levin pump station and wastewater rising main contract
play

Levin Pump Station and Wastewater Rising Main Contract Project - PowerPoint PPT Presentation

Levin Pump Station and Wastewater Rising Main Contract Project Overview Construction of : New Pump Station at Levin Wastewater Treatment Plant Control Building Laying of 7km of 560 dia PE pipeline 22 Air valve Structures


  1. Levin Pump Station and Wastewater Rising Main Contract

  2. Project Overview Construction of : • New Pump Station at Levin Wastewater Treatment Plant • Control Building • Laying of 7km of 560 dia PE pipeline • 22 Air valve Structures • Outlet manhole in pond

  3. Job Location

  4. Machinery Used

  5. Labour Force LABOUR FORCE Hawkins Infrastructure: Project Manager, Construction Manager, Site Manager, Quantity Surveyor. Subcontractors included: Drainage – Higgins Levin PE Welding and Testing – City Care Pump Station Civil Works – Bailey Civil Pump Station Mechanical and Electrical – Max Tarr Stream Crossing – GP Friel Directional Drilling – Universal Underground

  6. SITE CONDITIONS WEATHER CONDITIONS Very wet weather and storm events May, June and July, The remainder of the project timeline the weather was fairly good. SITE ACCESS, LOCATION EASY OR DIFFICULT Of the 7km of pipeline, 6km was either on the road shoulder (of a country road) or in the laneway. Many issues with traffic management and the need for constant Hawkins Site Manager attention. GROUND CONDITIONS Varied greatly both vertically and along the alignment. Some sections were clean dune sand which made for unstable trenches for which shields were required over 1.5m deep.

  7. SITE CONDITIONS .

  8. Innovative Ideas Used

  9. Human Relations HEALTH AND SAFETY ISSUES Need to improve local sub-contractors understanding of HSE requirements onsite. Ensure that Method plans and risk analysis being followed onsite. Improvements were identified and immediately put in place. HSE attitude was turned around quickly EMPLOYEE TRAINING GIVEN The pipe manufacturer, IPLEX provided a Powerpoint presentation and practical training of how to handle, store, transport and joint PE pipe. They also frequented site to ensure there were no major issues and provide support where necessary. ANY SUBCONTRACTOR ISSUES A lack of experience in large scale drainage and the ability to troubleshoot problems.

  10. Arawhata Stream Crossing The biggest challenge on the project Originally this section of pipeline was intended to be directional drilled Open cutting through the stream in the middle of winter

  11. Was the Job on Time Mutual extension of one month to 20 August Practical completion 13 October Was the Job on Budget Completed within Council’s Budget Variations 39 variations - most minor design changes

  12. Any Questions ?

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend