Market Renewal Discussion with the Ontario Waterpower Association - - PowerPoint PPT Presentation
Market Renewal Discussion with the Ontario Waterpower Association - - PowerPoint PPT Presentation
Market Renewal Discussion with the Ontario Waterpower Association February 26, 2018 Disclaimer This presentation and the information contained herein is provided for information and discussion purposes only. This presentation does not
- This presentation and the information contained herein is provided
for information and discussion purposes only. This presentation does not constitute, nor should it be construed to constitute, legal advice or a guarantee, representation or warranty on behalf of the
- IESO. In the event of any conflict or inconsistency between the
information contained in this presentation and the Market Rules, the Market Manuals, any IESO contract or any applicable legislation or regulation, the provisions of the Market Rules, Market Manuals, contract, legislation or regulation, as applicable, govern.
Disclaimer
2
Today’s discussion will include:
- Recap of Market Renewal
- Focused discussion on cascade hydro participation in a day-ahead
market
- Update on work related to non-emitting resources
Overview
3
- Market Renewal is an ambitious set of initiatives which
will amount to a fundamental redesign of Ontario’s electricity markets and prepare us for future change
- Although our current design has served Ontario well,
the demands of a modern grid are evolving rapidly
- Reforms are required today in order for the IESO to
continue to manage the grid reliably and cost effectively
- IESO vision is a market with transparent prices for the
services needed to meet system needs
Market Renewal
4
Mission and Guiding Principles
5
Mission
MRP
Scoping Market Renewal
6
An ENERGY workstream A CAPACITY workstream
- Single Schedule Market
- Day Ahead Market
- Real Time Unit
Commitment
- Incremental Capacity
Auction
- More Frequent Intertie Scheduling and other Operability/Flexibility projects
will be explored as part of a broader conversation on the Future of Ontario’s Electricity Market
- The IESO will also continue to explore near-term market enhancement
projects that are consistent with MRP
Single Schedule Market
7
Replace Ontario’s two schedule system with a single schedule market that better aligns price with dispatch
Reduced complexity unlocks
- ther design
changes Improved price signals increase efficiency of dispatch and investments Reduced complexity unlocks
- ther design
changes investments Improved price signals increase efficiency of dispatch and investments Together, these outcomes will reduce the production cost of electricity
Day-Ahead Market
8
- A new market allowing suppliers/consumers to lock into
guaranteed prices for supply/consumption a day ahead of when it is required What is changing?
- Efficient way of improving operational certainty for system
- perators as real-time approaches
- Improves financial certainty for dispatchable resources
- Establishes a hedge against price volatility in the real-time
market caused by changes in supply and demand What are the benefits?
Incremental Capacity Auction
9
Incremental
- Will secure
resources to meet system adequacy needs that are not met by contract or rate regulation
- Contracted and
regulated capacity will not be eligible to participate
- Will secure
resources to meet system adequacy needs that are not met by contract or rate regulation
- Contracted and
regulated capacity will not be eligible to participate Capacity
- Will procure a single
uniform capacity product
- Other products and
services will be incentivized via
- ther revenue
streams
- Will procure a single
uniform capacity product
- Other products and
services will be incentivized via
- ther revenue
streams Auction
- A stable long-term
mechanism that will secure capacity in a technology agnostic manner from diverse resource types
- Fundamental
change in risk allocation from contract paradigm
- A stable long-term
mechanism that will secure capacity in a technology agnostic manner from diverse resource types
- Fundamental
change in risk allocation from contract paradigm
- New market design will require new approaches to participating in the
IESO administered markets
- OWA members will need to understand key changes and can explore new
- pportunities
Key Considerations for OWA Members
Areas of Interest for OWA Members
10
Location Marginal Pricing (LMP)
- Nodal pricing for MP
suppliers; price variations across ON
- Non-MP supplier
pricing determined by OEB
Contract Amendments
- Amendments
required but IESO not aiming to extract value from contracts
ICA- All resource types will
participate in competitive auction
- Auction timelines,
- bligations, and
capacity qualification
- f interest to
OWA
DAM
- Obligations and
implications for energy limited resources of interest to OWA
11
QUESTIONS & COMMENTS
12
DAY-AHEAD MARKET
CASCADE HYDRO PARTICIPATION
- Cascade hydro systems have ponding capabilities and complex
intertemporal relationships governing their output that can be difficult to model
- The existing Day Ahead Commitment Process (DACP) design
recognized this problem and addressed it by allowing cascade resources to resubmit their offers after the first run of DACP in
- rder to correct any infeasible schedules prior a second and final
run of DACP.
Current Day Ahead Scheduling Process
13
G1 G2 G3 4 hrs 2 hrs
Current DACP & Transitioning Issues
14
All Resources Submit Offers (Quantities at Prices)
Initial Submission Window 06:00 – 10:00
Initial Resource Schedules Published
Initial Run of DACP 10:00 - 11:00
Cascade Hydro Revise and Resubmit Offers as Needed
Resubmission Window (11:00 – 12:00)
Final Resource Schedules Published
Final Run of DACP (12:00 - 13:00)
- While this is an appropriate solution for non-financially binding
DACP, retaining the resubmission window under a financially binding day-ahead market (DAM) would provide one group of participants the potential to improve their own financial positions but harm others’
All Resources Submit Offers DAM Submission Window 06:00 – 09:00 Resource Schedules and Prices Published DAM Execution 09:00 - 12:30
- With no resubmission window
available under a future DAM, cascade hydro resources may receive financially binding DAM schedules that are
- perationally infeasible
- This can create financial risk
because undelivered day- ahead schedules may have to be bought back at higher real- time prices
Problem Statement
15
Two Settlement Mechanics
16
Day Ahead
QDA x $DA
Real-Time (Balancing)
(QRT – QDA) x $RT
Real-time deviations from day-ahead obligations must be bought or sold back at real-time prices.
DAM Schedule Real-Time Output
- Responsibility for managing operational and financial risk lie with
the market participant – Participants are in the best position to most efficiently manage these risks – Typically managed through their offer curve submissions
- Ways in which system operators assist cascade resources and other
resource technologies in mitigating some of their operational and financial risk include: – Offer requirements (market rules) – Modelling generic offer parameters that participants can couple with their offer curves
Key Observations in Other Markets
17
- Cascade resources typically manage their operating characteristics
through their offer curves – Offer desired quantities at lower prices and undesired quantities at higher prices, for example:
- These base strategies are used in other DAMs with cascade hydro
penetration similar to Ontario (i.e. New York and California)
Typical Offer Strategies
18
G1 G2 G3 4 hrs 2 hrs
G1 for 4 hrs at low $ G2 + G3 for 4 hrs at high $ G1 for 2 hrs at high $ G2 for 2 hrs at low $ G3 for 2 hrs at high $ Dispatchable (Flexible) Strategy Illustration
- Offers strategies can also be used to exercise market power and the
DAM will include features designed to mitigate these behaviours:
- While these measures are necessary, they may further limit a
cascade resource’s ability to generate feasible DAM schedules through their offer curves
Dispatchable Strategy: Potential Barriers
19
Behaviour Mitigation Physically withholding supply in
- rder to increase margins for other
remaining supply. Must Offer Requirements – the minimum quantity a resource must
- ffer into the DAM
Economically withholding supply by offering at very high prices when you’re one of the only resources available. Reference Levels – price caps that replaces the offer price of a resource when it is deemed to be economically withholding
- Assuming G1 only wants to clear 50 MW in the DAM to respect
downstream needs for G2 (anything more considered infeasible)
- Without mitigation, G1 could offer no more than 50 MW into DAM
- However with mitigation, G1 is at a greater risk of receiving an
infeasible schedule above 50 MW
Dispatchable Strategy: Potential Barriers
20
Desired Schedule
30 200 50 100 G1 offer prices ($) G1 capability (MW)
Barrier 2: Reference level (price cap) of $120 G1 may be scheduled to an infeasible schedule of 100 MW if clearing prices exceed the reference level Barrier 1: Must offer requirement of at least 80 MW G1 offers 1st 50 MW low and next 50 MW high
Market power mitigation design may limit the extent to which offer curves can be used to respect operating characteristics for cascade resources
- Cascade resources can also couple additional parameters with their
- ffer curves to minimize the risk of an infeasible DAM schedule:
– Daily Energy Limits (do not schedule > X MWh per day) – Forbidden Regions (do not schedule between X MW and Y MW)
- The NordPool (Norway) DAM has a much larger penetration of
hydro (~95%) and provides participants with the ability to link offer curves between resources
Dispatchable (Flexible) Strategy
21
G1 G2 G3 4 hrs 2 hrs
G1 offer must first be economic for G2 and G3 offers to be considered
- Linked offer capabilities are available to all participants (i.e.
