Lower Middlesex Water Source Evaluation Project Update March 29, 2017 AGENDA 1. Source Evaluation/Selection 2. Distribution System Layout 3. Project Scope/Project Costs/Financing Sources 4. Proposed Rates/Connection 5. Financial
AGENDA
- 1. Source Evaluation/Selection
- 2. Distribution System Layout
- 3. Project Scope/Project Costs/Financing Sources
- 4. Proposed Rates/Connection
- 5. Financial Sustainability Curve
- 6. Next Steps
- 7. Project Schedule
- 8. Questions
Source Evaluation/Selection
- Objective: To identify high quality sources with high
yields to supply lower Middlesex County
- Methodology:
- 77 existing wells identified and incorporated into Decision Matrix
- Evaluated well yields, water quality, well construction details
- Identified Rosegill Wells as very favorable for use
- Conducted Groundwater Modeling of the Rosegill wells – Results
- favorable. Met with DEQ, response favorable.
- Recommended Selection of Rosegill wells as desired source
Distribution System Layout
- Begins at Rosegill wells
- Extends to Topping
- Extends to Stingray Point
- 2 Storage/Pumping Facilities
- Approximately 120 fire hydrants
Distribution System Layout
Distribution System Layout
Project Scope/Project Costs/Financing Sources
- Approximately 40 miles of pipeline – 12”-2”
- 2 Storage/Pumping Facilities
- Estimated Project Cost - $17,442,838
- Proposed Financing
VDH USDA County County $8,133,122 $7,609,716 $1,000,000 $700,000 2.75% 2.0% 2.5% (TBD) 30 years 40 years 30 years (TBD) Fire Hydrant $401,650 $278,179 $47,778 (TBD) Grant
Proposed Rates/Connection Fees
Vacant Lot ¾” 1” RATES:
- Min. Rate per Month
$20.00 $45.00 $45.00 Rate/1,000 gal (Above min. of 3,000 gal) n/a $10.00 $10.00 Rate breakpoint (gal/mo.) n/a 3,000 3,000 CONNECTION FEES: Initial Connection Fee (yr. 0) $5,000 $4,000 $12,500 Secondary Connection Fee (yrs. 1+) n/a $10,000 $25,000
Subscribers Needed
Meter Sizes
Subscribers
Vacant Lot 3/4" 1" 1 1/2" 2" 3" Previous 43 421 9 1 2 New 40 70 9 2 3 New Subscriber Base
83 491 18 1 4 3 Total Subscribers 600
Financial Sustainability Curve
$0 $2,000,000 $4,000,000 $6,000,000 $8,000,000 $10,000,000 $12,000,000 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 Project Years
Financial Sustainability Curve
(Should never be <$0)
Next Steps
- Submit Funding Application to VDH by April 1
- Submit PER to VDH & USDA
- Press release(s)
- Direct mailing to potential subscribers
- Conduct subscriber meetings to recruit subscribers – April-June