miller children s hospital
play

Miller Childrens Hospital Pediatric Inpatient Addition Long Beach, - PowerPoint PPT Presentation

Miller Childrens Hospital Pediatric Inpatient Addition Long Beach, CA Presentation Outline Presentation Outline Electrical Breadth PV Panels Building Background System Sizing Existing Systems Summary Cost Estimate


  1. Miller Children’s Hospital Pediatric Inpatient Addition Long Beach, CA

  2. Presentation Outline Presentation Outline • Electrical Breadth – PV Panels • Building Background • System Sizing • Existing Systems Summary • Cost Estimate and Payback • Design Objectives • Electrical System Integration • Summary and Recommendation • Mechanical Depth – CHP • Conclusions • CHP Screening Process • Energy Analysis • Central Plant Redesign • Electrical System Integration • Cost Breakdown and Emissions • Summary and Recommendation

  3. Building Background • General Building Information Owner • Miller Children’s Hospital Building Background Building Background Presentation Outline Presentation Outline Project Size • 127,000 square feet • Building Building Background Background • Electrical Breadth – PV Panels • The Pediatric Inpatient Addition Total Cost • Existing Systems Summary • System Sizing - 4-Story Hospital Facility • Cost Estimate and Payback • $151,000,000 (estimated) • Design Objectives • Electrical System Integration - 7 Operating Rooms Design-bid-build • Mechanical Depth – CHP • Summary and Recommendation Completion Date Completion Date - Neonatal Intensive Care Unit Neonatal Intensive Care Unit • CHP Screening Process • Conclusions • Fall 2009 - Utilizes Green Roof System • Energy Analysis • Central Plant Redesign • Electrical System Integration • Cost Breakdown and Emissions • Summary and Recommendation

  4. Existing Systems Summary Existing Systems Summary Condenser Water Flow Diagram Chilled Water Flow Diagram Presentation Outline Presentation Outline Mechanical System Mechanical System • Building Background • Electrical Breadth – PV Panels • 7 Air Handling Units (located on roof) • System Sizing • Existing Existing Systems Systems Summary Summary • Constant Volume with Space Reheat • Cost Estimate and Payback • HEPA Filters Used for Operating Rooms • Design Objectives • Electrical System Integration • (2) 500 ton Centrifugal Water Cooled Chillers • Mechanical Depth – CHP • Summary and Recommendation • (2) Induced Draft Cooling Towers • Conclusions • CHP Screening Process • Energy Analysis • (2) 2,000 MBh Gas-Fired Hot Water Boilers • Central Plant Redesign • Electrical System Integration Hot Water • Cost Breakdown and Emissions Flow Diagram • Summary and Recommendation

  5. Existing Systems Summary Existing Systems Summary Electrical System Single Line Diagram Presentation Outline Presentation Outline Electrical System Electrical System • Building Background • Electrical Breadth – PV Panels • Electric Utility – Southern California Edison • System Sizing • Existing Existing Systems Systems Summary Summary • 480Y/277V 3-phase 4-wire secondary • Cost Estimate and Payback • (2) 750 kW emergency generators • Design Objectives • Electrical System Integration • 10,000 kW redundant transformer • Mechanical Depth – CHP • Summary and Recommendation - Miller Children’s Hospital Mill Child ’ H it l • Conclusions • CHP Screening Process - Does not serve loads • Energy Analysis - For future use and owner preference • Central Plant Redesign • Electrical System Integration • Cost Breakdown and Emissions • Summary and Recommendation

  6. Design Objectives Design Objectives Annual Energy Consumption Energy Consumption • Electricity - 5,900,000 kWh/year Presentation Outline Presentation Outline Main Objectives Main Objectives • Gas • Gas - 38,000 therms/year 38 000 therms/year • Building Background • Electrical Breadth – PV Panels Operational Costs • Reduce energy consumption • Existing Systems Summary • System Sizing • Save money in operational costs • Electricity - $1,100,000/year • Cost Estimate and Payback • Gas - $30,000/year • Design Objectives Design Objectives • Cut back on emissions • Electrical System Integration • Mechanical Depth – CHP • Summary and Recommendation Emissions (Utility Generated) Emissions (Utility Generated) • Conclusions • CHP Screening Process • NO X – 6,000 lbs/year • Energy Analysis • SO X – 5,000 lbs/year • Central Plant Redesign • Electrical System Integration • CO 2 – 3,800 lbs/year • Cost Breakdown and Emissions • Summary and Recommendation

  7. Mechanical Depth Mechanical Depth Combined Heat & Power Combined Heat & Power Energy Costs and Consumption Energy Costs and Consumption Presentation Outline Presentation Outline CHP Screening Process CHP Screening Process • Building Background • Electrical Breadth – PV Panels • Spark Spread • Existing Systems Summary • System Sizing -The difference between electricity and • Cost Estimate and Payback • Design Objectives gas rates in $/MMBtu • Electrical System Integration General Factors Affecting CHP • Mechanical Mechanical Depth Depth – – CHP CHP - Higher spread favors CHP • Summary and Recommendation • Conclusions • Cost of electricity ( > $0.05/kWh) • CHP Screening Process CHP Screening Process • Energy Analysis • Cost of gas( < $4.00/MMBtu) • Central Plant Redesign • Electrical System Integration • Cost Breakdown and Emissions • Summary and Recommendation

  8. Mechanical Depth Mechanical Depth Combined Heat & Power Combined Heat & Power Electric Load Profiles Presentation Outline Presentation Outline Energy Analysis Energy Analysis • Peak Electric Load • Building Background • Electrical Breadth – PV Panels - September 6 at 5:00 pm • Existing Systems Summary • System Sizing • Cost Estimate and Payback - 900 kW • Design Objectives • Electrical System Integration • Peak Heating Load • Mechanical Mechanical Depth Depth – – CHP CHP • Summary and Recommendation - January 1 at 7:00 am (T OA = 40°F) • Conclusions • CHP Screening Process -1,700 MBh • Energy Analysis Energy Analysis • Central Plant Redesign • Peak Cooling Load • Electrical System Integration - September 6 at 5:00 pm (T OA = 91°F) • Cost Breakdown and Emissions • Summary and Recommendation - 225 tons

  9. Mechanical Depth Mechanical Depth Combined Heat & Power Combined Heat & Power Caterpillar Reciprocating Engine Caterpillar Reciprocating Engine Presentation Outline Presentation Outline Energy Analysis Energy Analysis • Building Background • Peak Electric Load – 900 kW • Electrical Breadth – PV Panels • Existing Systems Summary • System Sizing - 15% over-sizing • Cost Estimate and Payback - 1,035 kW generator required • Design Objectives • Electrical System Integration • Use reciprocating engine • Mechanical Mechanical Depth Depth – – CHP CHP • Summary and Recommendation - Little heating needed Little heating needed • Conclusions • CHP Screening Process • Cannot use absorption cooling • Energy Analysis Energy Analysis - Generator size too small • Central Plant Redesign • Electrical System Integration • Generator Operation Condition • Cost Breakdown and Emissions - Demand output • Summary and Recommendation

  10. Mechanical Depth Mechanical Depth Combined Heat & Power Combined Heat & Power CHP System Schematic and Annual Energy Use Presentation Outline Presentation Outline Energy Analysis Energy Analysis • Building Background • Recovered Heat Energy • Electrical Breadth – PV Panels • Existing Systems Summary • System Sizing • System Schematic • Cost Estimate and Payback • Design Objectives • Electrical System Integration • Mechanical Depth Mechanical Depth - - CHP CHP • Summary and Recommendation • Conclusions • CHP Screening Process • Energy Analysis Energy Analysis • Central Plant Redesign • Electrical System Integration • Cost Breakdown and Emissions • Summary and Recommendation

  11. Mechanical Depth Mechanical Depth Combined Heat & Power Combined Heat & Power Existing Central Plant CHP Plant Redesign Presentation Outline Presentation Outline Central Plant Redesign C t l Pl t R d i • Building Background • Located north of the Pediatric Inpatient • Electrical Breadth – PV Panels • Existing Systems Summary • System Sizing Addition • Cost Estimate and Payback • Design Objectives • Comprised of: • Electrical System Integration • Mechanical Mechanical Depth Depth – – CHP CHP • Summary and Recommendation - Pump Room - Chiller Room • Conclusions • CHP Screening Process - Electrical Switchgear • Energy Analysis Central Plant Area = 4,700 sq. ft. New Central Plant Area = 5,880 sq. ft. - Emergency Generator Room • Central Plant Redesign Central Plant Redesign 25% Increase • Electrical System Integration -Transformer Yard • Cost Breakdown and Emissions • New Generator Room – 1,180 sq. ft. • Summary and Recommendation

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend