bnsf railway public projects and grade crossing safety
play

BNSF Railway Public Projects and Grade Crossing Safety APWA - PowerPoint PPT Presentation

BNSF Railway Public Projects and Grade Crossing Safety APWA Chicago Metro Division Calvin Nutt Manager Public Projects IA, IL, WI November 18, 2015 1 11/24/2015 Agenda - BNSF Public Projects Overview - Crossing Safety - At-Grade


  1. BNSF Railway – Public Projects and Grade Crossing Safety APWA Chicago Metro Division Calvin Nutt – Manager Public Projects – IA, IL, WI November 18, 2015 1 11/24/2015

  2. Agenda - BNSF Public Projects Overview - Crossing Safety - At-Grade Crossing Consolidation - Interconnection/Preemption - Pedestrian Concerns - Grade Separations - Permitting - Public Projects Department vs. Jones Lang LaSalle - Contractor Safety 2 11/24/2015

  3. BNSF Overview - 32,500 miles of track - 28 States, 3 Canadian Provinces - 47,000 Employees - Average 1,600 trains/day - 10 million carloads in 2014 - 50 million packages each holiday season - 500 miles/gallon for 1 ton of freight - 8,000 locomotives - 13,000 bridges - 25,700 Grade Crossings 3 11/24/2015

  4. BNSF Public Projects Team Public Crossing Statistics - Chicago Area - 105 At-Grade - 31 Overpasses - 84 Underpasses - Illinois - 1,500 At-Grade - 168 Overpasses - 206 Underpasses 2015 Projects Total = $88MM 4 11/24/2015

  5. Public Projects Overview Project Types - Roadway Realignments/Widening - Grade Separations - Signal Installations - Surface Installations - Grade Crossing Closures - Improvement projects paralleling BNSF ROW - Quiet Zones - Multi-use paths 5 11/24/2015

  6. Public Projects Overview - Responsibilities - Project Administration - Conceptual or Preliminary Plan Approval - Internal BNSF Coordination on Agency Projects - Facilitating plan review - Project meetings - Project scheduling - Agreement Negotiations - Contractor Onboarding - Preconstruction Meeting - Project Hand-Off 6 11/24/2015

  7. Grade Crossing Safety Highway-railroad grade crossing safety is an integral part of BNSF’s operation and culture and involves the daily cooperative effort of many employees 7 11/24/2015

  8. Grade Crossing Safety Crossing Facts - It takes a fully loaded freight train moving 50 mph approximately 1 ½ miles to come to a complete stop - Motorists are 40 times more likely to die in a crash with a train than with a motor vehicle - Trains can’t swerve – travel on set route - Large objects appear to be traveling slower than reality - Any time is train time - Varied levels of warning devices - Most train/vehicle crashes are preventable Crossing Statistics - 52% of BNSF crossing collisions occur at active-warning crossings 8 11/24/2015

  9. Grade Crossing Safety Nearly all grade crossing collisions are caused by motorist error Stopped, Proceeded 71 4% Did Not Stop Stopped on Tracks: 482 (29%) 593 (36%) Other 228 Drove Around (14%) Gate: 212 (13%) Sources: AAR Analysis of Highway-Rail Incident Database for 2013 (March 2014). FRA, Railroad Safety Statistics Annual Report 2010, Table 8-6. Note: Motor vehicle highway-rail incidents at public crossings. 9 11/24/2015

  10. Grade Crossing Safety Warning Classes - Passive (Cross Bucks, Yield Signs, Stop Signs) - Active (Traffic Signals, Flashing Lights, Lights and Gates, Four-Quadrant Gates) 10 11/24/2015

  11. Grade Crossing Safety Crossing Consolidation - The safest at-grade crossing is ALWAYS no at-grade crossing - BNSF Program to reduce at-grade crossings - Started in 2000 - Currently 30-35 team members - Built on Education, Engineering, and Enforcement - Successfully eliminated 6,000 crossings - Any at-grade crossing is a potential closure, and any closure is beneficial 11 11/24/2015

  12. Grade Crossing Safety Crossing Interconnect/Preemption - BNSF supports installation of new preemption as well as improvements to existing preemption - Road authority determines required preemption time and requests from BNSF 12 11/24/2015

  13. Grade Crossing Safety Quiet Zones - FRA Train Horn Rule establishes requirements for use of horn when approaching at-grade crossings - Public authorities may establish Quiet Zones in accordance with FRA rule (Pt. 222 of 49 CFR) - Public Authority is the owner of the process - BNSF is involved in the process and encourages SSM’s at every crossing to create a sealed corridor - SSM’s include four-quadrant gates, closure, and medians 13 11/24/2015

  14. Grade Crossing Safety Pedestrian Treatments - New Chapter 8D approved for next publication of MUTCD - Will be used for future roadway reconstruction, streetscape, and commuter platform projects 14 11/24/2015

  15. Grade Separations - Railroads can be obligated to contribute 5% to initial grade separations. - Additional funding potential if multiple at-grade crossings are eliminated - 5% number does not include aesthetic components, additional landscaping, etc. - All grade separations must meet the requirements of the BNSF/UP Grade Separation Guidelines - Highway structure typically more feasible than railway structure - Lower loads - Shorter span - Higher maximum allowable grade 15 11/24/2015

  16. Municipality Project Coordination BNSF is involved in - Design - Permitting - Right-of-Way - Contract Negotiation - Contractor Safety - Construction Inspection/Coordination 16 11/24/2015

  17. Permitting with BNSF Temporary Occupancy and Utility Permits - Pipelines, utilities, surveys, geotech, etc. - Handled by Jones Lang LaSalle (JLL) - 6-8 weeks to obtain - $750 processing fee (approx.) - $2,500 permit fee (approx.) - Permit outlines insurance, flagging, safety, etc. - Information at www.bnsf.com/communities/faqs/permits- real-estate/ 17 11/24/2015

  18. Public Projects vs. JLL When do you use BNSF Public Projects vs. JLL? - Public Projects - Grade separations, roadway widening, new crossings, crossing reconfiguration/reconstruction, quiet zones, closures, etc. - JLL - Surveys, geotech, utilities, permits, maintenance ROE 18 11/24/2015

  19. Contractor Safety Flagging Requirements - Work within 25 feet of track centerline - Work on BNSF ROW - Work is capable of fouling track - Within 4’ of track if equipment falls (cranes and excavators) - Coordinated through local Roadmaster - Paid by road authority - Required through ROE, permit, or C/C1 Agreement 19 11/24/2015

  20. Contractor Start-Up - Right of Entry - Minimum 30 days for ROE, permit, or C/C1 Agreement - Contractor Orientation - BNSFContractor.com - Covers safety requirements when working on BNSF ROW - Must have card and photo on person when on BNSF ROW - E-RailSafe - www.e-railsafe.com - Personnel screening and security management - Submittals (overpass/underpass projects) - Contractor submittal requirements included in Grade Separation Guidelines - Submittals require 4 weeks for each review cycle - Consider consultants and contractors with railroad expertise. 20 11/24/2015

  21. Questions? Calvin Nutt Manager Public Projects Minneapolis, MN Calvin.Nutt@BNSF.com 21 11/24/2015

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend