manhattan community board 11 manhattan community board 11
play

Manhattan Community Board #11 Manhattan Community Board #11 East - PowerPoint PPT Presentation

2 2 nd Avenue Subw ay Projec t Presentation to Manhattan Community Board #11 Manhattan Community Board #11 East Harlem February 7 th , 2012 Presentation Contents Project Overview Project Personnel Project


  1. 2 2 nd Avenue Subw ay Projec t Presentation to Manhattan Community Board #11 Manhattan Community Board #11 East Harlem February 7 th , 2012

  2. Presentation Contents � � Project Overview � Project Personnel � � Project Progress & Updates � � � Construction Progress Photos � � Upcoming Work – next 6 months � Stage 5 Work – east side of 2 nd Avenue � Stage 5 Work – east side of 2 Avenue � � Staging Work at Metropolitan Hospital Center � � Bus Stops � � Questions

  3. PROJECT OVERVIEW 96 th Street 92 nd Street 93 rd Street 94 th Street 95 th Street 97 th Street Entrance 1 Ancillary 2 Entrance 3 TBM Launc h Box (Cont rac t 1) Entrance 2 Existing Tunnel Connection Cont rac t 2A: Sit e Work and Heavy Civil Ancillary 1 Contract 2A: 96th Street Station - Site Work & Heavy Civil

  4. PROJECT PERSONNEL � � Project Personnel � � Owner – MTA Capital Construction � � Consultant Construction Manager - Parsons Brinkerhoff � � General Contractor - E.E. Cruz/Tully Construction Co., A JV � � Community Relations – MTA Government Community Relations

  5. PROGRESS AND UPDATES � � Completed Work Majority of all Utility relocation work north of 95 th Street : � � Gas, Electric, Water, Sewer, Telephone � � Slurry Walls along west side of Second Avenue & Entrance #3 (Rite Aid Store) � � Ancillary #2 Secant Piles (Former Century Lumber) � � Building stabilization (grouting and structural work) between Building stabilization (grouting and structural work) between 96 th to 97 th Streets (Don Pedro’s to Subway) � � Secant Piles and jet grouting for tie-in to existing subway tunnel at 99 th Street (opposite MHC) Traffic decking from 95 th to 99 th Streets (95%) � � Shifted traffic to west side of 2 nd Avenue north of 97 th Street � �

  6. PROGRESS AND UPDATES � Ongoing Work � � � Jet Grout Blocks at Ancillary #2 & Entrance #3 and Jet Grout strut at Ancillary #2 Decking of the intersections at 96 th and 97 th Streets west side of � � Second Avenue � � Utility relocation work at Entrances #1 & #2 (west and east of Utility relocation work at Entrances #1 & #2 (west and east of 2 nd Avenue at 94 th Street) Secant pile installation at Ancillary #1 (NE corner of 93 rd Street) � �

  7. CONSTRUCTION PROGRESS: Slurry Wall Construction Excavation of Slurry Wall Trench – Installation of Steel Reinforcement West Side Cage for Slurry Wall – West Side

  8. CONSTRUCTION PROGRESS: 2 nd Ave & 97 th St Steel Deck Beam & Concrete Decking Installation – West Side

  9. CONSTRUCTION PROGRESS: 2 nd Ave & 97 th St Installation of Jet Grout Blocks Ancillary # 2 (Former Century Lumber)

  10. CONSTRUCTION PROGRESS: 2 nd Ave & 96 th St Steel Deck Beam Installation – West Side

  11. PROGRESS AND UPDATES � Upcoming Work (Next 6 Months) � Complete Installation of Decking along west side of 2 nd Avenue � � Relocate Work Zones to east side of 2 nd Avenue (traffic to west � � side) Rebar Cage Assembly – 99 th to 101 st Streets Rebar Cage Assembly – 99 th to 101 st Streets � � � � Continue Secant Pile Installation at Ancillary # 1 � � Slurry Wall Construction at Entrances # 1 & # 2 � � Secant Pile Installation at east side tie-in to existing tunnel Slurry Wall Construction along east side of 2 nd Avenue � � Restore bus stop to 97 th Street � �

  12. CURRENT WORK STAGE STAGE 5 Rebar Steel Assembly Area • Fabricate reinforcement steel cages for Slurry Wall Construction • Install Secant Piles for tie in connection to existing subway tunnel

  13. CURRENT WORK STAGE STAGE 5 Ancillary # 2 • Slurry Wall Construction along east side of Second Avenue

  14. MHC – ENTRANCE AND EXIT CLOSURES STAGE 5 – SLURRY WALL WORK Ancillary # 2 Closure of Entrance • Slurry Wall Construction in front of Metropolitan Hospital Center will require the closure of the entrance or exit of Metropolitan Hospital.

  15. MHC – ENTRANCE AND EXIT CLOSURES STAGE 5 – SLURRY WALL WORK Ancillary # 2 Closure of Exit • Slurry Wall Construction in front of Metropolitan Hospital Center will require the closure of the entrance or exit of Metropolitan Hospital.

  16. CONSTRUCTION PROGRESS: Bus St ops (J anuar y 2012) BUS STOP KEY CURRENT M15 STOP M15 ROUTE PROPOSED BUS STOP M15 STOP RELOCATION M15 ROUTE M15 ROUTE CURRENT M96 STOP M96 ROUTE CURRENT SBS STOP SBS ROUTE

  17. 2 2 nd Avenue Subw ay Projec t Questions ? Questions ?

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend