Manukau Harbour Crossing Alliance Rimu Rd Bridge Construct South - - PowerPoint PPT Presentation
Manukau Harbour Crossing Alliance Rimu Rd Bridge Construct South - - PowerPoint PPT Presentation
Manukau Harbour Crossing Alliance Rimu Rd Bridge Construct South Half of Bridge Gain access from SH20 NB lanes to construct temporary piles/ pavement and permanent piles on the north western side of Rimu Rd Bridge. Site access also from
Legend
TL3 barriers and screens Crash cushion
Gain access from SH20 NB lanes to construct temporary piles/ pavement and permanent piles on the north western side of Rimu Rd Bridge. Site access also from western side of temporary Rimu Rd to gain entry to the remaining western abutment construction Gain access from Crawford St to construction zone on the south western side of Rimu bridge Central median to be pulled out and replaced with temporary TL3 barrier. This temporary barrier will enable us to shift NB and SB lanes laterally to produce construct space when constructing new bridge piers
Rimu Rd Bridge – Construct South Half of Bridge
Pavement Design Adopted
25mm OGPA or 30mm SMA 35mm AC 14 55mm AC 20 Emulsion Prime coat 220mm – 320mm 4% Cement Treated Basecourse 300mm Stabilised Subgrade
Cement Treated Basecourse Production
Water Aggregate Cement Mixing Bowl Control Box Conveyor
Cement Treated Basecourse Construction
Asphalt Paving
70% 78% 77% 77% 77% 81% 73% 79% 82% 72% 68% 75% 68% 86% 80% 82% 79% 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
MHX MW Team - Percent of Planned Activities Completed (All Groups)
Very Wet Period
4 10 3 10 9 14 44 8 21 44 10 2 5 10 15 20 25 30 35 40 45 50 Total No. to Date for Each Reason