energy solutions for a better world
Report on
Two Generation Expansion Alternatives
Board of Commissioners of Public Utilities N f dl d d L b d
p for the Island Interconnected Electrical System
Newfoundland and Labrador Date: February 15/2012
Two Generation Expansion Alternatives p for the Island - - PowerPoint PPT Presentation
energy solutions for a better world Report on Two Generation Expansion Alternatives p for the Island Interconnected Electrical System Board of Commissioners of Public Utilities N Newfoundland and Labrador f dl d d L b d Date: February
energy solutions for a better world
Report on
Board of Commissioners of Public Utilities N f dl d d L b d
Newfoundland and Labrador Date: February 15/2012
Estimating
Reliability Study
Standards
February 15, 2012 2
Introduction
"Th B d h ll i d t t G t h th th P j t t "The Board shall review and report to Government on whether the Projects represent the least-cost option for the supply of power to Island Interconnected Customers over the period of 2011-2067, as compared to the Isolated Island Option, this being the 'Reference Question'. In answering the Reference Question, the Board:
N l ' f t d ti f th I l d l d t l i Nalcor's forecasts and assumptions for the Island load, system planning assumptions, and the processes for developing and comparing the estimated costs for the supply of power to Island Interconnected Customers; and h ll th t f th P j t hi h i i f th
needs of the Province is not monetized or utilized, and therefore the Board shall not include consideration of the options and decisions respecting the monetization of the excess power from the Muskrat Falls generation facility, i l di th M iti Li k P j t ”
February 15, 2012 3
including the Maritime Link Project.”
Introduction
Th t i f th i th T G ti E i The report is a summary of the reviews on the Two Generation Expansion Alternatives for the Island Interconnected Electrical System. The two Generation Expansion Options were identified in the terms of p p reference, and are as follows:
Labrador Island Link HVdc Project and Labrador-Island Link HVdc Project, and
expansion plan. p p
February 15, 2012 4
Introduction
February 15, 2012 5
Introduction
RFP and Proposal are on Board s public website
February 15, 2012 6
Introduction
g g
February 15, 2012 7
Introduction
February 15, 2012 8
February 15, 2012
Options Reviewed
9
One Hydroelectric Plant (Portland Creek 23 MW)
S h C d C i t H l d (HTGS)
February 15, 2012 10
Options Reviewed
February 15, 2012
Options Reviewed
11
February 15, 2012 12
Options Reviewed
Holyrood Thermal Generating Station
Plant replaced with three 170 MW CCCTs, two in 2033 and one in 2036
S 170 MW CCCT
February 15, 2012 13
Options Reviewed
February 15, 2012
Options Reviewed
14
February 15, 2012 15
February 15, 2012 16
Review Methodology
February 15, 2012 17
Review Methodology
Discount Rates
PPA C t f S i A h f M k t F ll
February 15, 2012 18
Review Methodology
Nalcor’s Decision Gate Process
February 15, 2012 19
February 15, 2012 20
Project Screening and Cost Estimating
Source: Nalcor’s Final Submission, Volume 2, page 35
Class 5: +100% to -50%, Concept Screening Class 4: +50% to -30%, Study or Feasibility (DG2) Class 3: +30% to -20%, Budget Authorization (DG3) , g ( ) Class 2: +20% to -15%, Control or Bid/Tender Class 1: +15% to -10%, Check Estimate
February 15, 2012 21
Project Screening and Cost Estimating
February 15, 2012
Project Screening and Cost Estimating
22
February 15, 2012 23
Project Screening and Cost Estimating
Nalcor and their consultants categorize risks under two headings.
Evaluation of Design and Planning Aspects
etc etc.
Changes in Scope
g
February 15, 2012 24
Project Screening and Cost Estimating
February 15, 2012
Project Screening and Cost Estimating
25
February 15, 2012
Project Screening and Cost Estimating
26
February 15, 2012
Project Screening and Cost Estimating
27
February 15, 2012
Project Screening and Cost Estimating
28
MHI’s review of Nalcor’s Load Forecast
February 15, 2012 29
February 15, 2012 30
Load Forecast
sector or the number of housing starts
February 15, 2012
Load Forecast
31
February 15, 2012
Load Forecast
32
Q y gy y y
(CDM) programs
February 15, 2012 33
Load Forecast
February 15, 2012 34
Load Forecast
February 15, 2012 35
Load Forecast
February 15, 2012 36
Load Forecast
February 15, 2012
Load Forecast
37
February 15, 2012
Load Forecast
38
February 15, 2012 39
Load Forecast
February 15, 2012 40
Load Forecast
February 15, 2012 41
Load Forecast
February 15, 2012 42
Load Forecast
February 15, 2012 43
and energy requirements at all times, taking into account scheduled and reasonably expected unscheduled outages of system components.
withstand sudden disturbances such as electric short circuits or unanticipated loss of system components. For example, the loss of the HVdc Transmission line
February 15, 2012 44
Power System Reliability
February 15, 2012 45
Power System Reliability
performs annual LOLE studies for the region considering transmission restrictions.
Operator, Inc. utilities as part Midwest Reliability Organization or ReliabilityFirst Corporation,
the Western Electricity Coordinating Council (WECC)
February 15, 2012
Power System Reliability
46
Reinforcement Project,
y p g management in Ontario.
February 15, 2012
Power System Reliability
47
Interconnected Reliability”
y y ( )
February 15, 2012
Power System Reliability
48
February 15, 2012
Power System Reliability
49
February 15, 2012 50
Power System Reliability
February 15, 2012 51
Power System Reliability
February 15, 2012 52
Power System Reliability
February 15, 2012 53
Power System Reliability
February 15, 2012 54
February 15, 2012
AC Integration Studies
55
February 15, 2012 56
AC Integration Studies
February 15, 2012 57
AC Integration Studies
February 15, 2012
AC Integration Studies
58
Transmission Planning
February 15, 2012
AC Integration Studies
59
interconnection agreements NERC standards help define interconnection agreements. NERC standards help define these norms.
February 15, 2012
AC Integration Studies
60
facilities to operate the system under the new configuration MHI finds the absence of these st dies a major gap in
Nalcor’s work to date
and prepare for compliance to NERC Standards with or and prepare for compliance to NERC Standards with or without the Maritime link.
February 15, 2012
AC Integration Studies
61
February 15, 2012 62
February 15, 2012 63
Hydrology
February 15, 2012 64
Hydrology
February 15, 2012 65
Hydrology
capacity of 36 MW
capacity of 18 MW capacity of 18 MW
gy y capacity of 23 MW
February 15, 2012
Hydrology
66
February 15, 2012 67
Hydrology
Generation Plan
February 15, 2012 68
Muskrat Falls Development
Conceptual Drawing of Muskrat Falls Generating Station
February 15, 2012
Infeed Option
69
identify any factors that might preclude successful development of the site;
comprehensive as a basis for planning;
project cost estimates; and
February 15, 2012 70
Infeed Option
Assessed methods used to prepare cost estimates
p y 1998 and 2010. This can largely be explained by changes in scope and inflation.
February 15, 2012 71
Infeed Option
February 15, 2012 72
Infeed Option
February 15, 2012 73
Infeed Option
February 15, 2012 74
Infeed Option
February 15, 2012 75
Infeed Option
rating
(transient)
pole outage could not be supplied without a backup supply and could lead to load shedding or a possible black-out
February 15, 2012 76
Infeed Option
Henday CS is presented as an example. 2000 MW +/- 500 kV dc 230 kV ac
February 15, 2012 77
Infeed Option
condensers to support dc conversion and stabilize ac performance
condenser units condenser units
result of higher fault currents
February 15, 2012 78
Infeed Option
February 15, 2012 79
Infeed Option
February 15, 2012 80
Infeed Option
February 15, 2012 81
Infeed Option
Risk analysis should be completed prior to completion of finalization of specifications of HVdc Converter Stations post DG2
February 15, 2012 82
Infeed Option
February 15, 2012 83
Infeed Option
Connaigre Peninsulas
Icing on the Long Range Mountain Ridge”, 2009
2010
Ex 96 Evaluate Extreme Ice Loads From Freezing Rain for Newfoundland and Labrador Hydro”, 2010
Labrador – Island Transmission Link”, 2011
February 15, 2012 84
Infeed Option
level greater than that of the existing 230 kV ac system g g y
the 230 kV system which could down the HVdc line while all 230 kV lines are intact.
February 15, 2012 85
Infeed Option
February 15, 2012 86
Infeed Option
If the primary Outages of the transmission line could be lengthy. If the primary source of power, then rotating outages to interconnected customers could be a reality, if the worst case scenario occurs.
response plan. As an example, best utility practice response plan could include:
I t f t d t i l t
E i t it
contractors and manufacturers.
