MoDOT Utility Construction 5/11/2016 & Erosion Control Seminar - - PDF document
MoDOT Utility Construction 5/11/2016 & Erosion Control Seminar - - PDF document
MoDOT Utility Construction 5/11/2016 & Erosion Control Seminar Handout Kansas Citys Favorite DUE Mr. Robert Rhodes, MoDOT District Utilities Engineer Kansas City District Counties included in the KC District: Cass Pettis
MoDOT Utility Construction & Erosion Control Seminar Handout 5/11/2016 Section 1 – MoDOT Utility Installation Policy 1
- Mr. Robert Rhodes,
MoDOT District Utilities Engineer Kansas City District
Counties included in the KC District:
- Cass
- Clay
- Jackson
- Johnson
- Lafayette
- Pettis
- Platte
- Ray
- Saline
Kansas City’s Favorite DUE
- Mr. Robert Rhodes,
MoDOT District Utilities Engineer Kansas City District
Duties Include:
- Coordinating Utility Work on MoDOT Statewide Transportation
Improvement Projects, both Reimbursable and Non-Reimbursable.
- Reviewing, Approving/Rejecting, and Processing Variance Requests.
- Oversight of Utility Permits in the District.
- Serve as District Contact for Railroad Safety Projects.
MoDOT Utility Construction & Erosion Control Seminar Handout 5/11/2016 Section 1 – MoDOT Utility Installation Policy 2
- Mr. Robert Rhodes,
MoDOT District Utilities Engineer Kansas City District
- Clay I-435
June 2016 Interchange Improvements at 210 Hwy.
- Platte 45
June 2016 Corridor Widening from I-435 to Rte. K.
- Jackson I-49
November 2016 Interchange Improvements at 155th Street.
- Jackson 50
February 2017 Interchange Improvements at Rte. 291 (South)
- Cass 291
March 2017 Capacity Improvements in Harrisonville
- Mr. Robert Rhodes,
MoDOT District Utilities Engineer Kansas City District
- Jackson I-70
October 2017 Interchange Improvements at I-435.
- Jackson I-70
February 2018 Bridge Improvements (4 Locations).
- Clay 152
June 2018 Interchange Improvements at I-35.
- Jackson I-435
January 2019 Bridge Improvements from KS State Line to I-49.
- Mr. Robert Rhodes,
MoDOT District Utilities Engineer Kansas City District (816) 607-2234
Any Quick Questions?
MoDOT Utility Construction & Erosion Control Seminar Handout 5/11/2016 Section 1 – MoDOT Utility Installation Policy 3
- Mr. Richard Orr, P.E.
MoDOT Transportation Project Manager Northwest (St. Joseph) District (816) 387-2483
The Facts Behind the Policy
- 1804 - Philadelphia had the distinction of being the first city in the
world to use cast iron pipe for its public water mains. Wooden pipes were commonly used before that.
- 1859 - ‘Colonel’ Edwin Drake, a former railroad conductor, built a two-
inch diameter natural gas pipeline that ran 5½ miles from the well to the village of Titusville, Pennsylvania.
- 1861 - President Lincoln established the US Military Telegraph Corps.
Over 15,000 miles of copper telegraph cable was built across the country purely for military purposes.
- 1878 - Inventor Thomas Edison built a system to provide electric
lighting to businesses and homes. When service started, he had 85 customers in a one square-mile area and powered 400 incandescent lights for them using 6 ‘jumbo dynamos’ housed at Pearl Street Station, Manhattan.
Historical Public Utilities - Fun Factoids
- 1935 – In response to concerns about price gouging by utility
companies, Congress enacted the Public Utility Holding Act to be
- verseen by the recently created Securities Exchange
- Commission. The law did not name any specific standard that the
SEC was to use in evaluating the plans, and the SEC itself did not set any particular rule to govern its decisions. What a plan!
Historical Public Utilities - Fun Factoids
MoDOT Utility Construction & Erosion Control Seminar Handout 5/11/2016 Section 1 – MoDOT Utility Installation Policy 4
- 1988 – A Good Year for Utilities
- Prior to 1988, the Federal Highway Administration prohibited
utilities from being installed within interstate rights-of-way, and many states had adopted this same policy for their state highways.
- In 1988, however, FHWA changed that policy to allow each
state to decide whether to permit utilities within interstate ROW as long as it was safe for the traveling public and did not affect maintenance of the facilities. Not surprisingly, many states shortly followed suit and adopted that very same policy for their state routes.
The Foundation of MoDOT’s Utility Policy
- Federal Definition of a Utility:
- A "privately, publically, or cooperatively owned line, facility or
system for producing, transmitting, or distributing communications, cable television, power, electricity, light, heat, gas, oil, crude products, water, steam, waste, storm water not connected with highway draining, or any other similar commodity, including any fire or police signal system
- r street lightening system, which directly or indirectly
serves the public" (23 CFR 645.207).
The Foundation of MoDOT’s Utility Policy The Foundation of MoDOT’s Utility Policy
- The Basis for Allowing Utilities within the ROW
- Departments of Transportation (DOTs) can allow public and
private utilities within the ROW if they have an approved Utility Accommodation Policy (UAP).
- The American Association of Highway and Transportation
Officials (AASHTO's) "Guide for Accommodating Utilities within the Right-of-Way" establishes guidelines for states' UAPs, which FHWA ultimately reviews and approves.
MoDOT Utility Construction & Erosion Control Seminar Handout 5/11/2016 Section 1 – MoDOT Utility Installation Policy 5
The Foundation of MoDOT’s Utility Policy
- Some of the Regulations Governing Placement of
Utilities in the ROW:
49 Code of Federal Regulations (CFR) 18.31(b) (Real Property) 23 United States Code (USC) 111 (Use and Access to ROW) 23 CFR 645 Subpart B (Accommodation of Utilities) 23 CFR 710 (ROW and Real Estate) 23 CFR 752.5 (Safety Rest Areas)
So… What Does all that Mean?
- Take a look at this typical state maintained route
with normal access ROW:
- The ‘Utility Corridor’ is the 6-ft. width adjacent to
the ROW line.
- Utilities may be installed in the utility corridor
without charge, providing they conform to MoDOT’s requirements.
- Variances are exceptions to the MoDOT standard
policy that must be approved by District Utility Engineers and, in some cases, FHWA.
So… What Does all that Mean?
1
Permit Permit Proc Process ss & Saf Safety ty Requireme rements ts
Course Objectives
- Our permit process and procedures
- Our Work Zone Safety and Mobility Policy
- Our “Notice of Intent to Work” process and
how that impacts public notification
- Our High Visibility Safety Apparel
requirements
Upon completion, you will:
3
MoDOT’s Work Zone Safety and Mobility Policy
Engineering Policy Guide SECTION 616.14 http://modot.org
2 Work Zone Safety and Mobility Policy
- Provide an environment conducive to roadway user
and worker safety. – Work toward zero work zone fatalities. – Reduce crashes in all types of work zones.
- Minimize impact of work zones on roadway user.
– Limit traffic delays to 15 minutes or less. – Provide customers real-time work zone information.
Work Zone Safety and Mobility Policy
- Fundamental Principles
- Responsibilities
Fundamental Principles
- Prepare a temporary traffic control plan and
communicate it to all parties prior to
- ccupying the site
- Schedule and coordinate operations with all
involved parties
- Provide training appropriate to the level of
responsibility
- Avoid frequent or abrupt geometric
changes
- Minimize delay and disruption to traffic
3 Fundamental Principles
- Provide adequate warning,
delineation, and channelization in advance of and through the area affected
- Provide positive guidance
- Assume drivers will only reduce their
speeds if they perceive a need to do so
- Ensure continuation of emergency
services
Fundamental Principles
- Communicate with and provide reasonable
accommodations for adjoining property
- wners
- Provide temporary traffic control devices
that are in good working order
- Inspect and maintain temporary traffic
control devices
- Monitor performance of the work zone and
modify as needed
Fundamental Principles
- Remove, cover, or turn off all unnecessary
temporary traffic control devices
- Keeping the public, local businesses,
trucking and transit associations, emergency responders, and government entities, etc. informed of work zone activities
- Provide for safe working operations!!!
4
SAFETY IS THE #1 PRIORITY AT MODOT SAFETY FOR UTILITY WORKERS & CONTRACTORS SAFETY FOR THE MOTORISTS OF MISSOURI
5
SAFETY CAN BE ACHIEVED BY WORKING TOGETHER WITH OTHER AGENCIES
Responsibilities
- MoDOT Permit Staff
- Utility Permittees
- Contractors and Sub-Contractors
Responsibilities District Permit Staff
- Review, Approve, and Issue Permits for work
performed on MoDOT right of way.
