Los Pelambres - Site Visit December 6 th , 2016 Robert Mayne - - PowerPoint PPT Presentation

los pelambres site visit
SMART_READER_LITE
LIVE PREVIEW

Los Pelambres - Site Visit December 6 th , 2016 Robert Mayne - - PowerPoint PPT Presentation

Los Pelambres - Site Visit December 6 th , 2016 Robert Mayne Nicholls General Manager Cautionary statement This presentation has been prepared by Antofagasta plc. By reviewing and/or attending this presentation you agree to the following


slide-1
SLIDE 1

December 6th, 2016 Robert Mayne Nicholls General Manager

Los Pelambres - Site Visit

slide-2
SLIDE 2

Cautionary statement

This presentation has been prepared by Antofagasta plc. By reviewing and/or attending this presentation you agree to the following conditions: This presentation contains forward-looking statements. All statements other than historical facts are forward-looking statements. Examples

  • f forward-looking statements include those regarding the Group's strategy, plans, objectives or future operating or financial performance;

reserve and resource estimates; commodity demand and trends in commodity prices; growth opportunities; and any assumptions underlying or relating to any of the foregoing. Words such as “intend”, “aim”, “project”, “anticipate”, “estimate”, “plan”, “believe”, “expect”, “may”, “should”, “will”, “continue” and similar expressions identify forward-looking statements. Forward-looking statements involve known and unknown risks, uncertainties, assumptions and other factors that are beyond the Group’s control. Given these risks, uncertainties and assumptions, actual results could differ materially from any future results expressed or implied by these forward-looking statements, which speak only as of the date of this presentation. Important factors that could cause actual results to differ from those in the forward-looking statements include: global economic conditions; demand, supply and prices for copper; long-term commodity price assumptions, as they materially affect the timing and feasibility of future projects and developments; trends in the copper mining industry and conditions of the international copper markets; the effect of currency exchange rates on commodity prices and operating costs; the availability and costs associated with mining inputs and labour; operating or technical difficulties in connection with mining or development activities; employee relations; litigation; and actions and activities of governmental authorities, including changes in laws, regulations or taxation. Except as required by applicable law, rule or regulation, the Group does not undertake any obligation to publicly update or revise any forward-looking statements, whether as aresult of new information, future events or otherwise. Certain statistical and other information about Antofagasta plc included in this presentation is sourced from publicly available third party

  • sources. Such information presents the views of those third parties and may not necessarily correspond to the views held by Antofagasta

plc. This presentation is for information purposes only and does not constitute an offer to sell or the solicitation of an offer to buy shares in Antofagasta plc or any other securities in any jurisdiction. Further it does not constitute a recommendation by Antofagasta plc or any other person to buy or sell shares in Antofagasta plc or anyother securities. Past performancecannot be reliedon as a guide to futureperformance.

2

slide-3
SLIDE 3

Key Messages

3

Leaders in innovation Creating long term value through Sustainability Positioned for growth Focus on cost and

  • perational

reliability Emphasis on profitable tonnes

  • Only profitable

production

  • Every tonne

must make an earnings contribution

  • Rebase costs
  • Protect margins
  • Planning and

forecasting

  • Advance
  • rganic growth

projects for approval

  • Robust balance

sheet

  • New

community engagement model

  • Social licence to
  • perate or grow
  • History of

innovation

  • Enables

sustainability and lower costs

  • Embedded

practice

slide-4
SLIDE 4

Agenda

Overview Operations Review Sustainability Growth Opportunities

4

slide-5
SLIDE 5

High PotentialAccident vs Near Miss (Leading Indicators)

10 14 13 8 9 16 19 11 8 15 33 31 40 53 19 64 79 58

44.6 5 10 15 20 25 30 35 40 45 50 10 20 30 40 50 60 70 80 90 100 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16

HP Near- Miss Index # HP Incidents

HP Accidents HP Near Miss Target HP Near Miss Index 2016 HP Near Miss Index 2016 (Q3)

Safety first -24 months with zero fatalities

5

Focus on:

  • Identify and assess key fatality and

serious injury risks.

  • Preventative reporting and

investigation of high-potential near misses.

  • On-the-ground executive safety

leadership.

  • Development of verification tools

for the implementation of critical controls of the transversal fatality risks for each Company.

  • Progress in communications and

culture.

High Potential (HP) Incidents: Total number of HP accidents and HP Near misses *Near -miss index : Represents total number of high potential near misses for every million hours worked. *Near -miss index Target 2016: 17

1 1

0.7 1.3 1.0 1.4 1.8

2012 2013 2014 2015 YTD 2016 Fatalities LTIFR

1. Lost Time Injury Frequency Rate

(1)

Safety Performance

slide-6
SLIDE 6

6

Overview

slide-7
SLIDE 7

Los Pelambres overview

7

  • Ownership structure

– 60% Antofagasta – 15% MM LP Holding – 25% Nippon LP Investment

  • History

– Part of Antofagasta since 1985 – Large scale mining commenced in 1999

  • Location

– 240km north-east of Santiago

  • Facilities overview

– Concentrator with 175ktpd throughput capacity

  • Production

– 5th largest copper producer in Chile

  • Life of Mine

– 23 years (Reserves )

Santiago

Los Pelambres

Cu Conc. C1

YTD Q3 016 Production (t) YTD Q3 2016 ($/lb) Guidance 2016 Production (t) Guidance 2016 ($/lb) 259,300 1.04 355,000 - 365,000 1.25

2016 Guidance

slide-8
SLIDE 8

MineraLos Pelambres(MLP) Team

8

Robert Mayne-Nicholls

Chief Executive Officer Jose Miguel Labbe

Chief Financial Officer

Rodrigo Catalán

Head of Human Resources

Juan Andrés Morel

Chief Operations Officer

Pierino Venturini

Head of Projects

Sebastián Trejos

Head of Safety and Occupational Health

Julio Cesar Castillo

Head of Resource Planning and Development

Hernan Delaigue

Mine Manager

Sergio Valdebenito

Plants and Tailings Manager

Fernando Garay

Port Manager

Pablo Hernández

Operational Excellence Manager

Jorge Araneda

Head of Sustainability

Ivo Fadic

Head of Maintenance

Denotes presence at presentation

slide-9
SLIDE 9

Mine site visit

9

Mine Operations Center Hualtatasviewpoint To be visited

slide-10
SLIDE 10

Concentrator plant site visit

10

1.600 m.a.s.l Throughput: 175 ktpd. Tailings Thickeners Moly plant Flotation Stockpile SAG and Ball Mills To be visited

slide-11
SLIDE 11

Background: a story of sustained growth

11

1914 William Braden first explored in the area of the Los Pelambres deposit 1969 – 71 ENAMI carries out exploration to define the deposit’s potential 1978 Anaconda Minerals buys the Los Pelambres deposit rights that had been tendered by ENAMI 1985 Antofagasta Holdings buys Anaconda Chile and its right over the Los Pelambres deposit 1992 Minera El Chacay starts its small – scale underground operations (5 ktpd) 1997 EIA approved and construction starts. Japanese partners take 40% interest. Bank financing obtained 1999 Successful Ramp – up completed in 84 days with a capacity of 85 ktpd 2004 – 09 Several expansion projects take the processing capacity to 175 ktpd 2016 + Desalination plant and water pipeline EIA submission (enabling LT expansions) 5 85 126 159 175 190

20 40 60 80 100 120 140 160 180 200

< 1999 1999 - 2000 2000 - 2004 2004 - 2008 2008 - 2012 2012 - 2016 2020 + ktpd ktpd ktpd ktpd ktpd ktpd

Throughput (nominal capacity)

slide-12
SLIDE 12

Los Pelambres, a world –class asset

12 363 Peer 1 Peer 2 Peer 3 Peer 4 Los Pelambres Peer 5 Peer 6 Peer 7 Peer 8 Centinela

Chile’s 5th largest copper producer in 2015

25 50 75 100

Los Pelambres C1 cash cost position

103 c/lb 129c/lb 151c/lb MLP*

  • Los Pelambres’s ownership

– Antofagasta Group 60% – MM LP Holding BV 15% – Nippon LP Investment 25%

  • Chile’s 5th largest copper producer

– ~ 140 Mt/year total material movement with competitive stripping ratio – ~ 175 ktpd throughput capacity

  • Total manpower of 4,709

(906 employees + 3,803 contractors)

  • Focus on optimise our processes and lowering
  • ur cost base to strengthen margins
  • Chile’s 7th largest deposit (reserves &

resources) – Incremental Expansion project will allow MLP to maximise the value of its resources

Ktpa c/lb

Source: Cochilco Source: Woodmackenzie. Cash cost curve as per Q3 2016 update

slide-13
SLIDE 13

One of our main operating challenges: ore hardness

13

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 100 200 300 400 500 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 Guidance

ktpa

Cu production Hardness (%) of ore fed to plant

slide-14
SLIDE 14

Reserves and Resources

14

Los Pelambres Tonnage (millions of tonnes) Copper (%) Molybdenum (%) Gold (g/t)

Measured 1.151 0,59 0,022 0,05 Indicated 2.263 0,53 0,015 0,05 Inferred 2.690 0,46 0,015 0,06 Total(1)

6.104

0,51 0,016 0,06

Los Pelambres Tonnage (millions of tonnes) Copper (%) Molybdenum (%) Gold (g/t)

Proven 704 0,61 0,022 0,05 Probable 604 0,60 0,015 0,04 Total(1)

1.309

0,61 0,019 0,05

Note: Information as of 31 Dec 2015

Resources: Reserves:

slide-15
SLIDE 15

15

Operations Review

slide-16
SLIDE 16

16

Integrated production process & facilities

2 Gyratory Crushers MINE STOCKPILE PLANT STOCKPILE MINE 52 Komatsu 930E Trucks 5 Electric shovels 2 Front-end loaders Conveyor Belt Tunnel 58 Rougher Cells 2 Cu – Mo Thickeners 14 Column cells 3 Vertical mills 3 Tailings Thickeners El Mauro Tailings Dam 3 SAG Mills 6 Ball Mills 28 Cyclones PUNTA CHUNGO CONCENTRATE SHIPMENT 8 Ceramic filters Molybdenum Plant Molybdenum concentrate Wastedump

slide-17
SLIDE 17

17

Mine plan

Phase10 (2018 to2026) Phase12 (2030 to2037) Phase9 (2021 to2026) Phase8 (until2018) Phase7 (until2021 ) Phase11 (2027 to2034)

slide-18
SLIDE 18

Fleet and mining equipment

18

Type Brand - Model No of units

Drilling

  • Production
  • Support

Atlas Copco Pit Viper 351 (E) Atlas Copco Pit Viper 351 (D) Atlas Copco Pit Viper 316 Atlas Copco ROC L-8 3 5 1 4 Loading

  • Shovels
  • Loaders

P&H 4100 A 53Yd3 P&H 4100 XPB 73Yd3 P&H 4100 XPC 73Yd3 LeTourneau L1850 GII 33Yd3 LeTourneau L2350 54Yd3 1 3 1 1 1 Haulage Komatsu K930E 300 ton 52

slide-19
SLIDE 19

Concentrator plant description

19

Plant Specifications Througput: 175 ktpd Recovery  Cu: 90% / Mo: 81% Cycle length: Continuous Operation Crushing and conveyor 2 Primary Crushers :Gyratory, 60”x113”, 1000 HP each Ore conveyor: 3 Conveyor belts of 12.8 Km of total length, 10 motors of 3300 HP each Milling SAG mills: 3 SAG mills, 36’x17’, 20.000 HP each Ball mills:

