SLIDE 1 NORTH FERRY STREET PUMP STATION PROJECT
March 1, 2017
STOCKADE ASSOCIATION BOARD PRESENTATION
SLIDE 2 Presentation Outline
Summary of the Advisory Committee Workshops
- Overview of the City’s Wastewater System
- History of Regulatory Challenges
- Order on Consent Requirements
- Key Project Considerations
- Pump Station Layout within the Park
- Preliminary Renderings of the Pump Station
- Next Steps
SLIDE 3
SLIDE 4
SLIDE 5
SLIDE 6
SLIDE 7
- 2005: DEC required that the City “characterize” the
performance of the wastewater system
- 2005: An Order on Consent required the City to assess
inflow and infiltration which resulted in a 5-Year CIP
‒ Central State Street Neighborhood ‒ Hamilton Hill and Vale Village Neighborhoods ‒ Mt. Pleasant Neighborhood ‒ Downtown Business District
- 2013: Re-classification of the Alco Regulator from a
CSO to SSO
- 2014: New Order on Consent for SSO Abatement
History of Regulatory Challenges
Timeline Summary
SLIDE 8
SLIDE 9
SLIDE 10 Insert Figure of Flood Levels within the Stockade illustrating Existing Pump Station
“Hardening” of the Pump Station
Protection of Critical Equipment and Continuous Operations
Mohawk River elevations shown at 100-year flood levels
SLIDE 11 Key Project Design Considerations
- Pump Station needs to be “hardened” to
protect critical equipment and ensure
- perations during flood events
- Maintain continuous operation of the
pump station during construction
- Incorporate flexibility in the design to
accept additional flows from City development, Rotterdam and Scotia
- Ensure sufficient pumping and wet well
capacity to deliver flows to the WRRF to enable the SSO Abatement
- Building and landscape architectural
elements need to be matched to the character of the historic neighborhood
SLIDE 12 Insert Figure of Arial of Riverside Park with Potential PS Sites
Preliminary Site Selection Discussion
SLIDE 13
Pump Station Layout
Viewsheds and Access
SLIDE 14
Pump Station Renderings
Architectural Elements and Treatments
SLIDE 15
Pump Station Renderings
Architectural Elements and Treatments
SLIDE 16
Pump Station Renderings
Architectural Elements and Treatments
SLIDE 17
Pump Station Renderings
Architectural Elements and Treatments
SLIDE 18
Pump Station Renderings
Architectural Elements and Treatments
SLIDE 19
Pump Station
Plantings and Screening
SLIDE 20 Project Advisory Committee
Influenced Decisions and/or Recommendations
- New facility to be located to the west of the existing pump
station to preserve critical green space areas
- Building was “re-conceptualized” and site grading approach
has been modified to minimize the fill limits and disturbances
- Architecture has been modified to reflect more modern
aesthetics and treatments
- Proposed “dry-dock” to protect the backup power generator
- Minimization of impacts to “viewsheds”
‒ Consideration of placement relative to adjacent properties ‒ Set-back distance from the river walkways ‒ Screening and plantings, including use of the existing visual barrier created by Governor Yate’s brick garden wall
- Proposed access to the pump station from Governors Lane
‒ Limits paved surfaces and preserves green space ‒ Minimizes impacts to primary park entrance
SLIDE 21 Next Steps
- Presentation of the Project to the Stockade Association and
broader general public audience
- Targeted date for completion of plans and specifications by
December 2017
- Targeted date for the completion of construction by
December 2019
SLIDE 22
Final Questions or Comments
SLIDE 23
Additional Slides
SLIDE 24
Possible Architectural Wall Materials
SLIDE 25
Screening Landscape Options