Grade Crossing Improvements Projects Citizen Advisory Committee January 16, 2019 Agenda Item #8 Background Information 1. Redwood City Grade Crossing Improvements Project 2. Santa Clara Grade Crossing Medians Project 3. FY16 Grade


  1. Grade Crossing Improvements Projects Citizen Advisory Committee January 16, 2019 Agenda Item #8

  2. Background Information 1. Redwood City Grade Crossing Improvements Project 2. Santa Clara Grade Crossing Medians Project 3. FY16 Grade Crossing Improvements Project

  3. Scope of Work Redwood City Grade Crossing Improvements 1. Whipple Ave 2. Broadway 3. Main St

  4. Scope of Work Redwood City Grade Crossing Improvements • Installed new pedestrian gates and emergency swing gates • Improved sidewalk with warning tactile and guard rails • Installed pavement markers and markings • Installed a new cantilever signal at Whipple

  5. Whipple Ave

  6. Broadway, Redwood City

  7. Main St

  8. Santa Clara Grade Crossing Medians 1. Churchill Ave, Palo Alto 2. East Meadow, Palo Alto 3. Sunnyvale Ave, Sunnyvale 4. Auzerais Ave, San Jose 5. West Virginia, San Jose

  9. East Meadow Crossing Median

  10. Sunnyvale Ave Crossing Median

  11. Auzerais Crossing Median

  12. FY16 Grade Crossings Improvements 16 th St – San Francisco 1. Broadway – Burlingame 2. Peninsula – Burlingame 3. 4 th Ave – San Mateo 4. Ravenswood – Menlo Park 5. Alma – Palo Alto 6. Charleston – Palo Alto 7. Rengstorff – Mountain View 8. Castro – Mountain View 9. 10. Mary Ave – Sunnyvale

  13. FY16 Grade Crossings Improvements Scope of Work 16 th St, Broadway, Peninsula, 4 th Ave, Ravenswood • Installed new pedestrian gates and emergency swing gates • Improved sidewalk with warning tactile and guard rails • Installed pavement markers and markings • Installed new signage

  14. 16 th St

  15. Broadway, Burlingame

  16. Peninsula

  17. 4 th Ave

  18. Ravenswood

  19. FY16 Grade Crossings Improvements Scope of Work Alma, Charleston, Rengstorff, Castro, Mary Ave • Improved sidewalk with guard rails • Installed pavement markers and markings • Installed new signage • Installed medians at Alma and Charleston

  20. Alma

  21. Charleston

  22. Rengstorff

  23. Castro

  24. Mary Ave

  25. Questions?

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.