  1. BUCKROE BOARDWALK Repairs, Renovation, & Extension 11 September 2019

  2. OVERVIEW • Current conditions + scope • Design options + costs • Overall plan + common design features • 3 Options for existing boardwalk • 3 Options for southern section/extension • Recommendations • Next Steps • Questions

  3. current CONDITIONS

  4. current CONDITIONS

  5. SCOPE • Repair items identified by Hampton Public Works • Evaluate structural integrity of seawall • Repairs to seawall, boardwalk, and masonry planters • Extend boardwalk south to James T. Wilson Fishing Pier • Provide ADA accessible design improvements • Provide increased seating options along boardwalk • Evaluate lighting • Design to reduce sand buildup on boardwalk • Identify planting opportunities & low-maintenance plantings • Evaluate option for removing existing seawall and building raised boardwalk

  6. DESIGN: overall plan

  7. DESIGN: amenities Proposed Proposed Boardwalk Proposed LED Boardwalk Bench Garbage Bin Lighting

  8. DESIGN: plantings Shade Tree Evergreen Tree Flowering Tree Live Oak Japanese Black Pine Crepe Myrtle Ornamental Grass Ornamental Grass Ornamental Grass Salt Meadow Hay Coastal Panic Grass Blue Switchgrass

  9. DESIGN: seawall Decorative Seawall Option 1 Decorative Seawall Option 2 Decorative Seawall Option 3

  10. DESIGN: pedestrian beach access Proposed Pedestrian Access Ramp Existing Steps Placement = every 200’

  11. DESIGN: options Existing boardwalk • Repair • Reconstruction • Raised* Southern section/extension • Streetscape • Composite • Seawall + streetscape

  12. DESIGN: northern section Repair Option Reconstruction Option

  13. DESIGN: buckroe park section Repair & Reconstruction Option

  14. COSTS northern & buckroe park sections 30 yrs Repair $3,675,000 50 yrs Reconstruction $6,000,000 Includes improvements to concrete seawall (+ seating), boardwalk surface, planters, ADA accessibility, replacement of lighting, plantings Major cost difference between ‘Repair’ & ‘Reconstruction” is the concrete seawall cap & the boardwalk surface reconstruction

  15. DESIGN: southern section/extension Streetscape Concept Composite Concept

  16. COSTS southern section/extension Streetscape $400,000 Composite $525,000 Seawall + Streetscape $1,100,000 Realignment of seawall will take approx. 6’ – 8’ of beach

  17. DESIGN: raised boardwalk Northern Section (below) Buckroe Park Section (above) Southern Section (above)

  18. COSTS: raised boardwalk 75 yrs Raised $18,400,000 Raised approx. 5’6” above ground level, with additional 3’ • railing on top Width ranges from 12’ – 41’ dependent upon section • Access onto and off of is more challenging • Creates visual barrier between park and beach •

  19. planned FUNDING Capital Funding for ‘Enhanced Park Maintenance & Buckroe Boardwalk’ FY 20 $1,000,000 FY 21 $3,000,000 FY 22 $2,000,000 $6,000,000 for total project Can shift funding to necessary fiscal year • Can supplement with PRLS capital funding •

  20. COSTS northern & buckroe park sections 30 yrs Repair $3,675,000 50 yrs Reconstruction $6,000,000 75 yrs Raised $18,400,000 Includes improvements to concrete seawall (+ seating), boardwalk surface, planters, ADA accessibility, replacement of lighting, plantings Major cost difference between ‘Repair’ & ‘Reconstruction” is the concrete seawall cap & the boardwalk surface reconstruction

  21. COSTS southern section/extension Streetscape $400,000 Composite $525,000 Seawall + Streetscape $1,100,000 Realignment of seawall will take approx. 6’ – 8’ of beach

  22. RECOMMENDATION 50 yrs Reconstruction $6,000,000 75 yrs Seawall + Streetscape $1,100,000 $7,100,000 for total project Structural, aesthetic, and accessibility improvements • Consistent with character of neighborhood, uniform look and • enhanced durability Divvied out into 2 components for permitting purposes if • choosing to realign seawall $1.1 million over the allotted funding/augment with PRLS • maintenance funds

  23. NEXT STEPS Meet with Community Tentative September 2019 Phasing Plan for Construction November 2019 Phase 1: Buckroe Park Complete Pre Summer 2020 Future Phases: Construction December 2019 – May 2020 Document Prep & Permitting ITB for Construction June 2020 Contract Complete August 2020 Phase 2: Construction begins September 2020

  24. Questions?

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.