Project Intent:

  • Provide wayfinding for Ground Transportation destinations (Terminal-wide) located on multiple levels.
  • Rental Car Center
  • Metro-Rail
  • Metro-Bus
  • Tri-Rail
  • Greyhound/Megabus
  • Hotel Shuttles
  • Taxis
  • Shared Vans
  • Amtrak (Future)
  • Provide pedestrian wayfinding route from Baggage Claim and North Terminal International Arrivals,

Level 1, to the MIA Mover, Level 3. Routes include:

  • Escalators
  • Elevators
  • Moving walkways
  • Bridges
  • Existing overhead wayfinding system could not physically support additional text and graphics
  • Stand Alone Trail Blazing
  • Adopt color code for Miami Intermodal Center (MIC) - Magenta

Introduction MIA MOVER

slide-3
SLIDE 3

Introduction MIA MOVER Level 1

  • Taxi
  • Shared Vans

Level 2

  • Hotel Shuttles

Level 3

  • MIA Mover to:
  • Rental Car Center
  • Metrorail
  • Metrobus
  • Tri-rail
  • Greyhound
  • Megabus
  • Amtrak (Future)

Ground Transportation Distribution

slide-4
SLIDE 4

Conceptual Design – 3 Sign Types MIA MOVER ST-175

  • 26.25” x 84”
  • Wall Mounted
  • Single-sided
  • Aluminum &

Stainless Steel

  • 2 Units

ST-186

  • 26.25” x 84” +

50.5” x 96”

  • Wall-mounted,

single & double-sided

  • Aluminum &

Stainless Steel

  • 16 Units

ST-134

  • 26.25” x 84”
  • Floor Mounted
  • Double-sided
  • Aluminum &

Stainless Steel

  • 130 Units
slide-5
SLIDE 5

Walk-Thru Example Final Implementation – Baggage Claim (Level 1)

Level 1

Baggage Claim

  • 44 Units
slide-6
SLIDE 6

Walk-Thru Example Final Implementation – Baggage Claim (Level 1)

slide-7
SLIDE 7

Walk-Thru Example Final Implementation – Departures (Level 2)

Level 2

Departures

  • 40 Units
slide-8
SLIDE 8

Walk-Thru Example Final Implementation – Departures (Level 2)

slide-9
SLIDE 9

Walk-Thru Example Final Implementation – Departures (Level 2)

slide-10
SLIDE 10

Walk-Thru Example Final Implementation – Departures (Level 2)

slide-11
SLIDE 11

Walk-Thru Example Final Implementation – Departures (Level 2)

slide-12
SLIDE 12

Walk-Thru Example Final Implementation – Moving Walkway & Bridges (Level 3)

Level 3

Moving Walkway & Bridges

  • 51 Units
slide-13
SLIDE 13

Walk-Thru Example Final Implementation – Moving Walkway & Bridges (Level 3)

slide-14
SLIDE 14

Walk-Thru Example Final Implementation – Moving Walkway & Bridges (Level 3)

slide-15
SLIDE 15

Walk-Thru Example Final Implementation – Moving Walkway & Bridges (Level 3)

slide-16
SLIDE 16

Walk-Thru Example Final Implementation – Moving Walkway & Bridges (Level 3)

slide-17
SLIDE 17

Walk-Thru Example Final Implementation – Rental Car Center (MIC)

MIC

  • Miami

Intermodal Center

  • Rental Car

Center

  • 13 Units