Newmarket Level Crossing
Community Liaison Group
21st August 2017
Newmarket Level Crossing Community Liaison Group 21 st August 2017 - - PowerPoint PPT Presentation
Newmarket Level Crossing Community Liaison Group 21 st August 2017 Agenda 1. Introductions and housekeeping 2. Update on Programme 2. Update on Design 3. Construction Staging 4. Consent Management Plans 5. Communications and Feedback 5.
21st August 2017
2
3
Late August Issue of construction tender October Construction commences 18-19 November Weekend works during rail shutdown 27 December – 7 January Christmas works during rail shutdown 27 – 29 January Auckland Anniversary works during rail shutdown March 2018 Completion of bridge and road works 30 March – 2 April Easter works to relocate rail signals April 2018 Opening of new road and bridge section, closure of crossing May 2018 Removal of final crossing infrastructure and KiwiRail signalling commissioning Second half 2018 Cowie St road and footpath renewals work
4
complete, undergoing external peer review and internal AT reviews.
Whenua at hui 13th September
Waitematā Local Board at 29th August workshop. Both these items will be discussed shortly in this presentation, and we invite your feedback on these two areas to inform decision making.
5
6
7
Park (combined with stormwater tree pits).
similar to Auckland War Memorial Museum.
safety auditor.
speed tables as an alternative, but chicanes preferred during the road safety reviews as more desirable for this environment.
current design is appropriate for achieving the project's safety objectives.
8
Several community members have requested that pedestrian access from Sarawia Street to Laxon Terrace be retained via either a level crossing or dedicated footbridge/subway.
Pedestrian Crossing Remains
KiwiRail do not consider the safety risks sufficiently reduced that they could relax the current safety restrictions.
Dedicated Footbridge or Subway
either at Cowie Street or Sarawia Street.
those travelling from Sarawia Street to Newmarket Park or Laxon Terrace to Parnell Road.
$2.9M. a significant and costly item, and costs for a pedestrian subway would be of a similar order. For this reason, the project is not proposing to construct a second Parnell Road pedestrian access.
9
the road.
meeting AT roading standards to achieve crime deterrence outcomes.
footpath patterning around observation area.
further 3 streetlights will be added along the length of Cowie St to supplement existing lighting levels.
10
11
12
patterns
down to Newmarket Park entrance
adjacent to Newmarket Park entrance.
13
Park entrance: Pou, seating, footpath patterning Observation area: handrail design, footpath patterning Abutments: patterning on concrete panels
14
colour effect.
motif.
15
16
Footpath Patterning
Investigating options to add colour to sandblasted patterning on the footpath near the entrance to Newmarket Park and at the observation area overlooking the park.
17
Draft management plan drafts will be loaded onto the website for comment by interested parties in the next few days, to be finalised by the Contractor following tender award:
These drafts have been recently shared with Cowie St Residents Association and Laxon Terrace Youngs Lane Residents Group contacts. We are seeking feedback on these initial management plans by Monday 4th September 2017. The following management plans will follow soon after:
All plans will be found at https://at.govt.nz/projects-roadworks/newmarket-level-crossing/.
18
Management of Construction Effects
footpath, traffic management in place when vehicles or construction activity occurring nearby.
busy periods
timing identified in advance
again within 6 months of project completion.
19
20
21
available shortly. The draft Plan is currently available, and feedback on this was sought at the May 2017 CLG.
meeting will introduce the Contractor team, and discuss the details of the construction staging.
Construction Communication and Consultation Plan will detail how we will keep the community informed during construction and respond to feedback
– please remember to enter your details if you haven’t previously.
22
Following tonight’s meeting, AT would like to invite feedback on the following in particular:
by Monday 28th August 2017
September 2017:
2017:
September 2017.
23
AT’s communications manager for the Project: Dai Bindoff, AT Senior Communications Advisor Dai.Bindoff@at.govt.nz 09 448 7110 Community Liaison Group independent facilitator for the Project: Kim Gilkison, Crisp Communications Kim@crisp.net.nz 0212413221