Marcus M. Morgenstern DGS-RP-AS LIU-PSB meeting
- June 18th, 2015 -
Marcus M. Morgenstern DGS-RP-AS LIU-PSB meeting - June 18 th , 2015 - - PowerPoint PPT Presentation
Marcus M. Morgenstern DGS-RP-AS LIU-PSB meeting - June 18 th , 2015 - Introduction Updated study previously performed by J. Blaha (2013) Updates include: Dump geometry Shielding geometry Aim: Study radiological
Marcus M. Morgenstern DGS-RP-AS LIU-PSB meeting
Radiological study for HSTS @ L4 – M. M. Morgenstern DGS-RP - 2015-06-18 2
requirements
shielding – done
Radiological study for HSTS @ L4 – M. M. Morgenstern DGS-RP - 2015-06-18 3
Radiological study for HSTS @ L4 – M. M. Morgenstern DGS-RP - 2015-06-18 4
Installation of HSTS
Radiological study for HSTS @ L4 – M. M. Morgenstern DGS-RP - 2015-06-18 5
Linac2
Radiological study for HSTS @ L4 – M. M. Morgenstern DGS-RP - 2015-06-18 6
YETS….)
as a Simple Controlled Radiation Area 363
Radiological study for HSTS @ L4 – M. M. Morgenstern DGS-RP - 2015-06-18 7
Exclusion area
Radiological study for HSTS @ L4 – M. M. Morgenstern DGS-RP - 2015-06-18 8
Fences have been installed
Radiological study for HSTS @ L4 – M. M. Morgenstern DGS-RP - 2015-06-18 9
available
high) on RAMSES
5 – 10 µSv (PAXLN202)
tunnel
Linac 2
Radiological study for HSTS @ L4 – M. M. Morgenstern DGS-RP - 2015-06-18 10
Radiological study for HSTS @ L4 – M. M. Morgenstern DGS-RP - 2015-06-18 11
Radiological study for HSTS @ L4 – M. M. Morgenstern DGS-RP - 2015-06-18 12
Thanks to Filippo Stefanini
FLUKA model
Downstream shielding Trolley Concrete shielding SSS shielding
Core/Jacket/Cooling
Radiological study for HSTS @ L4 – M. M. Morgenstern DGS-RP - 2015-06-18 13
Used for prompt dose rate calculation Maximum dose rate during day time
Radiological study for HSTS @ L4 – M. M. Morgenstern DGS-RP - 2015-06-18 14
Z [cm]
10500 − 10000 − 9500 − 9000 − 8500 −
Y [cm]
4000 4500 5000 5500 6000 6500
Sv/h] µ Prompt dose rate [
2 −10
1 −10 1 10
210
310
410
510
610
710
810
Z [cm]
10500 − 10000 − 9500 − 9000 − 8500 −
Y [cm]
4000 4500 5000 5500 6000 6500
Sv/h] µ Prompt dose rate [
2 −10
1 −10 1 10
210
310
410
510
610
710
810
Z [cm]
10400 − 10200 − 10000 − 9800 − 9600 − 9400 − 9200 − 9000 −
Y [cm]
2500 3000 3500 4000 4500 5000
Sv/h] µ Prompt dose rate [
2 −10
1 −10 1 10
210
310
410
510
610
710
810
Linac4 tunnel Linac4/Linac2 junction
@Linac2 amplifier gallery @Linac2 level
accessible during Linac4 operation
shielding sufficiently reduces dose from main dump, but doesn’t cover internal dump
seems similar to previous study, though detailed evaluation of profiles necessary to provide final answer of classification
Radiological study for HSTS @ L4 – M. M. Morgenstern DGS-RP - 2015-06-18 15
Z [cm]
10400 − 10200 − 10000 − 9800 − 9600 − 9400 − 9200 −Y [cm]
2600 2800 3000 3200 3400 3600 3800 4000Sv/h] µ Residual dose rate [
5 − 10 4 − 10 3 − 10 2 − 10 1 − 10 1 10 2 10 3 10 4 101m cooling time
Z [cm]
10400 − 10200 − 10000 − 9800 − 9600 − 9400 − 9200 −Y [cm]
2600 2800 3000 3200 3400 3600 3800 4000Sv/h] µ Residual dose rate [
5 − 10 4 − 10 3 − 10 2 − 10 1 − 10 1 10 2 10 3 10 4 101d cooling time
Z [cm]
10400 − 10200 − 10000 − 9800 − 9600 − 9400 − 9200 −Y [cm]
2600 2800 3000 3200 3400 3600 3800 4000Sv/h] µ Residual dose rate [
5 − 10 4 − 10 3 − 10 2 − 10 1 − 10 1 10 2 10 3 10 4 101h cooling time
Z [cm]
10400 − 10200 − 10000 − 9800 − 9600 − 9400 − 9200 −Y [cm]
2600 2800 3000 3200 3400 3600 3800 4000Sv/h] µ Residual dose rate [
5 − 10 4 − 10 3 − 10 2 − 10 1 − 10 1 10 2 10 3 10 4 106m cooling time
Z [cm]
10400 − 10200 − 10000 − 9800 − 9600 − 9400 − 9200 −Y [cm]
2600 2800 3000 3200 3400 3600 3800 4000Sv/h] µ Residual dose rate [
5 − 10 4 − 10 3 − 10 2 − 10 1 − 10 1 10 2 10 3 10 4 101w cooling time
Z [cm]
10400 − 10200 − 10000 − 9800 − 9600 − 9400 − 9200 −Y [cm]
2600 2800 3000 3200 3400 3600 3800 4000Sv/h] µ Residual dose rate [
5 − 10 4 − 10 3 − 10 2 − 10 1 − 10 1 10 2 10 3 10 4 108h cooling time
needed for exact numbers
Radiological study for HSTS @ L4 – M. M. Morgenstern DGS-RP - 2015-06-18 16
profiles) are required to get final conclusion on impact of updated shielding
updated shielding (~1-2 weeks)
beam dump
runs smoothly, final results are expected in a few weeks time scale