lse 299 summmit computer room summit and base it test
play

LSE-299 Summmit Computer Room Summit and Base IT Test, Verification - PowerPoint PPT Presentation

LSE-299 Summmit Computer Room Summit and Base IT Test, Verification and Validation Jeffrey Kantor LSST IT Sr. Manager LSST Project and Community Workshop 2018 August 13, 2018 #lsst2018 #lsst2018 LSST Project and Community Workshop 2018


  1. LSE-299 Summmit Computer Room Summit and Base IT Test, Verification and Validation Jeffrey Kantor LSST IT Sr. Manager LSST Project and Community Workshop 2018 August 13, 2018 #lsst2018 #lsst2018 LSST Project and Community Workshop 2018 • Tucson • August 13 - 17 LSST Project and Community Workshop 2018 • Tucson • August 13 - 17 1

  2. LSE-299 Summit Computer Room Requirements • Specifies requirements, for space, access, seismic/safety, power and cooling, ducts, conduits & trays, racks and power distribution units • Superceded LSE-76 (Phase 3 ICD) • Developed using LSE-239 Base Data Center Requirements as a starting point, imported into Magic Draw • Developed late in the process, after Summit Facility was already in construction, so constrained by existing contracts • Baselined and implemented in construction contract change orders, follow- on contracts • Lessons learned applied back to LSE-239, which was updated via LCRs #lsst2018 LSST Project and Community Workshop 2018 • Tucson • August 13 - 17 2

  3. LSE-299 Table of Contents 1 Data Center Reliability Requirements Definitions 2 General Facility Requirements 2.1 Consideration for All Spaces 2.2 Cable Ducting from the Exterior to the Computer Room 2.3 Power, UPS and Generation Equipment 2.4 General Cooling System Requirements 2.5 Service areas for network equipment 3 Computing Room Specifications 3.1 Earthquakes and Raised Floors 3.2 Raceways and Cables 3.3 Computing Rack Specifications 3.4 Aisle Specifications 3.5 Physical Security 4 Computing Lab and Prep Area Requirements #lsst2018 LSST Project and Community Workshop 2018 • Tucson • August 13 - 17 3

  4. Summit – Base ITC Test, V&V LSE-309 Summit Base ITC Design specifies standards for network connectivity, IT Security, • hardware and software It is long-standing LSST policy that all implementation be done by LSST subsystems, i.e. the • SB ITC Design Tiger Team, which is a part of LSST System Engineering, has no implementation responsibility Each subsystem has their own test, integration, verification and validation plans which are • required to incorporate means to test compliance with LSE-309 LSST System Engineering team certifies LSST subsystem V&V plans, monitors V&V activities • LSST Commissioning team accepts LSST subsystems into Commissioning phase • #lsst2018 LSST Project and Community Workshop 2018 • Tucson • August 13 - 17 4

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend