Lower Churchill Project Gilbert Bennett, VP, Lower Churchill Project - - PowerPoint PPT Presentation
Lower Churchill Project Gilbert Bennett, VP, Lower Churchill Project - - PowerPoint PPT Presentation
Lower Churchill Project Gilbert Bennett, VP, Lower Churchill Project March 22, 2013 Safety Moment Nalcor safety culture 2 Project Overview Lower Churchill Hydroelectric Development A dam and powerhouse at Two dams and powerhouse at
Safety Moment
- Nalcor safety culture
2
Project Overview
Lower Churchill Hydroelectric Development
Interconnecting Transmission Lines between Muskrat Falls, Gull Island, and Churchill Falls
2250 MW/ 12 TW-h/yr Reservoir length – 232 km Flood area – 85 sq km
A dam and powerhouse at Gull Island Two dams and powerhouse at Muskrat Falls
824 MW/ 5 TW-h/yr Reservoir length - 60 km Flood area – 41 sq km
Muskrat Falls Generating Facility
6
Muskrat Falls Generating Facility
South Dam North RCC Dam Spillway Intake Powerhouse Tailrace
Project Design
- Stage-gate process
- Front-end loading to mitigate risks
- Substantial design enhancements between DG2 and DG3:
– Greater definition and design improvements with engineering >50%
complete (~5% at DG2)
– >5,000 engineering drawings and documents
7
Meteorological Conditions
- 4500 towers; 460,000
insulators
- 6,000,000 m of conductor
- 13 distinct wind and ice
combination zones developed from multiple desktop report and existing network of test towers/test spans
- 170 km of High Alpine (Rime)
Ice and Wind Loading, 180 km Heavy Glaze Ice
- 250 km of remote
inaccessible line in central Labrador
9
Meteorological Conditions
10
Strait of Belle Isle (SOBI) Crossing
- Three cables will each have a dedicated
horizontally directionally drilled (HDD) conduit to protect it from shore and pack ice at the landfall points.
- Conduits will take each cable to a water
depth of between 60 to 80m.
- Cables will be laid on sea bed and each
protected with a rock berm.
11
Rock Placement Vessel Landfall Protection Horizontal Directional Drilling
SOBI - Iceberg and Pack Ice Protection
12 The bathymetric shield extends 50 km East of SOBI and stops icebergs with draft greater than60m The SOBI sea bed extends to depths of ~110 m The HDD takes the cable below 70 m – clear of iceberg drafts and takes the cable 1 to 2 km away from the shore to protect from pack ice
Project Update
13
Project Update
- Sanction decision made by the
provincial government in December 2012
- Preliminary site work completed
at Muskrat Falls
- More than 95% of
engineering work has been carried out in NL
- Moving forward with site
construction
- Contracts and packages
awarded for several major project components
Key Activities: 2013
Muskrat Falls – 2013
- Bulk excavation underway
- Start reservoir clearing
- North Spur geotechnical
engineering
- Accommodations complex
to be constructed
- First concrete to be poured
for spillway
16
Labrador Transmission
- Commence Right of Way (ROW) clearing
– Muskrat Falls to Churchill Falls
- Commence transmission construction
- Commence earth works at Churchill Falls switchyard
17
Labrador-Island Link/SOBI
- Anticipated release from Environmental Assessment early
2013
- Following release:
– Commence earthworks at Soldier’s Pond (Avalon Peninsula) – Start ROW clearing in
Labrador and Northern Peninsula
– Begin transmission
construction late 2013
– Begin Strait of Belle Isle
Horizontal Directional Drilling (HDD) program
Muskrat Falls Today
19
Muskrat Falls Site Today
- 7 contractors working on
site today
- Approx. 260 workers
- Security and medical
services located on site
- Health, Safety and
Environmental personnel
- nsite
20
Muskrat Falls Site
21
22
Powerhouse Area
23
Temporary Accommodations
Bulk Excavation
24
Bulk Excavation
25
Bulk Excavation
26
North & South Wall Bulk Excavation, Controlled Blasting
27
Line stringing across Churchill River
28
Line stringing across Churchill River
29
Newfoundland and Labrador Benefits
Benefits to NL will include:
- Long-term stable electricity rates for generations
- Reliable, long-term supply of clean, renewable energy
- Energy independence – an enviable position
- Energy for future mining and industrial development in
the province
- Diversified economy, jobs and benefits
- Link to North America’s electricity grid and ability to
export power to other markets
- Long-term revenue generation
Project Benefits
- The construction of Muskrat Falls
will mean significant economic benefits for Newfoundland and Labrador, including:
– $1.9B in income to labour and
business
– $320M in average income
benefits per year
– $290M in taxes to the
Government of NL
32
Project Benefits
- Approx. $500M in income to
business and labour will be earned by Labradorians and Labrador-based businesses.
- 23,300 person years of direct,
indirect & induced employment - 8,000 in Labrador.
- 9,100 direct person years of
employment during construction - 5,800 in Labrador.
33
Quarterly Labour Demand
34
Procurement Opportunities
Committed to Opportunities for NL
- Full and fair opportunity on a competitive basis
- Participate in the supply of works, goods and services
– Directly from Nalcor and SNC-Lavalin Inc. – Indirectly through contractors and suppliers
- Availability of businesses to provide goods and services
determines level and nature of economic benefits
- Nalcor, SNC-Lavalin Inc. and any contractors and suppliers
must adhere to provisions of:
– Impacts and Benefits Agreement (IBA) with Labrador Innu – NL Benefits Strategy – NL/NS Benefits Memorandum of Understanding
Innu Business Opportunities
- Nalcor is committed to enhancing Innu business
participation in the project in accordance with the IBA
- Innu Businesses have first bidding opportunity on $400
million of business opportunities, split between Phase 1 (Muskrat) and Phase 2 (Gull Island)
- First bidding opportunities cover a wide range of goods
and services
- Interested businesses should contact the Innu Business
Development Centre or Innu Nation to discuss partnership opportunities
Procurement Activities to Date
- Packages awarded for several major project components:
– Bulk excavation – Accommodations complex installation – Medical and security services – HVdc Submarine Cables – Turbines and generators – HVac transmission line steel towers Muskrat Falls to
Churchill Falls
– Site services for temporary camp
- Majority of procurement activity for the Project will be
initiated in 2013/14
Summary
- Over 95% of the engineering work carried out
in NL
- Construction work has commenced and will
continue as per the schedule
- Significant economic, business and
employment opportunities for NL
- Procurement opportunities available – bulk of
contracts to be awarded in 2013/early 2014
39
Learn More
- Nalcor Energy website: nalcorenergy.com
- Muskrat Falls Jobs website:
muskratfallsjobs.com
- Email: lowerchurchill@nalcorenergy.com
- Call toll-free: 1-888-576-5454
- Participate in supplier development sessions,
public meetings and open houses
40