

  • Coordination/Review of Environmental Aspects
  • Kevin Fleming, Planner
  • Amanda Saul, Planner
  • Chris Samorajczyk, Planner
  • Scott Speal, NRS Archaeologist
slide-3
SLIDE 3

Connecticut Department

  • f Transportation

Project Roles Project Roles

CTDOT Interchange 59 Project Team

  • Independent utilities and stand-alone projects
  • Continual coordination
  • Project No. 92-672
  • Scott Bushee, Supervising Engineer
  • Long-term Improvements
  • Marissa Washburn, Supervising Engineer

CTDOT Interchange 59 Project Team

  • Independent utilities and stand-alone projects
  • Continual coordination
  • Project No. 92-672
  • Scott Bushee, Supervising Engineer
  • Long-term Improvements
  • Marissa Washburn, Supervising Engineer
slide-4
SLIDE 4

Connecticut Department

  • f Transportation

Project Roles Project Roles

Federal Highway Administration (FHWA)

  • Federal Funding Anticipated
  • Review of Environmental Assessment and Design Plans
  • Timothy Snyder, Area Engineer
  • Christopher Hansen, Environmental Protection Specialist

CDM Smith

  • Retained as Design Consultant Engineer
  • Tunnel inspection and preliminary engineering report
  • Mike Egan, Principal, Project Manager
  • Dave Sousa, Public Engagement
  • Mohammad Jafari, Tunnel Designer

Federal Highway Administration (FHWA)

  • Federal Funding Anticipated
  • Review of Environmental Assessment and Design Plans
  • Timothy Snyder, Area Engineer
  • Christopher Hansen, Environmental Protection Specialist

CDM Smith

  • Retained as Design Consultant Engineer
  • Tunnel inspection and preliminary engineering report
  • Mike Egan, Principal, Project Manager
  • Dave Sousa, Public Engagement
  • Mohammad Jafari, Tunnel Designer
slide-5
SLIDE 5

Connecticut Department

  • f Transportation

Location Map Location Map

Exit 59

slide-6
SLIDE 6

Connecticut Department

  • f Transportation

Aerial View Aerial View

slide-7
SLIDE 7

Connecticut Department

  • f Transportation

Purpose of Project Purpose of Project

  • Tunnel Inspected Once per Year (Biennial and

Special Inspections)

  • Most current inspection has given the Tunnel an
  • verall rating of “Poor”
  • “Poor” rating is not an indication of an imminent

safety issue

  • Project scope to address safety, structural, and

geometric deficiencies.

  • Tunnel Inspected Once per Year (Biennial and

Special Inspections)

  • Most current inspection has given the Tunnel an
  • verall rating of “Poor”
  • “Poor” rating is not an indication of an imminent

safety issue

  • Project scope to address safety, structural, and

geometric deficiencies.

slide-8
SLIDE 8

Connecticut Department

  • f Transportation

Tunnel Description Tunnel Description

  • Opened in 1949 - Wilbur Cross Parkway
  • Eligible for Listing on State/National Historic Register
  • Only Highway Tunnel Through Natural Land Form in CT
  • Carries 70,000 vehicles per day
  • Each Barrel 1,200’ long, 28’ wide, 11’ Lanes, 6”

shoulders

  • Standards Require 12’ Lanes, 8’ left and 10’ right shoulder
  • Non-Compliance w/Tunnel Standards/Requirements
  • Geometrics, Ventilation and Emergency Systems
  • CDM Smith 2009 Inspection: Need for Rehabilitation
  • Opened in 1949 - Wilbur Cross Parkway
  • Eligible for Listing on State/National Historic Register
  • Only Highway Tunnel Through Natural Land Form in CT
  • Carries 70,000 vehicles per day
  • Each Barrel 1,200’ long, 28’ wide, 11’ Lanes, 6”

shoulders

  • Standards Require 12’ Lanes, 8’ left and 10’ right shoulder
  • Non-Compliance w/Tunnel Standards/Requirements
  • Geometrics, Ventilation and Emergency Systems
  • CDM Smith 2009 Inspection: Need for Rehabilitation
slide-9
SLIDE 9

Connecticut Department

  • f Transportation

Existing Conditions Existing Conditions

  • Significant Deterioration
  • Prior Biennial Reports
  • CDM Smith Inspection/Study
  • Peak Hour Congestion
  • Recurring Bottlenecks
  • Substandard Shoulder Widths

create emergency response constraints

  • Does not meet current standards

for electrical, mechanical or fire protection systems

  • Significant Deterioration
  • Prior Biennial Reports
  • CDM Smith Inspection/Study
  • Peak Hour Congestion
  • Recurring Bottlenecks
  • Substandard Shoulder Widths

create emergency response constraints

  • Does not meet current standards

for electrical, mechanical or fire protection systems

slide-10
SLIDE 10

Connecticut Department

  • f Transportation

Tunnels Tunnels

  • Ground Water Infiltration
  • Walls/Ceiling - Stalagmites
  • Freeze/Thaw Conditions
  • Falling Icicles
  • Cross Section Deficient
  • 28’ Existing Width
  • 50’ Required (2 Lanes)

(includes two 4’ curbs)

  • Frequent Maintenance

Requires Tunnel Closures – Shifting Traffic

  • Ground Water Infiltration
  • Walls/Ceiling - Stalagmites
  • Freeze/Thaw Conditions
  • Falling Icicles
  • Cross Section Deficient
  • 28’ Existing Width
  • 50’ Required (2 Lanes)

(includes two 4’ curbs)

  • Frequent Maintenance

Requires Tunnel Closures – Shifting Traffic

slide-11
SLIDE 11

Connecticut Department

  • f Transportation

Tunnel Walls

slide-12
SLIDE 12

Connecticut Department

  • f Transportation

Tunnel Wall Tunnel Wall

slide-13
SLIDE 13

Connecticut Department

  • f Transportation

Tunnel Wall Tunnel Wall

slide-14
SLIDE 14

Connecticut Department

  • f Transportation

Tunnel Wall

slide-15
SLIDE 15

Connecticut Department

  • f Transportation

Tunnel Ceiling Tunnel Ceiling

slide-16
SLIDE 16

Connecticut Department

  • f Transportation

Tunnel Ceilings

slide-17
SLIDE 17

Connecticut Department

  • f Transportation

Tunnel Ceiling Tunnel Ceiling

slide-18
SLIDE 18

Connecticut Department

  • f Transportation

Typical Cross Section at Steel Framing Typical Cross Section at Steel Framing

slide-19
SLIDE 19

Connecticut Department

  • f Transportation

Steel Framing (before concrete) Steel Framing (before concrete)

slide-20
SLIDE 20

Connecticut Department

  • f Transportation

Rehabilitation Report Summary Rehabilitation Report Summary

  • November 2014 Alternative

Construction Options Study and September 2016 Supplement Several Options Evaluated: Construction Methods Construction Duration Construction Schedule (Staging) Cost Traffic Impacts Construction Complexity Anticipated Useful Life

  • November 2014 Alternative

Construction Options Study and September 2016 Supplement Several Options Evaluated: Construction Methods Construction Duration Construction Schedule (Staging) Cost Traffic Impacts Construction Complexity Anticipated Useful Life

slide-21
SLIDE 21

Connecticut Department

  • f Transportation

Rehabilitation Options Rehabilitation Options

  • Rehabilitation Options Evaluated in 2014 Report:

Rehabilitation of Existing Tunnel by Complete shutdown of one barrel. Rehabilitation of Existing Tunnel by Partial shutdown

  • f one barrel.
  • Rehabilitation Options Evaluated in 2014 Report:

Rehabilitation of Existing Tunnel by Complete shutdown of one barrel. Rehabilitation of Existing Tunnel by Partial shutdown

  • f one barrel.
  • Significant Traffic Impacts During

Lane Closures

  • Geometrics Not Correctable Within

Existing Tunnel Widths

  • Structural Integrity of Tunnels
  • Ground Water Infiltration
  • Significant Traffic Impacts During

Lane Closures

  • Geometrics Not Correctable Within

Existing Tunnel Widths

  • Structural Integrity of Tunnels
  • Ground Water Infiltration
slide-22
SLIDE 22

Connecticut Department

  • f Transportation

Reconstruction Options Reconstruction Options

  • Reconstruction Options Evaluated in 2014 Report

and 2016 Supplement:

New One Lane Tunnel, Rehabilitate Existing Tunnels. New Two Lane Tunnel, Rehabilitate Existing Tunnels. Enlarge Existing Tunnels, while maintaining traffic, using Protective Shield. Construct a Temporary Bypass Tunnel, then Enlarge Existing Tunnels.

The 2014 Report and 2016 Supplement presents combinations of construction sequencing scenarios to assess traffic impacts and future level of service. Reconstruction can provide additional service life and meet future traffic flow capacity

  • Reconstruction Options Evaluated in 2014 Report

and 2016 Supplement:

New One Lane Tunnel, Rehabilitate Existing Tunnels. New Two Lane Tunnel, Rehabilitate Existing Tunnels. Enlarge Existing Tunnels, while maintaining traffic, using Protective Shield. Construct a Temporary Bypass Tunnel, then Enlarge Existing Tunnels.

The 2014 Report and 2016 Supplement presents combinations of construction sequencing scenarios to assess traffic impacts and future level of service. Reconstruction can provide additional service life and meet future traffic flow capacity

slide-23
SLIDE 23

Connecticut Department

  • f Transportation

New/Reconstructed Tunnel Barrel New/Reconstructed Tunnel Barrel

  • Two Lane Tunnel Cross Section
slide-24
SLIDE 24

Connecticut Department

  • f Transportation

Existing Environmental Resources Existing Environmental Resources

Natural Diversity Area Forested Woodland Wintergreen Brook Nature Center

slide-25
SLIDE 25

Connecticut Department

  • f Transportation

Environmental Document/Process Environmental Document/Process

  • Prepare Environmental Document
  • Alternative Analysis Including No Build
  • NEPA/CEPA* Processes
  • Potential Environmental

Impacts of All Alternatives

  • Public Outreach
  • Preliminary Design
  • Preferred Alternative
  • Construction Staging Impacts
  • Prepare Environmental Document
  • Alternative Analysis Including No Build
  • NEPA/CEPA* Processes
  • Potential Environmental

Impacts of All Alternatives

  • Public Outreach
  • Preliminary Design
  • Preferred Alternative
  • Construction Staging Impacts

*National Environmental Policy Act / Connecticut Environmental Policy Act

slide-26
SLIDE 26

Connecticut Department

  • f Transportation

Environmental NEPA/CEPA Tasks Environmental NEPA/CEPA Tasks

  • Prepare Environmental Assessment (EA)/ Environmental

Impact Evaluation (EIE)

Establish Purpose and Need Statement Conduct Field Studies Evaluate Alternatives Consider Construction/ Post-Construction Impacts

  • Consider Sensitive Resources:

West Rock Nature Center (City) Wintergreen Brook West Rock Ridge State Park Historic Designation

  • Prepare Environmental Assessment (EA)/ Environmental

Impact Evaluation (EIE)

Establish Purpose and Need Statement Conduct Field Studies Evaluate Alternatives Consider Construction/ Post-Construction Impacts

  • Consider Sensitive Resources:

West Rock Nature Center (City) Wintergreen Brook West Rock Ridge State Park Historic Designation

slide-27
SLIDE 27

Connecticut Department

  • f Transportation

Environmental NEPA/CEPA* Environmental NEPA/CEPA*

Air quality Water quality Noise Groundwater Wetlands, water bodies and floodplains Archaeological/Cultural resources Recreational Resources Natural communities, including endangered animal and plant species Aesthetics Traffic Air quality Water quality Noise Groundwater Wetlands, water bodies and floodplains Archaeological/Cultural resources Recreational Resources Natural communities, including endangered animal and plant species Aesthetics Traffic

*National Environmental Policy Act / Connecticut Environmental Policy Act

slide-28
SLIDE 28

Connecticut Department

  • f Transportation

Public Involvement Public Involvement

Includes:

  • Identification and Engagement of

Stakeholders

  • Project Website and Social Media
  • Email Bulletins to

Interested Citizens and Community Groups

Includes:

  • Identification and Engagement of

Stakeholders

  • Project Website and Social Media
  • Email Bulletins to

Interested Citizens and Community Groups

slide-29
SLIDE 29

Connecticut Department

  • f Transportation

Public Involvement Public Involvement

Includes Various Meetings:

  • Outreach Events (Pop-Ups)
  • Informational Meetings or

Open Houses

  • Formal Public Meeting(s)

Includes Various Meetings:

  • Outreach Events (Pop-Ups)
  • Informational Meetings or

Open Houses

  • Formal Public Meeting(s)
slide-30
SLIDE 30

Connecticut Department

  • f Transportation

Potential Stakeholders Potential Stakeholders

Large Employers/ Business Orgs:

  • Southern CT State University
  • Sikorsky
  • Yale University
  • Greater New Haven Chamber of

Commerce

  • REX Regional Economic Xcelleration
  • Yale-New Haven Hospital

Large Employers/ Business Orgs:

  • Southern CT State University
  • Sikorsky
  • Yale University
  • Greater New Haven Chamber of

Commerce

  • REX Regional Economic Xcelleration
  • Yale-New Haven Hospital

Governmental:

  • Elected Officials (Local, State &

Federal)

  • South Central Council of Gov’ts
  • CT Dept. of Energy & Environmental

Protection

  • Federal Highway Administration
  • U.S. Environmental Protection Agency

Governmental:

  • Elected Officials (Local, State &

Federal)

  • South Central Council of Gov’ts
  • CT Dept. of Energy & Environmental

Protection

  • Federal Highway Administration
  • U.S. Environmental Protection Agency

Non-Profit Orgs:

  • CT Association for

Community Transportation

  • AAA of Southern New

England

  • CT Coalition for

Environmental Justice

  • CT Fund for the

Environment

  • Economic

Development Corp. of New Haven

  • CT Technology Council
  • New Haven Urban

Design League

  • Elm City Cycling
  • CT Business &

Industry Association

Non-Profit Orgs:

  • CT Association for

Community Transportation

  • AAA of Southern New

England

  • CT Coalition for

Environmental Justice

  • CT Fund for the

Environment

  • Economic

Development Corp. of New Haven

  • CT Technology Council
  • New Haven Urban

Design League

  • Elm City Cycling
  • CT Business &

Industry Association

Municipalities:

  • Town of

Woodbridge

  • Town of Hamden
  • City of New

Haven

Municipalities:

  • Town of

Woodbridge

  • Town of Hamden
  • City of New

Haven

Transportation Providers:

  • CT Transit
  • Greater New

Haven Transit District

  • CT Rides
  • CTDOT

Transportation Providers:

  • CT Transit
  • Greater New

Haven Transit District

  • CT Rides
  • CTDOT
slide-31
SLIDE 31

Connecticut Department

  • f Transportation

Next Steps Next Steps

  • Early Field Work: Next 6-9 months
  • Topographical Survey
  • Endangered Species Survey
  • Archaeological Survey
  • NEPA/CEPA Document Studies: Next 18 months
  • Alternative Analysis
  • Environmental Assessment/Environmental Impact Evaluation
  • Preliminary Design: After NEPA/CEPA
  • Advance preferred alternative to 30% Design Level
  • Early Field Work: Next 6-9 months
  • Topographical Survey
  • Endangered Species Survey
  • Archaeological Survey
  • NEPA/CEPA Document Studies: Next 18 months
  • Alternative Analysis
  • Environmental Assessment/Environmental Impact Evaluation
  • Preliminary Design: After NEPA/CEPA
  • Advance preferred alternative to 30% Design Level
slide-32
SLIDE 32

Connecticut Department

  • f Transportation

THANK YOU! THANK YOU!

Project Contact Information:

  • Mr. David A. Cutler, P.E.

Transportation Supervising Engineer

Connecticut Department of Transportation Bureau of Engineering and Construction 2800 Berlin Turnpike, Newington, CT 06131 860-594-3210 David.Cutler@ct.gov

Project Website:

http://www.ct.gov/dot/heroes-tunnel

Project Contact Information:

  • Mr. David A. Cutler, P.E.

Transportation Supervising Engineer

Connecticut Department of Transportation Bureau of Engineering and Construction 2800 Berlin Turnpike, Newington, CT 06131 860-594-3210 David.Cutler@ct.gov

Project Website:

http://www.ct.gov/dot/heroes-tunnel