Levee Improvement District No. 7 2020 NTRCA Presentation Jim - - PowerPoint PPT Presentation

levee improvement district
SMART_READER_LITE
LIVE PREVIEW

Levee Improvement District No. 7 2020 NTRCA Presentation Jim - - PowerPoint PPT Presentation

Fort Bend County Levee Improvement District No. 7 2020 NTRCA Presentation Jim Grotte, Chairman Cindy Picazo, Vice-Chairman FBCLID 7 Board Gerald Kazmierczak, Secretary of Directors Jeff Hanig, Assistant Secretary Michael


slide-1
SLIDE 1

Fort Bend County Levee Improvement District

  • No. 7

2020 NTRCA Presentation

slide-2
SLIDE 2

FBCLID 7 Board

  • f Directors
  • Jim Grotte, Chairman
  • Cindy Picazo, Vice-Chairman
  • Gerald Kazmierczak, Secretary
  • Jeff Hanig, Assistant Secretary
  • Michael Pincomb, Director
slide-3
SLIDE 3

FBCLID 7 – Key Consultants

  • Schwartz Page Harding, LLP – Attorney
  • LJA, Inc. – Engineer
  • Levee Management System – Operator
  • Myrtle Cruz, Inc. – Bookkeeper
  • Masterson Advisors – Financial Advisor
  • AECOM –Brazos River Erosion Control Project Design

Engineer

  • Mike Stone Associates – Global Project Management
  • Touchstone District Services – District Communications
slide-4
SLIDE 4

Agenda

Projects

  • Brazos River Erosion Control Project
  • External Discharge Channel Erosion Control
  • Pumping Station Expansion
  • Detention
  • North Levee Closure

Costs Timing Q&A

slide-5
SLIDE 5

Fort Bend LID 7

slide-6
SLIDE 6

Brazos River Erosion Control Project

30% design nearing completion (AECOM) US Army Corps of Engineers (USACE) permit approval expected in next 30 days 75% FEMA project reimbursement awarded (approx. $45M) Fort Bend LID 7 is the first county entity to tackle a project on the Brazos

slide-7
SLIDE 7

Brazos River Erosion Control Design

slide-8
SLIDE 8
slide-9
SLIDE 9

Timing Brazos River Project

June 2020 Award design contract

  • Dec. 2020

TDEM / FEMA design review and approval July 2021 Start construction

  • Nov. 2022

Construction complete

slide-10
SLIDE 10

External Discharge Channel Erosion Control

  • Erosion control project
  • Outlet channel to Brazos River
  • Natural design qualifies for 80% cost reimbursement

October 2019

Grant Funding approved

February 2020

Construction Contract Awarded

2020

Construction Complete

slide-11
SLIDE 11

External Channel Project Site

slide-12
SLIDE 12

Internal Drainage Study

Study required for detention and pumpage expansions Facilitates scenario modeling for detention and pumpage expansions Generates models showing water elevations during extreme rainfall events Scenarios based on ‘Atlas 14’ 10- and 100- year rainfall studies (FEMA standard)

slide-13
SLIDE 13

Harvey High Water Map

slide-14
SLIDE 14

Pump Station Expansion

  • Increase pumping capacity by an additional 210,000 GPM
  • Designed for better maintainability
  • Accounts for increased automation to reduce need for
  • n-site personnel

March 2020

Design Approval

End of Year 2020

Design Complete

2021

Construction Begins

slide-15
SLIDE 15

Pump Station Expansion Preliminary Design

slide-16
SLIDE 16

Detention

Short-term storage during peak events Gives pumps time to catchup Several options under consideration Probably to include multiple sites

slide-17
SLIDE 17

North Levee Enclosure

Proposed Regional Levee South of 90A from 359 to Pitts Road Proposed Smith Ranch Levee South 90A from Pitts Road to New Territory If constructed: Levee would protect LID 7 North Side Make any improvements made by LID 7 obsolete Working with County to protect 99/90A intersection from flooding due to Bull Head Slough

slide-18
SLIDE 18

Flood Protection Projects

  • External Discharge Outfall Channel

$ 4M

  • Increased Stormwater Pumping Capacity

$13M

  • Increased Stormwater Detention

$14M

  • Brazos River Erosion Control Project

$60M

  • North Levee Closure

TBD Total $91M

slide-19
SLIDE 19

Tax Rate Impact

GOAL IS TO FUND ALL PROJECTS WITH 2019 TAX RATE OF $0.43 $91M –TOTAL PROJECT COSTS SEEKING ADDITIONAL OUTSIDE FUNDING (SB 7)

slide-20
SLIDE 20

Tax Rate History

Year Debt Service Tax Rate Maintenance Tax Rate Total Tax Rate 2019 $0.18 $0.25 $ 0.430 2018 $0.18 $0.14 $ 0.320 2017 $0.10 $0.22 $ 0.320 2016 $0.14 $0.085 $ 0.225

slide-21
SLIDE 21

Q&A

Think of a question on the drive home? Don’t worry! Reach out with your question on the FBCLID 7 website: www.fbclid7.com