  • 5 Ball mills, 21’x33’, 10.500 HP each
  • 1 Ball mill, 26’x40’ 20.700 HP

Flotation 36 rougher cells of 130 m3 each 22 rougher cells of 250 m3 18 scavenger cells of 130 m3 14 cells columns of 14 m height

slide-20
SLIDE 20

Tailings and transport

20

Authorised Capacity: 1.700 Mtons Construction method: Downstream Operates under D.S. 248 (authorised with the former one) Current tailings: 452 Mton Maximum wall height: 237 m Current height: 163 m Recirculation system with capacity for 1100 lts Safety spillway to evacuate 20 m3/s Perimeter canals and tailings dam to return water to Pupio stream Construction of tailings cycloned sand wall in cyclones cluster.

slide-21
SLIDE 21

Port

21

Concentrate thickeners and filters – Type: Ceramic Filters (8 units) – Capacity: 22,5 wmt/h (each one) Concentrate warehouse – Capacity: 130,000 wmt Shiploader – Type: SLRQ 1900.57/19 OX Radial Quadrant – Capacity: 1,800 wmt/h – Length: 180-220 m (Radial movement)

slide-22
SLIDE 22

Competitive and Cost Program (CCP)

22

Services Productivity Improving productivity and quality of contracts while reducing costs Operational & Maintenance Management Improving performance of critical processes and standardising maintenance management Corporate & Organisational Effectiveness Reducing corporate costs and restructuring corporate functions Energy Efficiency Improving energy pricing and consumption efficiency

Our strategic objective

Positioning MLP in the first cost quartile of the industry in the medium term

Cost Savings

H1 2016

US$ 25m US$ 26m US$ 4m US$ 1m Cost Savings

2015

US$ 28m US$ 45m US$ 1m

slide-23
SLIDE 23

Mine: optimisingkey value drivers and productivity

23

  • We operate a single open pit mine

– Total material movement of ~ 140 Mt/year – Competitive stripping ratio of ~ 1.2 – Life of mine: 21 years

  • Ore hardness is a challenge being mitigated by mining practices and improved plant utilisation,

and in the long term with the expansion project

  • Successful management of dust emissions

Optimising workforce

Already implemented On going On going

Status

Value

On going

Mine to Mill Reviewing key contracts OEE Optimisation

Better ore particle size to feed concentrator plant

Being implemented

Implementation

  • f fatigue devices

Reduction of accident risk of trucks operators Increase effective

  • perating time of

equipment Cost reduction Improve productivity and reduce cost

Initiatives to optimise mine performance

slide-24
SLIDE 24

Plant initiatives to capture full potential

24 Already implemented On going

Status

Value

Under evaluation

Several initiatives to Increase plant recovery Reviewing key contracts De-bottleneck lime plant

Recovery improvement

Being implemented

Reduce unexpected events

Optimiseplant reliability Optimisemix feed to plant to reduce ore hardness Cost reduction and service

  • ptimisation
  • We operate a 175 ktpd concentrator plant that

includes 3 SAG Mills and 6 Ball Mills

  • Ore hardness is challenging plant performance

(tons per hour)

  • Consolidation of continuous improvement

initiatives through the implementation of new

  • perational excellence area

Initiatives to unlock the plant potential

20 40 60 80 0% 20% 40% 60% 80% 100% 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 Mt %

Mineral processed (Mt) and ore hardness (%)

Processed ore Ore hardness (%)

50 100 150 200 0% 20% 40% 60% 80% 100% 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 ktpd %

Mineral processed (ktpd) and ore hardness (%)

Processed ore Ore hardness (%)

slide-25
SLIDE 25

25

Sustainability

slide-26
SLIDE 26

Strong commitment to renewable energy

Renewable energies:

  • Antofagasta has made important efforts to include clean energy directly in its operations
  • From its beginning, MLP takes advantage from its conveyor belts to generate energy, contributing

with 9% of the Company’s total energy consumption

  • Benefitting from Javiera photovoltaic plant energy supply, during the second half of 2015, MLP

achieved a new advance to integrate sources of renewable energies. This energy contributes with about 15% of the energy requirements of MLP

  • El Arrayán wind farm, the largest wind farm of its type built in Chile, was inaugurated in August

2014 and it supplies approximately 20% of MLP’s energy demand

26

25% 27% 20% 28%

Coal Solar Wind Mix Hydro

20% 20% 16% 44%

2016 2020+

slide-27
SLIDE 27

SomosChoapa

We ARTICULATE regional government and municipalities interaction with private companies and communities, committed to local development in a CONSORTIUM responsible for watching over the implementation of Somos Choapa and its initiatives.

LOS PELAMBRES, LOCAL COMPANIES

MUNICIPALITIES

Canela, Los Vilos, Salamanca, Illapel

REGIONAL GOVERNMENT

SOMOS CHOAPA COMMUNITY

27

slide-28
SLIDE 28

SomosChoapa

Illapel

Participative Process 22 diverse occasions for citizen participation, with nearly 2,000 attendees in total. REVOLVING FUND FOR EXTRAPREDIAL IRRIGATION BORDE RIO: Irrigation Study; Title Study SPORTS AND COMMUNITY CENTER EL POLÍGONO REMODELING RAMÓN “MONCHO” VEGA STADIUM (In development) REMODELING CONSTITUCIÓN STREET

(In development)

SPORTS AND COMMUNITY CENTER LA AGUADA

(In development)

Design for Liceo Politécnico of Illapel

6

Salamanca

6 Territorial meeting 1,260 participants SOCIAL CENTER LUISÍN LANDÁEZ

(In development)

SOCIAL CENTER OF RAYUELA 12 DE OCTUBRE

(In development)

JV CENTER CHALINGA RIVER

(In development)

UNDERGROUND WORKS AV INFANTE (In bidding) SANTA ROSA PLAZA IMPROVEMENT HOUSE OF CULTURE (In bidding) IMPROVEMENT PANGUESILLO FIELD

(In bidding)

Salamanca Park Design

Los Vilos

Participative Process

22 diverse occasions for citizen participation, with nearly 2,000 attendees in total.

PLADECO 2015 – 2019 (Plan for Community Development)

PACA MEETING March 30th 2016 (Anticipated citizen participation) Forming Citizen Committee for the Installation of Somos Choapa Los Vilos

28

Influence area Initiatives under execution Planned initiatives

slide-29
SLIDE 29
  • Two longstanding claims concerning:

Quality and quantity of water in stream

Ability of dam wall to withstand extreme seismic event

  • Formal and transparent dialogue with community

to understand concerns and share views

  • Agreement reached with community in April

2016

  • Both court cases resolved in favour of

Los Pelambres in August 2016

Los Pelambres –El Mauro tailingsdam

29

Outstanding court cases resolved

slide-30
SLIDE 30

30

Growth opportunities

slide-31
SLIDE 31

Growth opportunities

31

2017 2018 2019 2020+ 2016

Incremental Expansion Phase 1

Throughput expansion to 190 ktpd under existing permits. New grinding and flotation circuit to counter the increasing hardness of the ore

Cu: 60 ktpa Capex: US$ 1,100m Incremental Expansion Phase 2

Throughput expansion to 205 ktpd. New permits required. Repower conveyors from primary crusher to

  • concentrator. El Mauro tailing dam capacity increment.

Cu: 30 ktpa Capex: US$ 500m

Feasibility study completion and investment decision Earliest Start of Construction Ramp up Earliest Start of Construction

slide-32
SLIDE 32

Key Messages

  • World class deposit with low strip ratio and large resource base provides opportunity to

unlock value in the long term

  • Ore hardness challenge mitigated by:

Short term  effective operational actions Mid term  plant capacity expansion

  • New community engagement model in place, based on the principles of transparency and

participation

  • Cost improvements to position operation in the first quartile
  • History of strong labour relations with employees and contractors

32

slide-33
SLIDE 33

December 6th, 2016 Robert Mayne Nicholls General Manager

Los Pelambres - Site Visit