technology neutral) – Gas resources can also use this feature to link their gas and steam unit dependencies
- Linked offers can be more easily accommodated because their day
ahead market engine is less complex – Less processing time needed because they do not account for the same level of transmission constraints that North American markets are required to account for in determining day ahead market schedules
The NordPool Market
22
- Cascade resources could alternatively choose to self-schedule their
resources in the DAM in order (non-dispatchable strategy) – Submit fixed quantities irrespective of price, for example:
- This strategy is used by cascade hydro in the PJM market, however
their hydro penetration is < 5%
Alternative Offer Strategies
23
G1 G2 G3 4 hrs 2 hrs
Self Scheduled (Inflexible) Strategy Illustration G1 for 4 hrs at X MW G2 + G3 for 4 hrs at 0 MW G1 for 2 hrs at 0 MW G2 for 2 hrs at X MW G2 for 2 hrs at 0 MW
- Self scheduling strategies also create risk for both the market
participant and the IESO – Market participant becomes a price taker, which still leaves them financially exposed because they have no ability to respond to lower prices that may not cover marginal costs – IESO loses the flexibility that dispatchable resource can provide in managing forecast uncertainty and providing standby energy (operating reserve) – Market outcomes are more costly because they are less efficient
- The market design should not incentivize cascade resources to
participate as self-schedulers
Self Schedule (Inflexible) Strategy
24
Aiming for a Flexible Offer Strategy
25
- IESO will be working with stakeholders to implement a solution
that allows cascade resources to participate in the day-ahead market within an acceptable level of risk.
- Potential solutions include but are not limited to:
– Striking a balance between Must Offer Requirements and Reference Levels for Mitigation – Retaining the ability for Daily Energy Limits and Forbidden Regions to be submitted and optimized by the DAM engine – Introducing additional features such as linked offers
- Break Out Group 1 (Non Market Participants)
– Address questions about the problem statement and potential issues – Discuss how non-market participants may be impacted by the potential barriers and solutions
- Break Out Group 2 (Market Participants)
– Address questions about the problem statement and potential issues – Discuss offer strategies that may introduce additional barriers – Discuss offer strategies that may offer potential solutions – Discuss the pros and cons of potential solutions
Break Out Sessions & Discussion
26
27
NON-EMITTING RESOURCE UPDATE
- To provide an update on work related to non-
emitting resources
- Discussion will include:
– Non-emitting Resource Subcommittee (NERSC) – Upcoming Technical Conference – Non-emitting resource Request for Information
Purpose
Non-Emitting Resource Subcommittee
29
- The subcommittee will ensure the characteristics of non-emitting
resources are reflected in Market Renewal and the future market
- The committee will develop a report for Q3/4 2018 that explores:
1. Participation: barriers to participation for non-emitting resources in the proposed Market Renewal design 2. Market Efficiencies: impact of higher levels of non-emitting resources with very low to zero marginal costs 3. Commercial Mechanisms: the potential for incentive mechanisms to value environmental attributes
- The group has finalized a scope of work, established a work plan, and is
working through Focus Area 1: Participation
- For OWA members participating in the NERSC, what feedback do you
have on process to date?
- Next NERSC meeting will be a technical conference, with unique
format
- A venue for stakeholders to:
– Provide information on technical capabilities, key barriers, and the value that their resource can provide – Engage in dialogue with the IESO on these topics – Consider learnings from other jurisdictions on these topics
- Builds on key takeaways from NERSC work to date
- Brings discussion to a broader audience
- Enables fulsome responses to the RFI
Technical Conference
30
How does the Technical Conference fit in?
31
Pre-conference
Brainstorming at the NERSC of barriers and potential solutions in Ontario
Technical Conference
Focused discussions on barriers and learnings from external jurisdictions
Post conference
Detailed responses to the RFI Additional Research for IESO Outcomes for the NERSC 1. Help complete Participation phase of the work plan 2. Set the stage for the Market Efficiencies phase 3. Provide input for Market Renewal and potential future market evolution
The conference will have a formal registration process which will be communicated to stakeholders shortly
Technical Conference: Logistics
32
When will it take place?
- April 5th
- 8:30 am – 4:30 pm
Where will it take place?
- Metro Toronto Convention Centre (MTCC)
- Modest fee to be charged
Who is expected to participate?
- Participants of the NERSC and other non emitting resources
- Potential respondents to the IESO’s non emitting resource RFI
- Government and other interested stakeholders
- Anticipating 150 attendees
1. Focus on stakeholder presentations and discussion
– Stakeholder presentations on resource value and key barriers – Facilitated discussion with IESO experts on barriers and potential solutions – External perspectives on stakeholder presentations – Questions from the audience
2. Learning from other jurisdictions
– Case studies on challenges and opportunities with integrating NERs in other jurisdictions
3. Tying it together
– How does the day fit into the bigger picture – How will we build on the information from the day
Technical Conference: Proposed Format
33
- IESO will work with stakeholders to develop presentations and
discussion topics for the day
Technical Conference: Stakeholder Presentations
34
1.5 hour panel discussions
Stakeholder Presentations Panel Discussion Audience Comments
- Have identified potential presenters
from hydro, wind, solar, storage, DR, and DER communities
- How can we get the most out of the
panel discussions and audience comments?
- Are there specific topics OWA members
would like included in the day?
The IESO is in the early stages of a two phased RFI, which aims to gather information on non emitting resources and broaden the IESO’s understanding of:
Request for Information (RFI)
35
Technical Characteristics and Operating Capabilities
Of existing resources and potential projects (e.g., energy, capacity, and essential reliability services, regional or locational system benefits)
Potential Barriers and Mitigating Options
For participating in the IESO’s current and future markets, and ultimately, contributing to a reliable and efficient Ontario electricity system
Supports the Market Renewal Program (MRP) by gathering information on: – Current and future market opportunities and challenges – Technical characteristics of a resource or potential project – Products and services that can be provided Also focused on potential revenue streams under the MRP and other current IESO administered markets, including: – Incremental Capacity Auction – Energy markets (including the development of the single schedule market) – System flexibility and ancillary services
RFI Phase 1
36
Phase I - Technical and Market Information
Requested information will likely include : – Financial and commercial considerations – Project development requirements and considerations – Indicative project capital and operating costs – Additional technical information, as may be required to fully understand a given project or technology
- Phase 1 responses will be used to further tailor Phase 2
- Phase 2 is expected to be launched in August/September 2018
RFI Phase 2
37
Phase II – Project Costing and Information
Phase I Timeline and Submissions
38
February 16 Draft Phase 1 RFI posted for stakeholders comment IESO responses to initial RFI feedback posted March 2 Written feedback due on draft Phase 1 RFI at engagement@ieso.ca March 19 Post final Phase 1 RFI May 2 Phase 1 RFI submission deadline May to August 2018 Evaluate Phase 1 responses and design draft Phase 2 RFI
- The draft Phase 1 RFI is available at:
http://www.ieso.ca/-/media/files/ieso/document-library/working-group/market- renewal/ner-rfi-20180216-presentation.pdf?la=en
- Once finalized, RFI submissions to be sent to engagement@ieso.ca by the submission
deadline (May 2, 2018).
RFI and Market Renewal
39
- Phase 1 of the RFI will support the work of the non-emitting resource sub-
committee (NERSC)
Future Evolution RFI NERSC
- Phase 2 will inform the next steps that
follow from NERSC
- NERSC technical conference will help
respondents submit complete responses to phase 1 of the RFI
- Phase 1 RFI responses will inform research
- n barriers to participation and exploration
- f market efficiencies
- RFI can also support other IESO initiatives
(e.g., the LTEP implementation)
RFI and NERSC Timelines
40
NERSC, RFI and the Big Picture
41
Market Renewal Stakeholder Engagements High-Level Designs NERSC RFI Phase 1 RFI Phase 2
2018 2019
Detailed Design Future Evolution
HLD INTEGRATION
Other IESO- and Sector-Lead Initiatives
42
QUESTIONS & COMMENTS
43