BUCKROE BOARDWALK Repairs, Renovation, & Extension 11 September - - PowerPoint PPT Presentation
BUCKROE BOARDWALK Repairs, Renovation, & Extension 11 September - - PowerPoint PPT Presentation
BUCKROE BOARDWALK Repairs, Renovation, & Extension 11 September 2019 OVERVIEW Current conditions + scope Design options + costs Overall plan + common design features 3 Options for existing boardwalk 3 Options for southern
OVERVIEW
- Current conditions + scope
- Design options + costs
- Overall plan + common design features
- 3 Options for existing boardwalk
- 3 Options for southern section/extension
- Recommendations
- Next Steps
- Questions
current CONDITIONS
current CONDITIONS
SCOPE
- Repair items identified by Hampton Public Works
- Evaluate structural integrity of seawall
- Repairs to seawall, boardwalk, and masonry planters
- Extend boardwalk south to James T. Wilson Fishing Pier
- Provide ADA accessible design improvements
- Provide increased seating options along boardwalk
- Evaluate lighting
- Design to reduce sand buildup on boardwalk
- Identify planting opportunities & low-maintenance plantings
- Evaluate option for removing existing seawall and building
raised boardwalk
DESIGN: overall plan
DESIGN: amenities
Proposed Boardwalk Bench Proposed Boardwalk Garbage Bin Proposed LED Lighting
DESIGN: plantings
Shade Tree Live Oak Evergreen Tree Japanese Black Pine Flowering Tree Crepe Myrtle Ornamental Grass Salt Meadow Hay Ornamental Grass Blue Switchgrass Ornamental Grass Coastal Panic Grass
DESIGN: seawall
Decorative Seawall Option 1 Decorative Seawall Option 2 Decorative Seawall Option 3
DESIGN: pedestrian beach access
Proposed Pedestrian Access Ramp Placement = every 200’ Existing Steps
DESIGN: options
Existing boardwalk
- Repair
- Reconstruction
- Raised*
Southern section/extension
- Streetscape
- Composite
- Seawall + streetscape
DESIGN: northern section
Repair Option Reconstruction Option
DESIGN: buckroe park section
Repair & Reconstruction Option
COSTS
northern & buckroe park sections Repair Reconstruction $3,675,000 $6,000,000
Includes improvements to concrete seawall (+ seating), boardwalk surface, planters, ADA accessibility, replacement of lighting, plantings Major cost difference between ‘Repair’ & ‘Reconstruction” is the concrete seawall cap & the boardwalk surface reconstruction
30 yrs 50 yrs
DESIGN: southern section/extension
Streetscape Concept Composite Concept
COSTS
southern section/extension Streetscape Composite Seawall + Streetscape $400,000 $525,000
Realignment of seawall will take approx. 6’ – 8’ of beach
$1,100,000
DESIGN: raised boardwalk
Northern Section (below) Southern Section (above) Buckroe Park Section (above)
COSTS: raised boardwalk
Raised $18,400,000
- Raised approx. 5’6” above ground level, with additional 3’
railing on top
- Width ranges from 12’ – 41’ dependent upon section
- Access onto and off of is more challenging
- Creates visual barrier between park and beach
75 yrs
planned FUNDING
Capital Funding for ‘Enhanced Park Maintenance & Buckroe Boardwalk’
FY 20 FY 21 FY 22 $1,000,000 $3,000,000 $2,000,000 $6,000,000
for total project
- Can shift funding to necessary fiscal year
- Can supplement with PRLS capital funding
COSTS
northern & buckroe park sections Repair Reconstruction Raised $3,675,000 $6,000,000 $18,400,000
Includes improvements to concrete seawall (+ seating), boardwalk surface, planters, ADA accessibility, replacement of lighting, plantings Major cost difference between ‘Repair’ & ‘Reconstruction” is the concrete seawall cap & the boardwalk surface reconstruction
30 yrs 50 yrs 75 yrs
COSTS
southern section/extension Streetscape Composite Seawall + Streetscape $400,000 $525,000
Realignment of seawall will take approx. 6’ – 8’ of beach
$1,100,000
RECOMMENDATION
Reconstruction Seawall + Streetscape $6,000,000 $1,100,000 50 yrs 75 yrs $7,100,000
for total project
- Structural, aesthetic, and accessibility improvements
- Consistent with character of neighborhood, uniform look and
enhanced durability
- Divvied out into 2 components for permitting purposes if
choosing to realign seawall
- $1.1 million over the allotted funding/augment with PRLS
maintenance funds
NEXT STEPS
Meet with Community Phasing Plan for Construction Phase 1: Buckroe Park Future Phases: Construction Document Prep & Permitting ITB for Construction Contract Complete Phase 2: Construction begins
Tentative September 2019 November 2019 June 2020 August 2020 December 2019 – May 2020 September 2020 Complete Pre Summer 2020