- Plan, Notify the Public, and Coordinate all work
zone activities with the permittee. A minimum of two working days for any lane closure before any non-emergency work begins.
- Schedule lane closures during off-peak and/or
nighttime hours when capacity is an issue.
- Determine if work zones are being maintained in a
neat, orderly and effective manner for the safety of workers and motorists
6 Responsibilities District Permit Staff
- Minimize delay and disruption experienced during
permit activities for the traveling public.
- Perform quality assurance of work zones to
promote compliance with policies and guidelines. This includes review and approval of traffic control plans, initial set-up inspections, and periodic inspections for longer term activities.
- Notify the public about work zone locations! Enter
workzones in the TMS (Traffic Management System)
Responsibilities Utility Permitees & Contractors
- Develop and submit for approval an appropriate
traffic control plan for work to be done on the state highway right of way.
- Designate a trained person at the work level who
shall have the primary responsibility, with sufficient authority, for implementing the temporary traffic control plan and other safety and mobility aspects
- f the permit work.
- Submit a “Notice of Intent to Perform Work” to
the respective MoDOT district office for all work on state highway right of way. http://www.modot.org
7 PUBLIC NOTIFICATION
8 PUBLIC NOTIFICATION PUBLIC NOTIFICATION Responsibilities Utility Permitees & Contractors
- Identify a point of contact that shall be available for
the entire duration, while the permittee maintains a presence on state highway right of way and that shall be capable of correcting any deficiencies in a timely manner.
- Training all permittee personnel in temporary traffic
control to a level commensurate with their responsibilities.
9 Responsibilities Utility Permitees & Contractors
- Notifying the appropriate district staff, as required,
at least two working days before commencement of any work on the right of way.
- Maintaining a copy of the permit and the temporary
traffic control plan at the work site that prescribes the necessary traffic control measures for the work to be performed.
- Minimizing time of lane closures.
Responsibilities Utility Permitees & Contractors
- Ensure that work zones are neat, orderly and
effective for the safety of permit workers and motorists.
- Performing quality control of work zones to promote
consistency and ensure compliance with temporary traffic control plan, policies and guidelines.
- Monitor and adjust traffic control measures, as
needed, to improve traffic flow, visibility and workers and motorist safety.
Training
Each person whose actions affect temporary traffic control zone safety, from the upper-level management through field workers, should receive training appropriate to the job decisions each individual is required to make
- MUTCD 2003 and Work Zone Safety
and Mobility Rule Making 2004
10
Work Zone Basics
Work Zone Components
Temporary Traffic Control Zone Operations
11 Location of Work
Where is the work going to occur:
- Work Beyond the Shoulder
- Work On the Shoulder
- Work Within the Travelway
Work Beyond the Shoulder Work on the Shoulder
12 Work Within the Travelway Work Within the Travelway Flagger Control
- A flagger protects
personnel – that’s you!!!
- A flagger provides safe,
courteous, and authoritative directions to move traffic through the work zone
- All flaggers should have
appropriate training
The flagger’s job is the most important
- ne on the crew!
13 Flagger Control
- The flaggers
STOP/SLOW paddle shall be 18” X 18” minimum
- Flaggers shall (and all
workers in the public right
- f way) are required to
wear High-Visibility Safety Apparel.
The flagger’s job is the most important
- ne on the crew!
High Visibility Apparel
- All workers, including emergency responders, within
the right-of-way who are exposed either to traffic (vehicles using the highway for purposes of travel) or to work vehicles and construction equipment within the TTC zone shall wear high-visibility safety apparel that meets the Performance Class 2 or 3 requirements
- f the ANSI/ISEA 107–2004 publication entitled
"American National Standard for High-Visibility Safety Apparel and Headwear“ or equivalent revisions, and labeled as meeting the ANSI 107-2004 standard performance for Class 2 or 3 risk exposure. A person designated by the employer to be responsible for worker safety shall make the selection of the appropriate class of garment.
14 Questions?
5/10/2016 1
Sediment & Erosion Control Basics plus Best Management Practices
Valerie Hentges Environmental Specialist Design Division MoDOT
Why? Environmental Regulation
Clean Water Act (1972) = Section 402 ~ National
Pollution Discharge Elimination System (NPDES)
Permit goal: To protect the quality and beneficial
uses of the local surface waters from construction pollution
Clearing, grading, excavation, and stockpiling
activities resulting in 1 or more acres of land disturbance for the whole project
Requires an implementation plan for pollution
prevention and control of runoff until final stabilization of the construction project has been achieved
Land Disturbance Env. Regulation
EPA delegates the Clean Water Act regulations to
Missouri DNR = point source discharge permits
Does not authorize other impacts (Historic Preservation
Act; Endangered Species Act; Section 404, 401, 408, etc. ) DNR grants a 5-yr permit to MoDOT (expires May 2017)
Permit revisions for the next 5 years going on NOW! Possible changes include: Linear or strip construction may no longer be exempt Water quality standards may be a larger part of permit BMPs needed for what storm level Settleable solids or another measurable parameter?
5/10/2016 2
MO Land Disturbance Env. Regulation
DNR grants a 5-yr permit to MoDOT (expires May 2017) Legal agreement between applicant (e.g., MoDOT)
and DNR
Applicant held responsible to follow permit
conditions and regulations for land disturbance activities
DNR receives a quarterly report for all MoDOT
projects of land disturbance of 1 acre or more
Become familiar with your permit!
http://dnr.mo.gov/env/wpp/permits/issued/docs/R100000.pdf Or MoDOT Land Disturbance web page: www.modot.org/ld
Permit Prohibited Acts
To cause
pollution of waters of the state
To exceed
permit limits
“A bit murky for low flow!”
Permit Prohibited Acts
To cause
pollution of waters of the state
To exceed
permit limits
To “put or
place” pollutants in proximity to streams
“When it rains, where will this material go?”
5/10/2016 3
Permit Prohibited Acts
To cause
pollution of waters of the state
To exceed
permit limits
To “put or
place” pollutants in proximity to streams
To exceed
general or specific water quality criteria
“free from unsightly turbidity”
“free from harmful bottom deposits”
“How do we find where this came from?”
Erosion Control vs…
Erosion = process when soil is displaced by water Rate of erosion influenced by climate, topography,
soil type, vegetation
Erosion Control vs. Sediment Control
Erosion = process when soil is displaced by water
Rate of erosion influenced by climate, topography, soil
type, vegetation Sediment = soil displaced by erosion; potential to
be transported long distances
5/10/2016 4
Erosion Control vs. Sediment Control
Erosion = process when soil is displaced by water
Rate of erosion influenced by climate, topography, soil
type, vegetation Sediment = soil displaced by erosion; potential to
be transported long distances
Erosion Control: practices to keep soil in place
(keep soil from moving/eroding)
Considered non-structural BMPs Sediment Control: remove sediment from runoff
before the runoff is discharged from the site
Considered structural BMPs
Non-structural (erosion) BMPs
Temporary or permanent Minimize amount of time soil is disturbed Inactivity for > 14 days = vegetative cover Preservation of trees (minimize compaction) Protect vegetation (buffer strips) Mulch and/or sod Temporary seeding or final seeding Geotextiles (Erosion control blankets, etc.) Soil stabilizing emulsion/tackifiers Stabilized construction entrances
Non-Structural BMPs need to be monitored
MO-R100007 p. 5-6, C.6.e.
Topsoil & Stockpile Management
Save topsoil when practicable for reuse Try to replace to provide quick germination of
vegetation
MO Specification Section 804 Protection of stockpiled materials with temporary
BMPs (covers, berms, silt fences, fiber rolls, etc.)
Covered, stabilized, and/or protected prior to
rain event
5/10/2016 5
Seed, sod, and mulch
Permanent seeding is always the preferred
stabilization technique
Temporary seed if work is focused on another
area for a period of time
Quick stabilization may save future re-grading
efforts
Mulch without seed only as temporary BMP (best when late fall or early winter) – if approved by engineer 7 days if steep slope (3:1) OR 14 days if “normal slope” MO Specification Section 802, 803, 805
Hydro-mulching
Apply over all exposed soil surfaces Can be used for temporary erosion control; use in
combination with seeding for permanent
Application needs to match the soil type/condition
and slope degree/ratio
Used on soil stockpiles to control wind erosion Spray from multiple directions to ensure coverage
Erosion control blankets (ECB) & Turf reinforcement mats (TRM)
Protective netting: none, one side or both sides Netting made of plastic or cotton thread Variety of materials used based on weight and
thickness needed
ECB – prevent sheet, rill or gully erosion on slopes
and lower flow channels; limited lifespan
TRM – used on steep slopes or slope areas with
concentrated flow; typically used in channels; longer lifespan than ECB
Recommended on most slopes steeper than 3:1 –
depending on soil type
MO Specification Section 806.90
5/10/2016 6
Fiber Reinforced Matrix
Spray-on product conforms to surface and bonds
to – blankets bare soil
FRMs lock in moisture and nutrients to promote
seed germination
Slope protection – not for concentrated flows
within ditches, drainages, or streams
Spray slopes from multiple, varying directions for
full cover per manufacture specifications
May need other BMPs to decrease runoff velocities
(wattles, socks, logs, etc.)
Construction Phasing
When possible phase the construction/land
- pening for necessary area where work is done
Stabilize promptly, each phase stabilized Trenching: Place spoils on the uphill side so that if
it does erode, it goes back into the trench
Structural (sediment) BMPs
Control and/or divert flows Silt fence (filter fabric, mulch berm, logs/socks) Earthen dikes (berms) Ditch checks (rock or alternate types) Subsurface drains Pipe slope drains Sediment traps Sediment basins
Structural BMPs need to be monitored
MO-R100007 p. 6, C.6.f.
5/10/2016 7
Silt Fence
Must be properly installed to function properly Permeable fabric (3’ high) that prevents majority
- f sediment passing through; 4 foot spacing;
securely fastened
Intercepts sheet flow to moderately concentrated flows
Barrier to runoff not suitable: high flow areas Not used to divert water Inspect prior to & after rain
event
Remove accumulated
sediment when 1/3 the height of fence
MO Specification Section 806.70
Compost Filter Socks, Rolls, and Logs
Straw or related materials confined into a roll;
water passes but prevents majority of sediment from passing through
Ideal for sheet flow or slightly to moderately
concentrated flows; overlap if more than 1 roll
Project stabilized – fiber rolls can be left in place if
filled with biodegradable material that is cut and spread out
Inspect prior to and after each rain event Repair or replace damaged rolls Frequently due to failure and undermining of
device
Stormdrain inlet protection
Reduces sediment from entering storm drain
system – culvert, drop, or curb (typically goes straight to stream)
Prior to grading, identify storm drains to place
protection around the inlets (Socks, wattles, rolls, logs,
filter devices, etc.) Constantly checked, esp. after rain event Remove protection devices once project has
reached stabilization
MO Specification
Section 806.30.2.3
5/10/2016 8
Drainage (Grassed) Swales
Typically a longitudinal strip of riprap or the
preferred grassed/vegetation
Install to convey runoff to minimize erosion Can be in conjunction with other BMPs (silt fence,
logs, wattles, ditch checks, etc.)
Ditch checks (Rock or Alternate)
Small temporary dams of rock perpendicular to the
swale/ditch
Reduce velocity & allow sediment to drop out behind
dams where ditch slopes are 10% or less (Rock checks) or 4% or less (Alternate checks)
Rock: 4 -12 inch rock; spacing allows for the toe of one to be
the height of next; min. effective height – 18”
Alternate: when safety concerns for traveling public or other
constrains where rock not feasible; min. effective height – 9”
Inspect prior to and after rain event;
Extensive maintenance after high flow event
May be in a series along the ditch NO placement in a stream MO Specification Section 806.30.2
Ditch checks (Rock or Alternate)
MO Specification Section 806.30.2
5/10/2016 9
Tracking In/Out
Consist of rumble plates or gravel to reduce off
project tracking of various pollutants
Or water pit for washing off tires or tracks Maintained daily to increase effectiveness
Photo credits: San Diego Gas & Electric: Water Quality Construction BMP Manual
Sediment Basin
Temporary basins to capture sediment runoff to
allow for settling out before water exists project
Constructed with defined side slopes; riprap
placed in inlet and outlet areas; at least twice as long as wide (max. time of concentration within structure)
Required when large (≤ 10 acres) disturbed areas
- f concentrated flow drains to one point; sized to
capture runoff from at least a 2 yr/24 hr event
Maintenance required; accumulated sediment
removed when basin is no more than half-full
MO Specification Section 806.40
Soil surface roughening
Tracking: tracked equipment vertically tracking
up and down slops to create horizontal depressions, perpendicular to the runoff path
Reduce velocity and concentrated runoff; minimized rill
erosion; can lead to soil compaction Grooving: creation of series of ridges and
depressions running along the contour of a slope
Grooves no more than 3” deep; no more than 15” apart
Stair-stepping: construction of stair steps to
reduce runoff velocity; sedimentation on steeper slopes that will not be mowed
Vertical steps not to exceed 1’; horizontal step longer
than vertical step and sloped inward toward vertical step face to promote sedimentation
5/10/2016 10
Guidance
Engineering Policy Guide http://epg.modot.org The Engineering Policy Guide (EPG) contains
MoDOT policy, procedure and guidance for the planning, design, construction and maintenance of roadway and related facilities. It also includes specific technical topics of right of way, bridge, traffic and materials.
Specification Book for Highway Construction
http://www.modot.org/business/standards_and_specs/highwayspecs.htm
The standard specifications book contains material,
equipment and construction requirements for items specified in the construction of Missouri's transportation infrastructure.
Topsoil / Stockpile
Thoughts on more information:
Photo credit: John Cooper
What would you do better?
Filter Sock: failed, not installed properly, not
trenched in
Silt fence: failed, not installed
Photo credit: John Cooper
5/10/2016 11
Solutions?
Tracking: not tracked properly, bare slope for a
bit – needs to be covered with vegetation; slopes good for ECB
Photo credit: John Cooper
Any concerns?
Tracking correctly, basin sized correctly
Slopes
……and then use berms to divert runoff, and
stabilized ditches or slope drains to carry stormwater down the slopes
5/10/2016 12
Checks
Rock can be used in larger
drainage areas and steeper ditch grades.
Depending on the size and
topography of the drainage area and steepness of the ditch, you may want to incorporate ECB/TRM in concert with the rock.
Streams
Our primary focus for erosion and sediment
control should be holding and capturing sediment BEFORE it enters waters of the state
Questions?
Remember: Minimize disturbed area Stabilize promptly and correctly Be prepared for the worst, hope for the best!
Valerie Hentges Environmental Specialist
Valerie.Hentges@modot.mo.gov
1
Eric Kopinski MoDOT Environmental
Environmental Regulations – Why?
- Clean Water Act – October 1972
−Point Sources – 1972 −Amendment - 1987 (Nonpoint Sources)
- EPA has authority of Clean Water Act
- In Missouri authority delegated to MDNR
EPA’s - Priority List
2 How powerful is the EPA?
- Strict Liability
−Driving Under the Influence (DUI) −Selling alcohol to minors −Clean Water Act (CWA)
- CWA Fines = $37,500 per violation per day
Consent Decree - Basics
- Consent Decree – An agreement or settlement to
resolve a dispute between two parties without admission of guilt (criminal) or liability (civil). −MSD St. Louis - $4.7 Billion −City of Kansas City MO - $2.5 Billion −City of Independence MO - $35 Million
Consent Decree – Region VII
3 Not Just DOTs
$3.1 Million and National Compliance System $1.3 Million and National Compliance System
EPA – MoDOT Project Inspections
- History of NOVs from DNR and EPA
- Route 67 – Wayne County
- Route 54 – Camden County
Lessons Learned – EPA Audits
- Inspections resulted from public complaints
- Large grading projects
- Intense rain events
- MoDOT’s documentation needed to be improved
4 MoDOT’s Consent Decree - Basics
- Any project > 1 acre on ROW SHALL comply
- Required to use self-reporting online database
- Potential for 15 stipulated penalties
- Duration of at least 3 years
- MoDOT pays one time civil penalty of $750,000
What is a project?
- “Project shall mean any location in the State of
Missouri where defendant engages in land disturbance activities of greater than one (1) acre.”