February 15, 2012 87
Infeed Option
February 15, 2012
Infeed Option
88
February 15, 2012 89
Infeed Option
in Canada
y year return period for critical single sourced power supply
alpine regions considering potential access problems p g g p p
an alternate supply is available
February 15, 2012
Infeed Option
90
February 15, 2012
Infeed Option
91
February 15, 2012 92
Infeed Option
Belle Isle
y y Belle Isle
Development Study p y
Cable Crossing Supply and Install
February 15, 2012
Infeed Option
93
February 15, 2012 94
Infeed Option
February 15, 2012 95
Infeed Option
February 15, 2012
Infeed Option
96
February 15, 2012
Infeed Option
97
February 15, 2012
Infeed Option
98
February 15, 2012
Infeed Option
99
February 15, 2012
Infeed Option
100
Generation Plan
February 15, 2012 101
February 15, 2012 102
Isolated Island Option
February 15, 2012
Isolated Island Option
103
February 15, 2012
Isolated Island Option
104
February 15, 2012 105
Isolated Island Option
February 15, 2012 106
Isolated Island Option
February 15, 2012 107
Isolated Island Option
February 15, 2012
Isolated Island Option
108
February 15, 2012 109
Isolated Island Option
February 15, 2012 110
Isolated Island Option
February 15, 2012 111
Isolated Island Option
Cumulative Present Worth
February 15, 2012 112
February 15, 2012
CPW Analysis
113
O i CPW A Option CPW Amount Isolated Island $ 8.8 billion Infeed $ 6.6 billion Differential $ 2.2 billion
February 15, 2012 114
CPW Analysis
PPA h id i t f t h k f ll i
implementation
plant plant
February 15, 2012 115
CPW Analysis
February 15, 2012 116
CPW Analysis
February 15, 2012 117
CPW Analysis
February 15, 2012 118
CPW Analysis
February 15, 2012 119
CPW Analysis
Discount Rate 8.0 % 17.1 % Isolated Island $ 8.8 $ 3.0 Infeed $ 6.6 $ 3.0 Differential $ 2.2 $ 0.0
February 15, 2012 120
CPW Analysis
Nalcor Study Based on DG2 Estimating Accuracy
System capital costs increased by 25%, the CPW differential in favour of Infeed Option would be reduced from differential in favour of Infeed Option would be reduced from $2.2 billion to $1.2 billion DG2 L l ti t h th t ti l f t ti t t
increase by as much as 50%
the two Options to essentially become equivalent
February 15, 2012 121
CPW Analysis
Option Base Case 25% 50%
Isolated Island
$ 8.8 $ 8.8 $ 8.8
Infeed
$ 6 6 $ 7 6 $ 8 6
Infeed
$ 6.6 $ 7.6 $ 8.6
Differential
$ 2.2 $ 1.2 $ 0.2
February 15, 2012 122
CPW Analysis
February 15, 2012 123
CPW Analysis
Option Base Case Plant Closure Option Base Case Plant Closure Isolated Island $ 8.8 $ 6.6 Infeed $ 6.6 $ 6.2 Diff ti l $ 2 2 $ 0 4 Differential $ 2.2 $ 0.4
February 15, 2012 124
CPW Analysis
February 15, 2012 125
CPW Analysis
Option Base Case
Low Price Forecast
Isolated Island $ 8.8 $ 6.2 Infeed $ 6.6 $ 6.1 Differential $ 2 2 $ 0 1 Differential $ 2.2 $ 0.1
February 15, 2012 126
CPW Analysis
Changes to risk areas acting in unison could have major impact
by 20%
by 10%
February 15, 2012
CPW Analysis
127
Scenario
Isolated Island Infeed Differential
1 Base Case $ 8.8 $ 6.6 $ 2.2 2 LIL Cap Cost Increase by 25% $ 8.8 $ 7.0 $ 1.8 3 MF Cap Cost Increase by 25% $ 8.8 $ 7.2 $ 1.6 4 LIL and MF C.Cost Increase 25% $ 8.8 $7.6 $ 1.2 5 Pulp and Paper Mill Closure $ 6.6 $ 6.2 $ 0.4 6 LIL and MF Cost Increase 50% $ 8 8 $ 8 6 $ 0 2 6 LIL and MF Cost Increase 50% $ 8.8 $ 8.6 $ 0.2 7 Fuel Cost Decrease 20% + Load Growth Decrease 20% + LIL & MF Cap Cost Increase 20% $ 7.0 $6.9 $ 0.1 8 Fuel Costs – Low Price Forecast $ 6.2 $ 6.1 $ 0.1 9 Plant Closure + LIL & MF Cap Cost Incrs 10% $ 6.6 $ 6.6 $ 0.0 10 Fuel Cost Decrease of 44% $ 6.1 $ 6.1 $ 0.0
February 15, 2012 128
CPW Analysis
February 15, 2012 129
CPW Analysis
continued operation of existing pulp and paper mill)
p ( )
February 15, 2012
CPW Analysis
130
Inclosing
February 15, 2012 131
February 15, 2012
Conclusions
132
February 15, 2012
Conclusions
133
February 15, 2012 134
Conclusions
February 15, 2012