NEXT RAT m eeting W ednesday 2 3 .0 5 0 8 :3 0 in 9 3 6 / R-0 - - PDF document

next rat m eeting w ednesday 2 3 0 5 0 8 3 0 in 9 3 6 r 0
SMART_READER_LITE
LIVE PREVIEW

NEXT RAT m eeting W ednesday 2 3 .0 5 0 8 :3 0 in 9 3 6 / R-0 - - PDF document

W ARM MAGNETS COMMI SSI ONI NG POI NT 8 HARDWARE COMMISSIONING COORDINATION NEXT RAT m eeting W ednesday 2 3 .0 5 0 8 :3 0 in 9 3 6 / R-0 3 5 May 1 0 th , 2 0 0 7 Present: Maria Paz Casas Lino, Michel Condemine, Pierre


slide-1
SLIDE 1

W ARM MAGNETS COMMI SSI ONI NG POI NT 8

HARDWARE COMMISSIONING COORDINATION

♦ ♦ ♦

NEXT RAT m eeting W ednesday 2 3 .0 5 0 8 :3 0 in 9 3 6 / R-0 3 5

♦ ♦ ♦

May 1 0 th, 2 0 0 7

Present: Maria Paz Casas Lino, Michel Condemine, Pierre Dahlen, Carlos Fernández, Nicolas Gilbert, Jacky Mazet, Ivan Moya, David Smekens, Hugues Thiesen, Jan Uythoven. Point 8 – Contact HCC person: María Paz Casas Lino / I ván Moya 1 . Status of non conform ities and actions to be taken:

  • Polarity test non conformities in the following circuits: (RMSI.R8B2;

RQID.87900; RQID.88100; RQIF.87800: RQIF.88000 )

  • Solved (Condamine)
  • Large inductive loops in MSI and some quadripoles and in MBIAH.
  • Solved (Condamine)
  • 8h run non conformity RBXWSH.L8: An intervention of TS/ CV is

required to balance the cooling circuit. Nominal flow rate 20 l/ min. (EDMS: 829411)

  • Maria Paz Casas will contact TS/ CV
  • Power converter: MQIF87800 (3e-4 ripple).
  • It is agreed between AB/ PO (Hugues) and AB/ BT (Jan) that this

non conformity will be fixed during the tests. 2 . Modifications to be done before starting the tests:

  • Adjustment of TI8 functions. It is required by AB/ PO to have the

functions adjusted already at the beginning of the tests.

slide-2
SLIDE 2
  • Jan will contact Roger Genand to have the shape of the

functions specified in detail and to the person in charge of implementing these modifications. 3 . Program m e to finish the w arm m agnets com m issioning steps:

  • WELQA,WIC, SETUP of PC already completed in the previous

tests

  • Polarity test to be done in all the warm magnets TI2 LHC
  • 24h run to be done at I Injection

4 . I nterferences found at the com pensator m agnets

  • Description of the interferences and conditions during the

previous tests (summarized in the presentation below).

  • Programme to evaluate and solve the interferences (see

presentation below)

  • 1. Evaluation of the interferences:
  • I. Turn on ALL the PC of the warm magnets of TI8 (1st

evaluation)

  • II. Turn off the PC on the 1 8 kV line. (2nd evaluation)
  • III. Conclusions
  • 2. Solution implementation
  • 3. Solution validation

5 . Tim e requirem ent and planning

  • See presentation below. Note that after the meeting the

planning has been modified due to installation constraints. Activities start on Wednesday 23rd May instead of Monday 21st May 6 . Access restrictions

  • Warm magnets: Two panels will be placed close to the two

access points from the UA27 to the RA27 preventing the access to the warm magnets in between but not to the rest of the RA87 and to the inner triplet. For the accessible warm magnets, signalization and flashing lights will be put in place.

  • Power converters: Fencing, signalization and flashing light.

Maria Paz Casas Lino for the Hardw are Com m issioning Coordination

slide-3
SLIDE 3

WARM MAGNETS COMMISSIONING POINT 8 II

10/05/2007 TS/HDO

Agenda:

  • 1. Non conformities to be solved and improvements to be done

before starting the test.

  • 2. Procedure to follow to finish the commissioning and to assess the

reason and solution for the interferences found.

  • 3. Planning and resources.
  • 4. Security issues.
slide-4
SLIDE 4

2

GROUPS INVOLVED

AB/PO (Hugues Thiesen / Roger Genand/ Stephen Riegner) AT/MEL (Mikko Karppinen / David Smekens / Jacky Mazet) AB/CO (Pierre Dahlen) TS/EL (Jean Claude Guillaume / Michel Condamine / Baptiste Lebeau) AB/BT (Jan Uythoven) AB/ABP (Nicolas Gilbert) AB/OP (Verena Kain, Jorg Wenninger, James Ridewood) TS/HDO (Maria Paz Casas Lino, Ivan Moya)

slide-5
SLIDE 5

3

PREVIOUS TEST:

NON CONFORMITIES - IMPROVEMENTS

POWER CONVERTER: MQIF87800 (3e-4 ripple) TI8 MAGNETS FUNCTIONS:

  • Functions to be adjusted / smoothened, according to spec. Roger Genand. Timing of

logging to coincide with exact extraction moment

  • Redo heat run during cold check out, with shorter cycle (around 8 s instead of 28 s)
  • MCIAV88115 /6/7 are pulsed, should run dc for required stability

LARGE INDUCTIVE LOOPS IN MSI AND SOME QUADRIPOLE CABLING

Jan Uithoven presentation 30 March

POLARITY TEST:

RMSI.R8B2: Might be re-cabled and will need to be checked again RQID.87900: Wrong labelling on cables RQID.88100: Might be re-cabled and will need to be checked again RQIF.87800: Wrong labelling on cables RQIF.88000: Might be re-cabled and will need to be checked again

8H RUN NON CONFORMITY RBXWSH.L8: Magnet Temperature raised to 58 C due

too low flow rate. TS/CV to balance the cooling circuit. Nominal flow rate 20 l/min. (EDMS: 829411) MTF non conformities

TEMPORAL WIC CABLE ?

slide-6
SLIDE 6

4

PREVIOUS TEST: INTERFERENCES IN

COMPENSATOR MAGNETS

CONDITIONS DURING THE PREVIOUS TEST:

COMPENSATORS RUNNING AT 7TeV SETTINGS INSTEAD OF AT INJECTION ENERGY (450 GeV) NOT ALL TI8 PC WHERE POWERED DURING THE TEST. (upstream

  • f TED 87765) [1.3 MVA vs 5.4 MVA]

MAIN REACTIVE COMPENSATORS AT POINT 8 NOT OPERATIONAL

INTERFERENCES IN THE COMPENSATORS MORE IMPORTANT AT MBXWS (40 mH) than the MBXWH (160 mH)

slide-7
SLIDE 7

5

LHC Compensators - Performance

Interference with the TI 8 power converters Graphs for compensators running at 7 TeV settings

RBXWSH.R8 Without TI8 (end) With TI8 (end) 20 mA peak-peak 200 mApp

Start of ramp down End of ramp up ramp up

Specification is 20 ppm = 16 mA peak - peak

Jan Uythoven, AB /BT ICC, 30 March 2007

slide-8
SLIDE 8

6

Interference with TI 8 Power Converters

More important for RBXWSH.R8 than RBXWHX.L8

With TI8 (end) RBXWSH.R8 (40 mH, 62 mΩ) RBXWH.L8 (145 mH, 82 mΩ) 200 mApp 25 mApp Not OK About OK

Jan Uythoven, AB /BT ICC, 30 March 2007

slide-9
SLIDE 9

7

PROGRAMME PROPOSAL

1. COMPLETE THE WARM MAGNETS COMMISSIONING AT POINT 8

  • POLARITY CHECK (ALL WARM MAGNETS?)
  • 24H RUN (I INJECTION)

2. UNDERSTANDAND AND EVALUATE THE INTERFERENCES OF TI8 PC IN COMPENSATORS PC

  • TURN ON ALL TI8 WARM MAGNETS PC (1st EVALUATION)
  • TURN OFF TI8 WARM MAGNET PC 18 KV ( 2nd EVALUATION)
  • CONCLUSIONS

3. LOOK FOR A SOLUTION 4. VALIDATE SOLUTION??? (If we have time)

slide-10
SLIDE 10

8

TIME REQUIREMENTS

  • POWER CONVERTERS IST
  • WELQA
  • WIC
  • WIC PC
  • SETUP WARM CIRCUITS
  • WARM CIRCUIT POLARITY TEST
  • WARM CIRCUIT HEAT RUN
  • INTERFERENCES 1st EVALUATION
  • INTERFERENCES 2nd EVALUATION
  • SOLUTION IMPLEMENTATION
  • SOLUTION VALIDATION
  • 2 DAYS
  • 2 DAYS
  • ? DAYS
  • ? DAYS
  • DONE. 0 DAYS

COMPLETION STEPS WARM MAGNETS COMMISSINIG POINT 8 COMPENSATOR INTERFERENCES UNDERSTANDING AND SOLUTION POINT 8

  • 0.5 DAYS
  • 1 DAYS
slide-11
SLIDE 11

9

PLANNING

ID Task Name Duration 1 PREPARATION TO TE 7 days 2 POLARITY TEST 0,5 days 3 HEAT RUN 1 day 4 INTERFERENCES 1st EVALUATION 2 days 5 INTERFERENCES 2nd EVALUATION 2 days 6 SOLUTION IMPLEMENTATION 1 day 7 SOLUTION VALIDATIO 0,5 days 11/05 AB/PO, TS/EL, AB/BT 23/05 AB/PO, AT/MEL 23/05 AB/PO, AB/CO, AT/MEL, TS/EL 24/05 AB/PO, AB/BT 29/05 AB/PO, AB/BT 31/05 AB/PO, ? 01/06 AB/PO, ? T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W May '07 14 May '07 21 May '07 28 May '07 04 Jun '07

slide-12
SLIDE 12

10

ACCESS RESTRICTIONS

During the whole tests: Fencing, signalization and flashing lights at the Power Converters level Panels forbidding the access to the magnets in the RA87 between the two access from the UA87 Fencing, signalization and flashing lights for the rest of the warm magnets

slide-13
SLIDE 13

11

Warm magnet circuits at point 8 AC Warm magnet circuits at point 8 AC network network

TI8 1.8 MVA (pulsed) LHC 0.3 MVA (DC) 2 MVA (Zo ≈ 7%) 400 V 18 kV 40 MVA TI8 3.6 MVA (pulsed)

Interferences 1st evaluation Interferences 2nd evaluation