- Decree specifically between MoDOT and EPA
Projects – Decree Reporting
- Utilities – Projects > 1 acre
- Construction – Per project number, not contract ID
- Traffic Permits – ROW disturbance > 1 acre
- Maintenance – Keep work under one acre
- Local Roads/LPA – ROW impacts > 1 acre
- Lease Agreement – Level of involvement
5
Stipulated Penalty Summary 1 of 2
Rule Item Fine Amount 1 Decree point person (Kopinski’s role) $1,000 initial violation $750 for every 14 days 2 Assign MoDOT inspector & Contractor WPCM $750 initial violation $750 for every 14 days 3 Inspector, RE and WPCM need to be trained $750 initial violation $750 for every 14 days 4 Hold pre-construction conference $750 initial violation $250 every day 5 Create and distribute inspection protocol $750 per day 6 MoDOT performing weekly and runoff inspections $500 initial violation $100 every day 7 MoDOT inspection entered late $100 initial violation
Stipulated Penalty Summary 2 of 2
Rule Item Fine Amount 8 RE and WPCM both sign report within 3 days $250 initial violation 9 MoDOT oversight inspection when > 5 and either in 303(d) stream or T&E area $1,500 initial violation $250 every day 10 Failure to comply with permit or SWPPP $1,000 days 1-10 $2,500 days 11-20 $3,500 days 21+ 11 Failure to correct deficiencies (BMPs) $1,000 days 1-10 (day 8-17) $2,500 days 11-20 (day 18-27) $3,500 days 21+ (day 28+) 12 Failure to list deficiencies into database $200 per day per deficiency 13 RE 7 day review; Kopinski’s 14 day review $200 per day 14 Failure to submit spill report $750 initial violation $750 every 14 days
Money Details
- No federal funds can be used to pay fines
- All money is paid to US Treasury NOT EPA
- MoDOT’s expectations: $0
- Database testing period (4 month period): $359,000
in mock fines
6 Database Basics Stormwater System Design
User Expectation
Consent Decree Schedule
- Database testing rollout: July 15, 2015
- Database live: November 16, 2015
- Yearly reports: March of 2016, 2017 & 2018
- Termination scheduled date: July 20, 2018
- Only 788 days, 13 hours…….NOT that anyone is
counting
7 Construction – Potential Changes
- JSP for Consent Decree
- Utilize new products more often
- Remobilization pay item for hydroseeding
- Provide payment to repair items after significant
rain events
- Better document ponds and lakes
Design – Potential Changes
- Plan sheet changes – staging sheets
- RUSLE – Advanced design by west coast DOTs
- SELDM – USGS and FHWA developed
- Post rain event analysis
Future Technology – Pervious Pavements
- Piloted with limit success by MoDOT
- Technology is advancing
- Filters pollutants out of runoff (MS4)
- 1,500 gallons of water in 5 min ≈ 43” event
8 Future Technology - Focal Point Biofiltration
- Basin 1: 12,000sf → 240sf
- Basin 2: 3,037sf → 60sf
- Basin 3: 1,626sf → 40sf
- Basin 4: 2,055sf → 52sf
- Total: 18,718sf → 352sf (98%)
EPA – Future Interaction
Consent Decree – Formal Training
Date Location Room Time 5/26 CD – Jeff City District Office – Muri Room Noon – 4:30pm 6/14 SW – Springfield District Office – Conference Room #3 Noon – 4:30pm 6/29 SE – Sikeston District Office – SK Room Noon – 4:30pm
9 Additional Resources & Information
- Eric Kopinski
−Cell: 573.291.0364
−Desk: 573.751.2790 −E-mail: eric.kopinski@modot.mo.gov
- www.modot.gov/ld
- MoDOT’s EPG Section 800
Questions
MoDOT Utility Construction & Erosion Control Seminar Handout 5/11/2016 Section 1 – MoDOT Utility Installation Policy 1
Putting all the Pieces Together
A Sample Active Project with Panel Discussion
Final Questions? That’s All Folks!
Robert Rhodes, MoDOT Design – (816) 607-2233 Rick Orr, MoDOT Design – (816) 387-2483 Vernon Koch, MoDOT Traffic – (816) 607-2190 Valerie Hentges, MoDOT Environmental – (573) 526-4728 Eric Kopinski, MoDOT Environmental – (573) 751-2790 John Cooper, APWA KC Metro Chapter - (913) 577-8412 Ted Ingalls, APWA KC Metro Chapter – (913) 577-0071
with special thanks to
Visit kcmetro.apwa.net