Level Crossing Removal Project Kevin Devlin CEO, Level Crossing - PowerPoint PPT Presentation

Level Crossing Removal Project Kevin Devlin CEO, Level Crossing Removal Authority Level Crossing Removal Project Status Update 1 level crossing completed Over $2.8 billion in contracts awarded 18 in construction The


  1. Level Crossing Removal Project Kevin Devlin CEO, Level Crossing Removal Authority

  2. Level Crossing Removal Project – Status Update • 1 level crossing completed • Over $2.8 billion in contracts awarded • 18 in construction • The first 35 level crossings have been identified for removal, with construction on those 35 sites to either be complete or underway by the end of 2018. • At least 20 on schedule to be complete by end of 2018 • Planning and consultation underway to deliver entire program.

  3. Level Crossings: Burke Road, Glen Iris - completed North Road, Ormond – under construction, completion late 2016 Centre Road, Bentleigh – under construction, completion late 2016 McKinnon Road, McKinnon – under construction, completion late 2016 Furlong Road, St Albans – under construction, completion mid 2017 Main Road, St Albans – under construction, completion mid 2017 Blackburn Road, Blackburn – under construction, completion late 2017 Heatherdale Road, Mitcham – under construction, completion late 2017 Mountain Highway, Bayswater – under construction, completion late 2017 Scoresby Road, Bayswater – under construction, completion late 2017

  4. Level Crossings: Grange Rd, Carnegie – contract awarded, completion late 2018 Koornang Rd, Carnegie – contract awarded, completion late 2018 Murrumbeena Rd, Murrumbeena – contract awarded, completion late 2018 Poath Rd, Hughesdale – contract awarded, completion late 2018 Clayton Rd, Clayton – contract awarded, completion late 2018 Centre Rd, Clayton – contract awarded, completion late 2018 Corrigan Rd, Noble Park – contract awarded, completion late 2018 Heatherton Rd, Noble Park – contract awarded, completion late 2018 Chandler Rd, Noble Park – contract awarded, completion late 2018 Thompsons Road, Lyndhurst – in procurement phase, completion late 2018 Melton Highway, Sydenham – pre-procurement phase, completion late 2018

  5. Level Crossings: Kororoit Creek Road, Williamstown - planning and consultation, under construction by end of 2018 Abbotts Road, Dandenong South - planning and consultation, under construction by end of 2018 Charman Road, Cheltenham - planning and consultation, under construction by end of 2018 Balcolme Road, Mentone - planning and consultation, under construction by end of 2018 Edithvale Road, Edithvale - planning and consultation, under construction by end of 2018 Station Street, Bonbeach - planning and consultation, under construction by end of 2018 Station Street, Carrum - planning and consultation, under construction by end of 2018 Eel Race Road, Seaford - planning and consultation, under construction by end of 2018 Seaford Road, Seaford - planning and consultation, under construction by end of 2018 Skye/Overton Road - Frankston, planning and consultation, under construction by end of 2018 Bell Street, Preston - planning and consultation, under construction by end of 2018 High Street, Reservoir - planning and consultation, under construction by end of 2018 Grange Road, Alphington - planning and consultation, under construction by end of 2018 Lower Plenty Road, Rosanna - planning and consultation, under construction by end of 2018

  6. Level Crossings: Aviation Road, Laverton – early planning, completion by 2022 Bell Street, Coburg – early planning, completion by 2022 Buckley Street, Essendon – early planning, completion by 2022 Camp Road, Campbellfield – early planning, completion by 2022 Cherry Street, Werribee – early planning, completion by 2022 Clyde Road, Berwick – early planning, completion by 2022 Ferguson Street, Williamstown – early planning, completion by 2022 Glenroy Road, Glenroy – early planning, completion by 2022 Hallam Road South, Hallam – early planning, completion by 2022 Manchester Road, Mooroolbark – early planning, completion by 2022 Maroondah Highway, Lilydale – early planning, completion by 2022 Moreland Road, Brunswick – early planning, completion by 2022 South Gippsland Highway – early Dandenong planning, completion by 2022 Toorak Road, Kooyong – early planning, completion by 2022 Werribee Street, Werribee – early planning, completion by 2022

  7. Other Projects – Status Update • Cranbourne-Pakenham Line Upgrade ($608 million) – contract awarded, completion late 2018 • Mernda Rail Extension ($598 million) – budget announced, EoI process underway, completion in 2019 • Duplication of the Hurstbridge line ($140million ) – planning and consultation yet to commence, completion late 2018

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.