NORTH FERRY STREET PUMP STATION PROJECT STOCKADE ASSOCIATION BOARD - - PowerPoint PPT Presentation

north ferry street pump station project
SMART_READER_LITE
LIVE PREVIEW

NORTH FERRY STREET PUMP STATION PROJECT STOCKADE ASSOCIATION BOARD - - PowerPoint PPT Presentation

NORTH FERRY STREET PUMP STATION PROJECT STOCKADE ASSOCIATION BOARD PRESENTATION March 1, 2017 Presentation Outline Summary of the Advisory Committee Workshops Overview of the Citys Wastewater System History of Regulatory Challenges


slide-1
SLIDE 1

NORTH FERRY STREET PUMP STATION PROJECT

March 1, 2017

STOCKADE ASSOCIATION BOARD PRESENTATION

slide-2
SLIDE 2

Presentation Outline

Summary of the Advisory Committee Workshops

  • Overview of the City’s Wastewater System
  • History of Regulatory Challenges
  • Order on Consent Requirements
  • Key Project Considerations
  • Pump Station Layout within the Park
  • Preliminary Renderings of the Pump Station
  • Next Steps
slide-3
SLIDE 3
slide-4
SLIDE 4
slide-5
SLIDE 5
slide-6
SLIDE 6
slide-7
SLIDE 7
  • 2005: DEC required that the City “characterize” the

performance of the wastewater system

  • 2005: An Order on Consent required the City to assess

inflow and infiltration which resulted in a 5-Year CIP

‒ Central State Street Neighborhood ‒ Hamilton Hill and Vale Village Neighborhoods ‒ Mt. Pleasant Neighborhood ‒ Downtown Business District

  • 2013: Re-classification of the Alco Regulator from a

CSO to SSO

  • 2014: New Order on Consent for SSO Abatement

History of Regulatory Challenges

Timeline Summary

slide-8
SLIDE 8
slide-9
SLIDE 9
slide-10
SLIDE 10

Insert Figure of Flood Levels within the Stockade illustrating Existing Pump Station

“Hardening” of the Pump Station

Protection of Critical Equipment and Continuous Operations

Mohawk River elevations shown at 100-year flood levels

slide-11
SLIDE 11

Key Project Design Considerations

  • Pump Station needs to be “hardened” to

protect critical equipment and ensure

  • perations during flood events
  • Maintain continuous operation of the

pump station during construction

  • Incorporate flexibility in the design to

accept additional flows from City development, Rotterdam and Scotia

  • Ensure sufficient pumping and wet well

capacity to deliver flows to the WRRF to enable the SSO Abatement

  • Building and landscape architectural

elements need to be matched to the character of the historic neighborhood

slide-12
SLIDE 12

Insert Figure of Arial of Riverside Park with Potential PS Sites

Preliminary Site Selection Discussion

slide-13
SLIDE 13

Pump Station Layout

Viewsheds and Access

slide-14
SLIDE 14

Pump Station Renderings

Architectural Elements and Treatments

slide-15
SLIDE 15

Pump Station Renderings

Architectural Elements and Treatments

slide-16
SLIDE 16

Pump Station Renderings

Architectural Elements and Treatments

slide-17
SLIDE 17

Pump Station Renderings

Architectural Elements and Treatments

slide-18
SLIDE 18

Pump Station Renderings

Architectural Elements and Treatments

slide-19
SLIDE 19

Pump Station

Plantings and Screening

slide-20
SLIDE 20

Project Advisory Committee

Influenced Decisions and/or Recommendations

  • New facility to be located to the west of the existing pump

station to preserve critical green space areas

  • Building was “re-conceptualized” and site grading approach

has been modified to minimize the fill limits and disturbances

  • Architecture has been modified to reflect more modern

aesthetics and treatments

  • Proposed “dry-dock” to protect the backup power generator
  • Minimization of impacts to “viewsheds”

‒ Consideration of placement relative to adjacent properties ‒ Set-back distance from the river walkways ‒ Screening and plantings, including use of the existing visual barrier created by Governor Yate’s brick garden wall

  • Proposed access to the pump station from Governors Lane

‒ Limits paved surfaces and preserves green space ‒ Minimizes impacts to primary park entrance

slide-21
SLIDE 21

Next Steps

  • Presentation of the Project to the Stockade Association and

broader general public audience

  • Targeted date for completion of plans and specifications by

December 2017

  • Targeted date for the completion of construction by

December 2019

slide-22
SLIDE 22

Final Questions or Comments

slide-23
SLIDE 23

Additional Slides

slide-24
SLIDE 24

Possible Architectural Wall Materials

slide-25
SLIDE 25

Screening Landscape Options