lower main st crossing of james creek design team
play

Lower Main St. Crossing of James Creek Design Team Project - PowerPoint PPT Presentation

Lower Main St. Crossing of James Creek Design Team Project Principal Miranda Lange, P.E. Project Manager Dan Tuttle, P.E. Structural Engineer Steven Lykens, P.E. Geotechnical Engineer Ryan Lepro, P.G. Roadway Design Dan


  1. Lower Main St. Crossing of James Creek

  2. Design Team Project Principal – Miranda Lange, P.E. Project Manager – Dan Tuttle, P.E. Structural Engineer – Steven Lykens, P.E. Geotechnical Engineer – Ryan Lepro, P.G. Roadway Design – Dan Tuttle, P.E. Lead Hydraulics – Anthony Alvarado, P.E. BCA Analysis – Steve Pardue Hydraulics Engineer– James Hitchman, P.E.

  3. Project Background After the 2013 floods, the Town applied for and received a FEMA Hazard Mitigation Program Grant (HMGP) to analyze the Lower Main St. crossing of James Creek. After the proposal and interview process, our team was awarded this project in late May 2016. The main objective of this project, is to: Increase the capacity of the creek crossing to pass the 100-year storm event to reduce the risk of similar damage in a future flood. The major scope items that our team has been tasked with includes (but is not limited to): u Topographic Survey u Hydrology/hydraulic analysis for existing and proposed conditions u Geotechnical investigations and reporting u Develop alternatives for proposed improvements u Benefit Cost Analysis (BCA) u 60% design plans, specifications, and estimate

  4. Progression of Project 2016 May June July August September October Hydraulics for Public Direction existing Involvement from Town Hydraulic conditions Data & Town Board Board for Analysis for complete; begin Awarded Collection Presentation selected analyzing existing Project (LOMR data, design proposed conditions utilities, conditions. alternative continued BCA Analysis Geotechnical Begin 60% Bores Done design upon (Bedrock ~23’ Field Survey Hydrology & receiving Finalizing Deep) Done & Hydraulic Town Board Contract & Received Analysis of Approval Subcontracts Topographic Existing Begin Survey Conditions preliminary design for 3 alternatives

  5. Project Information Definition(s): 1. Freeboard – This is the distance between the water surface elevation and the bottom of the bridge. Freeboard is important because it correlates with the ability to pass floating debris. If we can pass floating debris, there is a high likelihood that the bridge does not get plugged and then flanked. 2. Clear Flow – This represents the flow of water that passes under the bridge with NO debris. 3. Debris Flow – This represents the flow of water that passes under the bridge with debris. Hydraulics & Hydrology: 1. Hydraulic Modeling – It is difficult to model debris flow, but as a standard practice, 2 or more feet of freeboard is used as a target during design.

  6. Initial Alternatives Made the cut Option 1 - Remove and Replace Bridge Option 2 - Raise Existing Bridge Deck Option 3 - Additional Span Discarded Remove and Relocate Bridge Downstream - VCUP issues at Elysian Park and private property impacts Fuse Plug - Difficult to design for the unknown & didn’t solve problem. Widen and Raise Existing Bridge – High cost and difficult to design with no as-built plans. Do nothing Existing Bridge

  7. Existing Bridge FREEBOARD DURING 100-YEAR EVENT PROS Approximate No construction needed. level of debris No construction impact to private FREEBOARD property. WATER ~23’ to bedrock CONS SURFACE Does not pass 100-year flow. ELEVATION Shallow spread footings that are vulnerable to failure during a 50 & 100-year storm. Old bridge built in 80s with approximately 20 years left on its lifespan (assuming properly maintained). Estimated Cost: Future maintenance costs needed includes: deck Freeboard Per Storm Event: rehab, spalling, future storm damage,etc. 100-Year = 0 FT 50-Year = 0 FT 10-Year = 2.4’

  8. Existing Bridge

  9. Existing Conditions – 100 Year Event (Clear Flow – No Debris) Breakout Flow (This is independent of bridge, and will happen in all scenarios) Fire Station Bridge Location Breakout Flow (This is independent of bridge, and will happen in all scenarios) James Creek Flow (cfs) 500-year event = 4834 100-year event = 2777 50-year event = 2095 25-year event = 1502 Breakout flow down Lower 10-year event = 912 Main (Approximately 200 cfs)

  10. Existing Conditions – 50 Year Event (Clear Flow – No Debris) Breakout Flow (This is independent of bridge, and will happen in all scenarios) Fire Station Bridge Location Breakout Flow (This is independent of bridge, and will happen in all scenarios) James Creek Flow (cfs) 500-year event = 4834 100-year event = 2777 50-year event = 2095 25-year event = 1502 Breakout flow down Lower Main 10-year event = 912

  11. Existing Conditions – 10 Year Event (Clear Flow – No Debris) Breakout Flow (This is independent of bridge, and will happen in all scenarios) Fire Station Bridge Location James Creek Flow (cfs) 500-year event = 4834 100-year event = 2777 50-year event = 2095 25-year event = 1502 10-year event = 912 Breakout flow down Lower Main

  12. Option 1 – New Bridge FREEBOARD DURING 100-YEAR EVENT PROS Approximate Passes 100-year, clear flow level of debris Passes 100-year, debris flow FREEBOARD Design life of new bridge would be 75 WATER years. ~23’ to bedrock SURFACE Constructible under current grant, except ELEVATION for the demolition costs. CONS Increases driveway slopes & requires moderate channel excavation. Requires a small amount of property acquisition or permanent easements. Highest construction cost, but still eligible under the current grant. Freeboard Per Storm Event: Estimated Construction Cost: 100-Year = 2.2 FT $1,033,443* (includes 30% Contingency) 50-Year = 2.9 FT *Cost does not include: Final design, Town administration costs, construction management 10-Year = 5.0’ sts, property or easement acquisition.

  13. Option 1 – New Bridge

  14. Option 1 – 100 Year Event (Clear Flow – No Debris) Breakout Flow (This is independent of bridge, and will happen in all scenarios) Fire Station Bridge Location Breakout Flow (This is independent of bridge, and will happen in all scenarios) James Creek Flow (cfs) 500-year event = 4834 100-year event = 2777 50-year event = 2095 Breakout flow down Lower 25-year event = 1502 Main St. eliminated 10-year event = 912

  15. Option 1 – 50 Year Event (Clear Flow – No Debris) Breakout Flow (This is independent of bridge, and will happen in all scenarios) Fire Station Bridge Location Breakout Flow (This is independent of bridge, and will happen in all scenarios) James Creek Flow (cfs) 500-year event = 4834 100-year event = 2777 50-year event = 2095 Breakout flow down Lower 25-year event = 1502 Main St. eliminated 10-year event = 912

  16. Option 2 – Raise Existing Bridge Deck PROS FREEBOARD DURING 100-YEAR EVENT Passes 25 & 50-year, clear flow. Approximate FREEBOARD Passes 25-year, debris flow. level of debris Minimal channel grading. WATER ~23’ to bedrock CONS SURFACE Does not pass 100-year, clear flow. ELEVATION Does not pass 100-year, debris flow. Unlikely to pass 50-year debris flow. Retrofitted Requires retrofitting deep foundations. foundations Increases driveway slopes. Existing Footer Requires a small amount of property acquisition or permanent easements. Estimated Construction Cost: Freeboard Per Storm Event: $663,287* (includes 30% Contingency) 100-Year = 0 FT *Cost does not include: Final Design, Town 50-Year = 0.5 FT administration costs, construction management costs. 10-Year = 3.6’

  17. Option 2 – Raise Existing Bridge Deck

  18. Option 2 – 100 Year Event (Clear Flow – No Debris) Breakout Flow (This is independent of bridge, and will happen in all scenarios) Fire Station Bridge Location Breakout Flow (This is independent of bridge, and will happen in all scenarios) James Creek Flow (cfs) 500-year event = 4834 100-year event = 2777 Breakout flow down Lower Main 50-year event = 2095 25-year event = 1502 10-year event = 912

  19. Option 2 – 50 Year Event (Clear Flow – No Debris) Breakout Flow (This is independent of bridge, and will happen in all scenarios) Fire Station Bridge Location Breakout Flow (This is independent of bridge, and will happen in all scenarios) James Creek Flow (cfs) 500-year event = 4834 100-year event = 2777 50-year event = 2095 25-year event = 1502 Breakout flow down Lower Main 10-year event = 912

  20. Option 3 – Additional Span PROS FREEBOARD DURING 100-YEAR EVENT Passes 100-year, clear flow. Approximate Constructible under current grant. level of debris FREEBOARD WATER CONS ~23’ to bedrock SURFACE Does not pass 100 or 50-year flow, debris flow. ELEVATION Creates a center pier that may catch debris. Requires retrofitting deep foundations. Increases driveway slopes & requires significant channel excavation. Requires property acquisition or permanent Existing Footer easements. Estimated Construction Cost: Freeboard Per Storm Event: $906,737* (w/30% Contingency) 100-Year = 0.7 FT *Cost does not include: Final Design, Town 50-Year = 1.5 FT administration costs, construction management costs, 10-Year = 3.2’ property or easement acquisitions.

  21. Option 3 – Additional Span

  22. Option 3 – 100 Year Event (Clear Flow – No Debris) Breakout Flow (This is independent of bridge, and will happen in all scenarios) Fire Station Bridge Location Breakout Flow (This is independent of bridge, and will happen in all scenarios) James Creek Flow (cfs) 500-year event = 4834 100-year event = 2777 50-year event = 2095 25-year event = 1502 Breakout flow down Lower Main eliminated 10-year event = 912

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend