NORTHBOUND NORTHWESTERN HWY SERVICE DRIVE ROAD REHABILITATION SOUTHFIELD RD TO LAHSER RD March 26, 2018 PROJECT LIMITS EAST OF LAHSER RD WEST OF SOUTHIELD RD NB NORTHWESTERN HWY SERVICE DRIVE Overview Concrete patching with asphalt
SLIDE 2
SLIDE 3
NB NORTHWESTERN HWY SERVICE DRIVE
Overview
- Concrete patching with asphalt overlay
- Reconstruction of the following intersections
- Mt
Vernon and NB Northwestern Hwy Service Drive
- Evergreen Rd and NB Northwestern Hwy Service Drive
- NB Northestern Hwy Service Drive north of Civic Center Dr
- New traffic signals at:
- Mt
Vernon St
- Evergreen Rd (mast arms)
- Civic Center Dr
- Bike lane between Mt
Vernon and Civic Center
- Sidewalk and driveway improvements
- One to two lanes traffic maintained throughout construction
- Funding from both Federal ($1.74M) & City’s Road Bond Construction fund ($5.84M) w/ CCAB $50k
SLIDE 4
NB NORTHWESTERN HWY SERVICE DRIVE REHABILITATION
Sidewalk Improvements
10 MILE EVERGREEN SIDEWALK TO MT VERNON BRIDGE SIDEWALK CROSSING 10 MILE BRIDGE SIDEWALK CROSSING EVERGREEN BRIDGE FILL SIDEWALK GAP
SLIDE 5
NB NORTHWESTERN HWY SERVICE DRIVE REHABILITATION
Sidewalk Improvements
FILL SIDEWALK GAP
2000 TOWN CENTER 25800 NORTHWESTERN
SLIDE 6
NB NORTHWESTERN HWY SERVICE DRIVE REHABILITATION
Sidewalk Improvements
CONTINUE NEW 10’ PATHWAY FROM THE SOUTH TO LAHSER CORPORATE DR LAHSER RD
SLIDE 7