i 84 mainline crosses rr twice
play

I-84 Mainline Crosses RR Twice Why I-84 was elevated when - PowerPoint PPT Presentation

I-84 Mainline Crosses RR Twice Why I-84 was elevated when constructed in 1960s Currently 80% of highway is elevated (30 acres) Orange = elevated or structure Mainline Alternatives Alternative 1: No-Build Green Alternative 2


  1. I-84 Mainline Crosses RR Twice Why I-84 was elevated when constructed in 1960s

  2. Currently 80% of highway is elevated (30 acres) Orange = elevated or structure

  3. Mainline Alternatives  Alternative 1: No-Build Green  Alternative 2 (elevated) Blue  Alternative 3 (lowered) Yellow  Alternative 4 (tunnel) Brown

  4. Probabilistic Cost Estimate Ranges Based on risk based cost analyses $14.0 $12.1 $12.0 $10.0 Cost in $ Billions $9.7 $8.0 $6.2 $6.0 $5.3 $4.9 $4.0 $3.1 $4.3 $2.0 $2.5 $- No-Build Elevated Lowered Tunneled Highway Highway Highway Alternatives August 2015

  5. Cost Range and Project Status Initial Probabilistic Range Estimated Project Cost Significant Risks Realized Few Risks Realized Currently at 5-10% Planning 30% Design 100% Design Construction Management

  6. Lowered Highway

  7. Preliminary Estimated Program Costs (Lowered Highway) • Approx. Hard Costs • Construction $ 1.5 b • Utilities 100 m 1.6 b • Soft Costs • Program Management 50 m • Design Engineering 120 m • Construction Engineering 230 m • Property Acquisition 180 m 0.6 b • Escalation 1.5 b • 0.6 – 1.6 b Risk Costs 4.3 – 5.3 b Total

  8. Major Cost Elements (Lowered Hwy) • Freeway & ramps • Extensive local roads (new & reconstructed) • Bridges • Viaduct demolition • Construction staging • Traffic control expensive in downtown area • Railroad relocation (not a typical project cost) • Utility relocations • Cost escalation on all elements

  9. N Existing Conditions (West)

  10. N Existing Mainline and Ramps (West) Exit 47: Sigourney St. Exit 46: Sisson Ave. Existing I-84 Mainline

  11. N Option W3-3 Proposed Roadway Layout Preliminary Subject to changed based upon ongoing analysis and design

  12. N Option W3-3 Potential Complete Streets East Coast Greenway CONCEPTUAL - FOR ILLUSTRATIVE PURPOSES ONLY Subject to changed based upon ongoing analysis and design

  13. Existing Conditions (East) N

  14. N Existing Mainline and Ramps (East) Exit 49: High St. Exit 48: Exit 50: Trumbull St. Asylum Ave. Exit 48B: Asylum St. Exit 48A: Capitol Ave. Exit 47: Sigourney St.

  15. N Existing Railroad (East)

  16. N Relocated Railroad and New Station Annex Station Annex Relocated Railroad Preliminary Subject to change based upon ongoing analysis and design

  17. N Option 3B: E2(S) Proposed Roadway Layout Preliminary Subject to change based upon ongoing analysis and design

  18. N Option 3B: E2(S) Potential Complete Streets Exploring Flower St. Reconnection East Coast Greenway CONCEPTUAL - FOR ILLUSTRATIVE PURPOSES ONLY Subject to changed based upon ongoing analysis and design.

  19. N Lowered Options W3-3 & 3B E2(S) shows extensive reconnections & modification needed on local road network Preliminary Subject to change based upon ongoing analysis and design

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend