I-84 Mainline Crosses RR Twice Why I-84 was elevated when - - PowerPoint PPT Presentation
I-84 Mainline Crosses RR Twice Why I-84 was elevated when - - PowerPoint PPT Presentation
I-84 Mainline Crosses RR Twice Why I-84 was elevated when constructed in 1960s Currently 80% of highway is elevated (30 acres) Orange = elevated or structure Mainline Alternatives Alternative 1: No-Build Green Alternative 2
I-84 Mainline Crosses RR Twice
Why I-84 was elevated when constructed in 1960s
Currently 80% of highway is elevated (30 acres)
Orange = elevated or structure
Mainline Alternatives
- Alternative 1: No-Build
Green
- Alternative 2 (elevated)
Blue
- Alternative 3 (lowered)
Yellow
- Alternative 4 (tunnel)
Brown
Cost in $ Billions
Probabilistic Cost Estimate Ranges
Alternatives
$- $2.0 $4.0 $6.0 $8.0 $10.0 $12.0 $14.0
No-Build Elevated Highway Lowered Highway Tunneled Highway $3.1 $2.5 $12.1 $9.7 $5.3 $4.3 $6.2 $4.9
August 2015
Based on risk based cost analyses
Cost Range and Project Status
Estimated Project Cost
Planning 30% Design 100% Design Construction Management Initial Probabilistic Range Significant Risks Realized Few Risks Realized Currently at 5-10%
Lowered Highway
Preliminary Estimated Program Costs
(Lowered Highway)
- Hard Costs
Approx.
- Construction
$ 1.5 b
- Utilities
100 m 1.6 b
- Soft Costs
- Program Management
50 m
- Design Engineering
120 m
- Construction Engineering
230 m
- Property Acquisition
180 m 0.6 b
- Escalation
1.5 b
- Risk Costs
0.6 – 1.6 b
Total 4.3 – 5.3 b
Major Cost Elements (Lowered Hwy)
- Freeway & ramps
- Extensive local roads (new & reconstructed)
- Bridges
- Viaduct demolition
- Construction staging
- Traffic control
- Railroad relocation (not a typical project cost)
- Utility relocations
- Cost escalation on all elements
expensive in downtown area
Existing Conditions (West)
N
Existing I-84 Mainline Exit 46: Sisson Ave. Exit 47: Sigourney St. N
Existing Mainline and Ramps (West)
Subject to changed based upon ongoing analysis and design
Preliminary
Option W3-3
Proposed Roadway Layout
N
East Coast Greenway
Subject to changed based upon ongoing analysis and design
CONCEPTUAL - FOR ILLUSTRATIVE PURPOSES ONLY
N
Option W3-3
Potential Complete Streets
Existing Conditions (East)
N
Exit 49: High St. Exit 50: Trumbull St. Exit 48A: Capitol Ave. Exit 48B: Asylum St. Exit 48: Asylum Ave. Exit 47: Sigourney St. N
Existing Mainline and Ramps (East)
N
Existing Railroad (East)
Relocated Railroad Station Annex Preliminary
Subject to change based upon ongoing analysis and design
N
Relocated Railroad and New Station Annex
Preliminary
Subject to change based upon ongoing analysis and design
N
Option 3B: E2(S)
Proposed Roadway Layout
East Coast Greenway
Subject to changed based upon ongoing analysis and design.
CONCEPTUAL - FOR ILLUSTRATIVE PURPOSES ONLY
Exploring Flower St. Reconnection
N
Option 3B: E2(S)
Potential Complete Streets
Preliminary
Subject to change based upon ongoing analysis and design
N
Lowered Options W3-3 & 3B E2(S) shows extensive reconnections & modification needed on local road network