Lower Churchill Project Gilbert Bennett, VP, Lower Churchill Project - - PowerPoint PPT Presentation

lower churchill project
SMART_READER_LITE
LIVE PREVIEW

Lower Churchill Project Gilbert Bennett, VP, Lower Churchill Project - - PowerPoint PPT Presentation

Lower Churchill Project Gilbert Bennett, VP, Lower Churchill Project March 22, 2013 Safety Moment Nalcor safety culture 2 Project Overview Lower Churchill Hydroelectric Development A dam and powerhouse at Two dams and powerhouse at


slide-1
SLIDE 1

Lower Churchill Project

Gilbert Bennett, VP, Lower Churchill Project March 22, 2013

slide-2
SLIDE 2

Safety Moment

  • Nalcor safety culture

2

slide-3
SLIDE 3

Project Overview

slide-4
SLIDE 4

Lower Churchill Hydroelectric Development

Interconnecting Transmission Lines between Muskrat Falls, Gull Island, and Churchill Falls

2250 MW/ 12 TW-h/yr Reservoir length – 232 km Flood area – 85 sq km

A dam and powerhouse at Gull Island Two dams and powerhouse at Muskrat Falls

824 MW/ 5 TW-h/yr Reservoir length - 60 km Flood area – 41 sq km

slide-5
SLIDE 5

Muskrat Falls Generating Facility

slide-6
SLIDE 6

6

Muskrat Falls Generating Facility

South Dam North RCC Dam Spillway Intake Powerhouse Tailrace

slide-7
SLIDE 7

Project Design

  • Stage-gate process
  • Front-end loading to mitigate risks
  • Substantial design enhancements between DG2 and DG3:

– Greater definition and design improvements with engineering >50%

complete (~5% at DG2)

– >5,000 engineering drawings and documents

7

slide-8
SLIDE 8

Meteorological Conditions

  • 4500 towers; 460,000

insulators

  • 6,000,000 m of conductor
  • 13 distinct wind and ice

combination zones developed from multiple desktop report and existing network of test towers/test spans

  • 170 km of High Alpine (Rime)

Ice and Wind Loading, 180 km Heavy Glaze Ice

  • 250 km of remote

inaccessible line in central Labrador

9

slide-9
SLIDE 9

Meteorological Conditions

10

slide-10
SLIDE 10

Strait of Belle Isle (SOBI) Crossing

  • Three cables will each have a dedicated

horizontally directionally drilled (HDD) conduit to protect it from shore and pack ice at the landfall points.

  • Conduits will take each cable to a water

depth of between 60 to 80m.

  • Cables will be laid on sea bed and each

protected with a rock berm.

11

Rock Placement Vessel Landfall Protection Horizontal Directional Drilling

slide-11
SLIDE 11

SOBI - Iceberg and Pack Ice Protection

12 The bathymetric shield extends 50 km East of SOBI and stops icebergs with draft greater than60m The SOBI sea bed extends to depths of ~110 m The HDD takes the cable below 70 m – clear of iceberg drafts and takes the cable 1 to 2 km away from the shore to protect from pack ice

slide-12
SLIDE 12

Project Update

13

slide-13
SLIDE 13

Project Update

  • Sanction decision made by the

provincial government in December 2012

  • Preliminary site work completed

at Muskrat Falls

  • More than 95% of

engineering work has been carried out in NL

  • Moving forward with site

construction

  • Contracts and packages

awarded for several major project components

slide-14
SLIDE 14

Key Activities: 2013

slide-15
SLIDE 15

Muskrat Falls – 2013

  • Bulk excavation underway
  • Start reservoir clearing
  • North Spur geotechnical

engineering

  • Accommodations complex

to be constructed

  • First concrete to be poured

for spillway

16

slide-16
SLIDE 16

Labrador Transmission

  • Commence Right of Way (ROW) clearing

– Muskrat Falls to Churchill Falls

  • Commence transmission construction
  • Commence earth works at Churchill Falls switchyard

17

slide-17
SLIDE 17

Labrador-Island Link/SOBI

  • Anticipated release from Environmental Assessment early

2013

  • Following release:

– Commence earthworks at Soldier’s Pond (Avalon Peninsula) – Start ROW clearing in

Labrador and Northern Peninsula

– Begin transmission

construction late 2013

– Begin Strait of Belle Isle

Horizontal Directional Drilling (HDD) program

slide-18
SLIDE 18

Muskrat Falls Today

19

slide-19
SLIDE 19

Muskrat Falls Site Today

  • 7 contractors working on

site today

  • Approx. 260 workers
  • Security and medical

services located on site

  • Health, Safety and

Environmental personnel

  • nsite

20

slide-20
SLIDE 20

Muskrat Falls Site

21

slide-21
SLIDE 21

22

Powerhouse Area

slide-22
SLIDE 22

23

Temporary Accommodations

slide-23
SLIDE 23

Bulk Excavation

24

slide-24
SLIDE 24

Bulk Excavation

25

slide-25
SLIDE 25

Bulk Excavation

26

slide-26
SLIDE 26

North & South Wall Bulk Excavation, Controlled Blasting

27

slide-27
SLIDE 27

Line stringing across Churchill River

28

slide-28
SLIDE 28

Line stringing across Churchill River

29

slide-29
SLIDE 29

Newfoundland and Labrador Benefits

slide-30
SLIDE 30

Benefits to NL will include:

  • Long-term stable electricity rates for generations
  • Reliable, long-term supply of clean, renewable energy
  • Energy independence – an enviable position
  • Energy for future mining and industrial development in

the province

  • Diversified economy, jobs and benefits
  • Link to North America’s electricity grid and ability to

export power to other markets

  • Long-term revenue generation
slide-31
SLIDE 31

Project Benefits

  • The construction of Muskrat Falls

will mean significant economic benefits for Newfoundland and Labrador, including:

– $1.9B in income to labour and

business

– $320M in average income

benefits per year

– $290M in taxes to the

Government of NL

32

slide-32
SLIDE 32

Project Benefits

  • Approx. $500M in income to

business and labour will be earned by Labradorians and Labrador-based businesses.

  • 23,300 person years of direct,

indirect & induced employment - 8,000 in Labrador.

  • 9,100 direct person years of

employment during construction - 5,800 in Labrador.

33

slide-33
SLIDE 33

Quarterly Labour Demand

34

slide-34
SLIDE 34

Procurement Opportunities

slide-35
SLIDE 35

Committed to Opportunities for NL

  • Full and fair opportunity on a competitive basis
  • Participate in the supply of works, goods and services

– Directly from Nalcor and SNC-Lavalin Inc. – Indirectly through contractors and suppliers

  • Availability of businesses to provide goods and services

determines level and nature of economic benefits

  • Nalcor, SNC-Lavalin Inc. and any contractors and suppliers

must adhere to provisions of:

– Impacts and Benefits Agreement (IBA) with Labrador Innu – NL Benefits Strategy – NL/NS Benefits Memorandum of Understanding

slide-36
SLIDE 36

Innu Business Opportunities

  • Nalcor is committed to enhancing Innu business

participation in the project in accordance with the IBA

  • Innu Businesses have first bidding opportunity on $400

million of business opportunities, split between Phase 1 (Muskrat) and Phase 2 (Gull Island)

  • First bidding opportunities cover a wide range of goods

and services

  • Interested businesses should contact the Innu Business

Development Centre or Innu Nation to discuss partnership opportunities

slide-37
SLIDE 37

Procurement Activities to Date

  • Packages awarded for several major project components:

– Bulk excavation – Accommodations complex installation – Medical and security services – HVdc Submarine Cables – Turbines and generators – HVac transmission line steel towers Muskrat Falls to

Churchill Falls

– Site services for temporary camp

  • Majority of procurement activity for the Project will be

initiated in 2013/14

slide-38
SLIDE 38

Summary

  • Over 95% of the engineering work carried out

in NL

  • Construction work has commenced and will

continue as per the schedule

  • Significant economic, business and

employment opportunities for NL

  • Procurement opportunities available – bulk of

contracts to be awarded in 2013/early 2014

39

slide-39
SLIDE 39

Learn More

  • Nalcor Energy website: nalcorenergy.com
  • Muskrat Falls Jobs website:

muskratfallsjobs.com

  • Email: lowerchurchill@nalcorenergy.com
  • Call toll-free: 1-888-576-5454
  • Participate in supplier development sessions,

public meetings and open houses

40

slide-40
SLIDE 40