Manukau Harbour Crossing Alliance Rimu Rd Bridge Construct South - - PowerPoint PPT Presentation

manukau harbour crossing alliance
SMART_READER_LITE
LIVE PREVIEW

Manukau Harbour Crossing Alliance Rimu Rd Bridge Construct South - - PowerPoint PPT Presentation

Manukau Harbour Crossing Alliance Rimu Rd Bridge Construct South Half of Bridge Gain access from SH20 NB lanes to construct temporary piles/ pavement and permanent piles on the north western side of Rimu Rd Bridge. Site access also from


slide-1
SLIDE 1

Manukau Harbour Crossing Alliance

slide-2
SLIDE 2

Legend

TL3 barriers and screens Crash cushion

Gain access from SH20 NB lanes to construct temporary piles/ pavement and permanent piles on the north western side of Rimu Rd Bridge. Site access also from western side of temporary Rimu Rd to gain entry to the remaining western abutment construction Gain access from Crawford St to construction zone on the south western side of Rimu bridge Central median to be pulled out and replaced with temporary TL3 barrier. This temporary barrier will enable us to shift NB and SB lanes laterally to produce construct space when constructing new bridge piers

Rimu Rd Bridge – Construct South Half of Bridge

slide-3
SLIDE 3
slide-4
SLIDE 4
slide-5
SLIDE 5
slide-6
SLIDE 6

Pavement Design Adopted

25mm OGPA or 30mm SMA 35mm AC 14 55mm AC 20 Emulsion Prime coat 220mm – 320mm 4% Cement Treated Basecourse 300mm Stabilised Subgrade

slide-7
SLIDE 7

Cement Treated Basecourse Production

Water Aggregate Cement Mixing Bowl Control Box Conveyor

slide-8
SLIDE 8

Cement Treated Basecourse Construction

slide-9
SLIDE 9

Asphalt Paving

slide-10
SLIDE 10
slide-11
SLIDE 11
slide-12
SLIDE 12
slide-13
SLIDE 13
slide-14
SLIDE 14
slide-15
SLIDE 15
slide-16
SLIDE 16
slide-17
SLIDE 17

70% 78% 77% 77% 77% 81% 73% 79% 82% 72% 68% 75% 68% 86% 80% 82% 79% 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

MHX MW Team - Percent of Planned Activities Completed (All Groups)

Very Wet Period

slide-18
SLIDE 18

4 10 3 10 9 14 44 8 21 44 10 2 5 10 15 20 25 30 35 40 45 50 Total No. to Date for Each Reason

Reasons for Not Completing WWP Task - Total to Date

slide-19
SLIDE 19