lower churchill project
play

Lower Churchill Project Gilbert Bennett, VP, Lower Churchill Project - PowerPoint PPT Presentation

Lower Churchill Project Gilbert Bennett, VP, Lower Churchill Project March 22, 2013 Safety Moment Nalcor safety culture 2 Project Overview Lower Churchill Hydroelectric Development A dam and powerhouse at Two dams and powerhouse at


  1. Lower Churchill Project Gilbert Bennett, VP, Lower Churchill Project March 22, 2013

  2. Safety Moment • Nalcor safety culture 2

  3. Project Overview

  4. Lower Churchill Hydroelectric Development A dam and powerhouse at Two dams and powerhouse at Gull Island Muskrat Falls 2250 MW/ 12 TW-h/yr 824 MW/ 5 TW-h/yr Reservoir length – 232 km Reservoir length - 60 km Flood area – 85 sq km Flood area – 41 sq km Interconnecting Transmission Lines between Muskrat Falls, Gull Island, and Churchill Falls

  5. Muskrat Falls Generating Facility

  6. Muskrat Falls Generating Facility Tailrace Spillway North RCC Dam Powerhouse Intake South Dam 6

  7. Project Design Stage-gate process • Front-end loading to mitigate risks • Substantial design enhancements between DG2 and DG3: • – Greater definition and design improvements with engineering >50% complete (~5% at DG2) – >5,000 engineering drawings and documents 7

  8. Meteorological Conditions 4500 towers; 460,000 • insulators 6,000,000 m of conductor • 13 distinct wind and ice • combination zones developed from multiple desktop report and existing network of test towers/test spans 170 km of High Alpine (Rime) • Ice and Wind Loading, 180 km Heavy Glaze Ice 250 km of remote • inaccessible line in central Labrador 9

  9. Meteorological Conditions 10

  10. Strait of Belle Isle (SOBI) Crossing Rock Placement Vessel • Three cables will each have a dedicated horizontally directionally drilled (HDD) conduit to protect it from shore and pack ice at the landfall points. • Conduits will take each cable to a water depth of between 60 to 80m. • Cables will be laid on sea bed and each protected with a rock berm. Horizontal Directional Drilling Landfall Protection 11

  11. SOBI - Iceberg and Pack Ice Protection The bathymetric shield extends 50 km East of SOBI and stops icebergs with draft greater than60m The SOBI sea bed extends to depths of ~110 m The HDD takes the cable below 70 m – clear of iceberg drafts and takes the cable 1 to 2 km away from the shore to protect from pack ice 12

  12. Project Update 13

  13. Project Update • Sanction decision made by the provincial government in December 2012 • Preliminary site work completed at Muskrat Falls • More than 95% of engineering work has been carried out in NL • Moving forward with site construction • Contracts and packages awarded for several major project components

  14. Key Activities: 2013

  15. Muskrat Falls – 2013 • Bulk excavation underway • Start reservoir clearing • North Spur geotechnical engineering • Accommodations complex to be constructed • First concrete to be poured for spillway 16

  16. Labrador Transmission • Commence Right of Way (ROW) clearing – Muskrat Falls to Churchill Falls • Commence transmission construction • Commence earth works at Churchill Falls switchyard 17

  17. Labrador-Island Link/SOBI • Anticipated release from Environmental Assessment early 2013 • Following release: – Commence earthworks at Soldier’s Pond (Avalon Peninsula) – Start ROW clearing in Labrador and Northern Peninsula – Begin transmission construction late 2013 – Begin Strait of Belle Isle Horizontal Directional Drilling (HDD) program

  18. Muskrat Falls Today 19

  19. Muskrat Falls Site Today • 7 contractors working on site today • Approx. 260 workers • Security and medical services located on site • Health, Safety and Environmental personnel onsite 20

  20. Muskrat Falls Site 21

  21. Powerhouse Area 22

  22. Temporary Accommodations 23

  23. Bulk Excavation 24

  24. Bulk Excavation 25

  25. Bulk Excavation 26

  26. North & South Wall Bulk Excavation, Controlled Blasting 27

  27. Line stringing across Churchill River 28

  28. Line stringing across Churchill River 29

  29. Newfoundland and Labrador Benefits

  30. Benefits to NL will include: • Long-term stable electricity rates for generations • Reliable, long-term supply of clean, renewable energy • Energy independence – an enviable position • Energy for future mining and industrial development in the province • Diversified economy, jobs and benefits • Link to North America’s electricity grid and ability to export power to other markets • Long-term revenue generation

  31. Project Benefits • The construction of Muskrat Falls will mean significant economic benefits for Newfoundland and Labrador, including: – $1.9B in income to labour and business – $320M in average income benefits per year – $290M in taxes to the Government of NL 32

  32. Project Benefits • Approx. $500M in income to business and labour will be earned by Labradorians and Labrador-based businesses. • 23,300 person years of direct, indirect & induced employment - 8,000 in Labrador. • 9,100 direct person years of employment during construction - 5,800 in Labrador. 33

  33. Quarterly Labour Demand 34

  34. Procurement Opportunities

  35. Committed to Opportunities for NL • Full and fair opportunity on a competitive basis • Participate in the supply of works, goods and services – Directly from Nalcor and SNC-Lavalin Inc. – Indirectly through contractors and suppliers • Availability of businesses to provide goods and services determines level and nature of economic benefits • Nalcor, SNC-Lavalin Inc. and any contractors and suppliers must adhere to provisions of: – Impacts and Benefits Agreement (IBA) with Labrador Innu – NL Benefits Strategy – NL/NS Benefits Memorandum of Understanding

  36. Innu Business Opportunities • Nalcor is committed to enhancing Innu business participation in the project in accordance with the IBA • Innu Businesses have first bidding opportunity on $400 million of business opportunities, split between Phase 1 (Muskrat) and Phase 2 (Gull Island) • First bidding opportunities cover a wide range of goods and services • Interested businesses should contact the Innu Business Development Centre or Innu Nation to discuss partnership opportunities

  37. Procurement Activities to Date • Packages awarded for several major project components: – Bulk excavation – Accommodations complex installation – Medical and security services – HVdc Submarine Cables – Turbines and generators – HVac transmission line steel towers Muskrat Falls to Churchill Falls – Site services for temporary camp Majority of procurement activity for the Project will be • initiated in 2013/14

  38. Summary • Over 95% of the engineering work carried out in NL • Construction work has commenced and will continue as per the schedule • Significant economic, business and employment opportunities for NL • Procurement opportunities available – bulk of contracts to be awarded in 2013/early 2014 39

  39. Learn More • Nalcor Energy website: nalcorenergy.com • Muskrat Falls Jobs website: muskratfallsjobs.com • Email: lowerchurchill@nalcorenergy.com • Call toll-free: 1-888-576-5454 • Participate in supplier development sessions, public meetings and open houses 40

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend