DESCRIPTION TRAFFIC EMERGENCY ROAD NAME: JP DISTRICT: MILEAGE: CONDITIONS: AREA: COST: SCHOOL BUSES: OF WORK: COUNTS: CALLS: Bogey Ln. 2 0.2 Critical Prairie Creek Asphalt Overlay $23,600.00 7 day- 100 2 1 Browning Rd. 12
Benton County ROAD NAME: JP DISTRICT: MILEAGE: CONDITIONS: AREA: DESCRIPTION OF WORK: COST: TRAFFIC COUNTS: SCHOOL BUSES: EMERGENCY CALLS: Bogey Ln. 2 0.2 Critical Prairie Creek Asphalt Overlay $23,600.00 7 day- 100 1 2 Browning Rd. 12 1.3 Fair Gentry Asphalt Overlay $153,000.00 6 day- 3853 1 19 Coose Hollow Ln. 11 1.4 Fair Rogers Asphalt Overlay $164,600.00 7 day- 1495 4 17 Cottonwood Ln. 2 0.3 Fair Beaver Shores Asphalt Overlay $25,900.00 5 day- 135 2 7 Fain Dr. 1 0.7 Critical Hwy 303 Asphalt Overlay $71,300.00 6 day- 758 2 4 Gum Dr. 2 0.1 Critical Beaver Shores Asphalt Overlay $11,800.00 5 day- 94 2 2 Gum Ln. 2 0.1 Critical Beaver Shores Asphalt Overlay $11,800.00 5 day- 56 2 6 Indian Creek Dr. 1 0.7 Fair Garfield Asphalt Overlay $71,300.00 7 day- 864 1 8 Jack Crabtree Rd. 7 1 Fair Bentonville/Bella Vista Asphalt Overlay $117,600.00 5 day- 4005 5 10 Larue Rd. 1 2.4 Fair Hwy 303 Asphalt Overlay $126,000.00 6 day - 1,547 2 11 Maple Ln. 2 0.2 Fair Beaver Shores Asphalt Overlay $23,525.00 5 day- 210 2 4 Old Prairie Creek Rd. 2 1.1 Fair Hwy 12 Asphalt Overlay $122,570.00 7 day- 4659 6 23 Park 2 0.4 Critical Prairie Creek Asphalt Overlay $47,200.00 7 day- 300 1 Tanglewood Rd. 1 1.8 Fair Hwy 303 Asphalt Overlay $211,300.00 6 day- 1227 2 1 Gailey Hollow Rd. 13 5 Fair Siloam Springs Crack Seal $6,164.00 TOTAL MILEAGE: 16.7 TOTAL COST: $1,187,659.00 POTHOLES 250 $50,000.00 LEVEL COATING $100,000 TOTAL ASPHALT BUDGET $1,337,659.00
❖ Larue Rd. not yet complete
Benton County
❖ Section repairs
- n:
▪
Beaty Rd.
▪
Black Oak Dr.
▪
Hickory Creek Rd.
Benton County
❖ IMPROVED WITH RED DIRT:
Approximately 66 roads / portions of road
❖ IMPROVED WITH GRAVEL:
Approximately 74 roads / portions of road
❖ CONCRETE:
Approximately 34 roads/projects
❖ CULVERTS:
Approximately 56 roads/projects
❖ BRUSH CUTTERS:
On 4th rotation
❖ GRADERS:
On 4th rotation
Benton County
Benton County
❖ Up and coming projects to be completed in 2021 ▪ Osage Hill Rd. ▪ Lawson Rd. ▪ Stephens Rd.
❖ YEARLY HAZARD MITIGATION GRANT FROM THE STATE THAT PROVIDES PERMANENT SOLUTIONS TO FLOOD PRONE AREAS ❖ COST SHARE: 50% / 50% ❖ SITES COMPLETED: Posy Mtn. Rd. & Coose Hollow Ln. ❖ TOTAL COST: $268,971.83 ❖ Future Project: Bill Young Rd.
❖ EMERGENCY WATERSHED PROTECTION PROGRAM THAT HELPS REMOVE HAZARD AND RESTORE STREAM BANK PROTECTION ❖ COST SHARE: 75% / 25% ❖ 6 SITES TOTAL/3 BRIDGE SITES ❖ TOTAL COST: $654,000
❖ Federal Share: $493,000 ❖ County Share: $161,000
❖COMPLETED
Benton County
❖ OVER 200 BRIDGES, CULVERTS, & LOW WATER CROSSINGS. ❖ 92 BRIDGES INSPECTED BY ARDOT AS PART OF THE NATIONAL BRIDGE INSPECTION PROGRAM. ❖ 50+ ARDOT BRIDGE INSPECTION REPORTS RECEIVED ANNUALLY.
Benton County
Benton County
❖ BRIDGE REPORTS COMPLETED: 20 ❖ N MOUNT OLIVE OVER WOLF CREEK ▪ REPLACED FAILED ABUTMENT WINGWALL ▪ REPAIRED FOUNDATION DAMAGE DUE TO EROSION ❖ STAGE COACH ROAD OVER SPAVINAW CREEK ▪ IMPROVEMENTS TO PREVENT REPEATED DAMAGE FROM EROSION ▪ UNDERPINNING THE ABUTMENTS AND APPROACHES WITH ROCK ▪ INSTALLING GABION BASKETS AT BASE OF PILE CAP TO PREVENT LOSS OF MATERIAL FROM UNDER AND BEHIND ABUTMENT ❖ LIMEKILN ROAD OVER SPAVINAW CREEK ▪ REPAIRED EXPOSED H-PILES DUE TO STORM EROSION
WAGON WHEEL BRIDGE COW FACE BRIDGE
❖ Engineering & Environmental consultants have completed 60% design and submitted to ARDOT for approval ❖ Awarded $1.5M STBGP-A Grant from NWARPC for Construction in 2021 ❖ Estimated cost: $1.5 M (80% Fed/20% local) ❖ COMPLETED!!! ❖ Cost: $932,836
OSAGE BRIDGE (OLD HWY 68)
❖ State Aid bridge ❖ Project Has Bid & Construction to Begin This Year ❖ Low Bid: $2,333,296.55 ❖ Cost share: 80% fed., 18% State, & 2% County
Benton County
ROBINSON BRIDGE
❖ Currently being designed in-house for construction in 2021 ❖ Estimated Cost $800,000
COLUMBIA HOLLOW
❖ Planned for Construction in 2021
Benton County
Benton County
ROAD DEPT. BRIDGE PROJECTS: PROJECT PHASE: BUDGET TOTAL: OFFSETTING REVENUE: 2020 CAPITAL REQUEST STATUS: ROBINSON ROAD BRIDGE CONST. $800,000.00 $0.00 $800,000.00 OSAGE CREEK BRIDGE CONST. $4,000,000.00 $3,920,000.00 $80,000.00 STATE AID 98/2 COON HOLLOW BRIDGE DESIGN $15,000.00 $0.00 $15,000.00 STATE AID WAGON WHEEL BRIDGE ROW $40,000.00 $0.00 $40,000.00 COLUMBIA HOLLOW BRIDGE DESIGN $225,000.00 $0.00 $225,000.00 $5,080,000 $3,920,000 $1,160,000 2020 PROJECT GRAND TOTALS:
Benton County
❖ IN 2017 THERE WERE 14 STRUCTURALLY DEFICIENT BRIDGES ❖ TODAY THERE ARE ONLY 7 ▪ 2 HAVE BEEN REPAIRED BUT NOT REINSPECTED ▪ 1 TO BEGIN CONSTRUCTION THIS YEAR ▪ 2 TO BEGIN CONSTRUCTION NEXT YEAR ❖ 5 YEAR PLAN TO BEGIN INCLUDING MORE MAJOR REPAIR & REHAB PROJECTS IN COMING YEARS