Module 7 Construction Bidding 1 2 3 4 5 6 7 8 9 10 11 12 - - PDF document

module 7 construction bidding
SMART_READER_LITE
LIVE PREVIEW

Module 7 Construction Bidding 1 2 3 4 5 6 7 8 9 10 11 12 - - PDF document

Module 7 Construction Bidding 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 Example File For Unsuccessful BID 24 Bidder did not include bid security Unsuccessful BID 25 26 27 28 29 Bidding


slide-1
SLIDE 1

1

Module 7 Construction Bidding

slide-2
SLIDE 2

2

slide-3
SLIDE 3

3

slide-4
SLIDE 4

4

slide-5
SLIDE 5

5

slide-6
SLIDE 6

6

slide-7
SLIDE 7

7

slide-8
SLIDE 8

8

slide-9
SLIDE 9

9

slide-10
SLIDE 10

10

slide-11
SLIDE 11

11

slide-12
SLIDE 12

12

slide-13
SLIDE 13

13

slide-14
SLIDE 14

14

slide-15
SLIDE 15

15

slide-16
SLIDE 16

16

slide-17
SLIDE 17

17

slide-18
SLIDE 18

18

slide-19
SLIDE 19

19

slide-20
SLIDE 20

20

slide-21
SLIDE 21

21

slide-22
SLIDE 22

22

slide-23
SLIDE 23

23

slide-24
SLIDE 24

24 Example File For “Unsuccessful” BID

slide-25
SLIDE 25

25 Bidder did not include bid security “Unsuccessful” BID

slide-26
SLIDE 26

26

slide-27
SLIDE 27

27

slide-28
SLIDE 28

28

slide-29
SLIDE 29

29

slide-30
SLIDE 30

30 Bidding Coordinator receives and checks Designer’s letter of recommendation and obtains Project Manager’s approval of Designer’s recommendation, if required awaits for SBC. Enters data into PITS files recommendation if rejected closes file. If awardable initiates contract, checks bids and Bid Tab amends Bid Tab if needed. Enters date into PITS files Bid Tab and Bids, secures cashier’s checks, asks Designer for missing documents, and verifies licenses. Gives copies of Bid Tab to OFD Executive Director, OFD Project Management Director, OFD Project Manager, OFD SBC Agenda Manager, faxes to State Architect and Dodge Report. When all bids are rejected Bidding Coordinator files closure, enters data into PITS, and disposes of cashier’s checks. Holds disposition of bidding documents if Project Manager is certain of imminent re- use in re-bid, otherwise gives to Project Manager. File disposition, if Project Manager is certain of imminent re-bid holds onto file, otherwise sends to main files.

slide-31
SLIDE 31

31

slide-32
SLIDE 32

32

slide-33
SLIDE 33

33

slide-34
SLIDE 34

34

slide-35
SLIDE 35

35

slide-36
SLIDE 36

36

slide-37
SLIDE 37

37