New Elementary School #42 Design Development Report Scott - PowerPoint PPT Presentation

New Elementary School #42 Design Development Report Scott Washington Director, School Construction October 22, 2015 Project Update Reconfiguration of administrative suite to provide a larger workroom and separate supply storage


  1. New Elementary School #42 Design Development Report Scott Washington Director, School Construction October 22, 2015

  2. Project Update • Reconfiguration of administrative suite to provide a larger workroom and separate supply storage • Reconfiguration of the health suite to increase cot visibility from the nurse’s office and assistant’s desk • Increased the size of all instructional areas within each of the kindergarten classrooms • Revised stair layout at both end stairs to allow for more natural daylight in these circulation spaces

  3. Project Update (cont.) • Site plan has been revised to improve the pedestrian connections to the surrounding community • An outdoor classroom has been developed for use as a teaching space as well as located for use by the community • Exterior elevations have been revised from the prototype to coordinate with the surrounding architecture

  4. New Elementary School #42 Site Plan

  5. New Elementary School #42 E nlar ge d Site Plan

  6. New Elementary School #42 De sign De ve lopme nt D F F ir i st F loor Plan Schematic Design First Floor Plan

  7. New Elementary School #42 De sign De ve lopme nt Se c ond F loor Plan Schematic Design First Floor Plan

  8. New Elementary School #42 Schematic Design First Floor Plan

  9. New Elementary School #42 F r ont E le vation

  10. T otal Project Budget Base Construction Estimate $33,252,535 Architect/ Engineering Fee $2,474,585 Construction M anagement Fee $2,350,000 Related Costs $1,666,000 Project Contingency $1,666,000 Equipment and Technology $2,333,520 Alternate #1: Outdoor Classroom at M ain Entrance $159,485 Alternate #2: Instructional Gazebo at Bus Loop $49,484 Project Total Budget $43,951,609 Funding Projections FY16 $2,807,000 FY17 $16,526,000 FY18 $20,658,000 FY19 $4,132,000 Total Funding Projections $44,123,000

  11. New Elementary School #42 Summary • Schedule – Construction Documents (CD) report April 2016 – Receive bids July 2016 – Construction starts September 2016 – Completion August 2018 • Request approval to move into CD phase

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.