Larue Rd. not yet complete Benton County Section repairs on: - PowerPoint PPT Presentation

DESCRIPTION TRAFFIC EMERGENCY ROAD NAME: JP DISTRICT: MILEAGE: CONDITIONS: AREA: COST: SCHOOL BUSES: OF WORK: COUNTS: CALLS: Bogey Ln. 2 0.2 Critical Prairie Creek Asphalt Overlay $23,600.00 7 day- 100 2 1 Browning Rd. 12


  1. DESCRIPTION TRAFFIC EMERGENCY ROAD NAME: JP DISTRICT: MILEAGE: CONDITIONS: AREA: COST: SCHOOL BUSES: OF WORK: COUNTS: CALLS: Bogey Ln. 2 0.2 Critical Prairie Creek Asphalt Overlay $23,600.00 7 day- 100 2 1 Browning Rd. 12 1.3 Fair Gentry Asphalt Overlay $153,000.00 6 day- 3853 1 19 Coose Hollow Ln. 11 1.4 Fair Rogers Asphalt Overlay 7 day- 1495 $164,600.00 4 17 Cottonwood Ln. 2 0.3 Fair Beaver Shores Asphalt Overlay $25,900.00 5 day- 135 7 2 Fain Dr. 1 0.7 Critical Hwy 303 Asphalt Overlay $71,300.00 6 day- 758 4 2 Gum Dr. 2 0.1 Critical Beaver Shores Asphalt Overlay $11,800.00 5 day- 94 2 2 Gum Ln. 2 0.1 Critical Beaver Shores Asphalt Overlay $11,800.00 5 day- 56 6 2 Indian Creek Dr. 1 0.7 Fair Garfield Asphalt Overlay $71,300.00 7 day- 864 1 8 Jack Crabtree Rd. 7 1 Fair Bentonville/Bella Vista Asphalt Overlay $117,600.00 5 day- 4005 10 5 Larue Rd. 1 2.4 Fair Hwy 303 Asphalt Overlay $126,000.00 6 day - 1,547 11 2 Maple Ln. 2 0.2 Fair Beaver Shores Asphalt Overlay $23,525.00 5 day- 210 4 2 Old Prairie Creek Rd. 2 1.1 Fair Hwy 12 Asphalt Overlay $122,570.00 7 day- 4659 6 23 Park 2 0.4 Critical Prairie Creek Asphalt Overlay $47,200.00 7 day- 300 1 0 Tanglewood Rd. 1 1.8 Fair Hwy 303 Asphalt Overlay $211,300.00 6 day- 1227 1 2 Gailey Hollow Rd. 13 5 Fair Siloam Springs Crack Seal $6,164.00 TOTAL MILEAGE: 16.7 TOTAL COST: $1,187,659.00 POTHOLES 250 $50,000.00 LEVEL COATING $100,000 TOTAL ASPHALT BUDGET $1,337,659.00 ❖ Larue Rd. not yet complete Benton County

  2. ❖ Section repairs on: ▪ Beaty Rd. ▪ Black Oak Dr. ▪ Hickory Creek Rd. Benton County

  3. ❖ IMPROVED WITH RED DIRT: Approximately 66 roads / portions of road ❖ IMPROVED WITH GRAVEL: Approximately 74 roads / portions of road ❖ CONCRETE: Approximately 34 roads/projects ❖ CULVERTS: Approximately 56 roads/projects ❖ BRUSH CUTTERS: On 4 th rotation ❖ GRADERS: On 4 th rotation Benton County

  4. Benton County

  5. YEARLY HAZARD MITIGATION ❖ GRANT FROM THE STATE THAT PROVIDES PERMANENT SOLUTIONS TO FLOOD PRONE AREAS COST SHARE: ❖ 50% / 50% SITES COMPLETED: ❖ Posy Mtn. Rd. & Coose Hollow Ln. TOTAL COST: ❖ $268,971.83 ❖ Up and coming projects to be Future Project: ❖ completed in 2021 Bill Young Rd. ▪ Osage Hill Rd. ▪ Lawson Rd. ▪ Stephens Rd. Benton County

  6. ❖ EMERGENCY WATERSHED PROTECTION PROGRAM THAT HELPS REMOVE HAZARD AND RESTORE STREAM BANK PROTECTION ❖ COST SHARE: 75% / 25% ❖ 6 SITES TOTAL/3 BRIDGE SITES ❖ TOTAL COST: $654,000 ❖ Federal Share: $493,000 ❖ County Share: $161,000 ❖ COMPLETED Benton County

  7. ❖ OVER 200 BRIDGES, CULVERTS, & LOW WATER CROSSINGS. ❖ 92 BRIDGES INSPECTED BY ARDOT AS PART OF THE NATIONAL BRIDGE INSPECTION PROGRAM. ❖ 50+ ARDOT BRIDGE INSPECTION REPORTS RECEIVED ANNUALLY. Benton County

  8. ❖ BRIDGE REPORTS COMPLETED: 20 ❖ N MOUNT OLIVE OVER WOLF CREEK ▪ REPLACED FAILED ABUTMENT WINGWALL ▪ REPAIRED FOUNDATION DAMAGE DUE TO EROSION ❖ STAGE COACH ROAD OVER SPAVINAW CREEK ▪ IMPROVEMENTS TO PREVENT REPEATED DAMAGE FROM EROSION ▪ UNDERPINNING THE ABUTMENTS AND APPROACHES WITH ROCK ▪ INSTALLING GABION BASKETS AT BASE OF PILE CAP TO PREVENT LOSS OF MATERIAL FROM UNDER AND BEHIND ABUTMENT ❖ LIMEKILN ROAD OVER SPAVINAW CREEK ▪ REPAIRED EXPOSED H-PILES DUE TO STORM EROSION Benton County

  9. COW FACE WAGON WHEEL OSAGE BRIDGE BRIDGE (OLD HWY 68) BRIDGE State Aid bridge COMPLETED!!! ❖ ❖ Engineering & Environmental ❖ Project Has Bid & Construction ❖ Cost: $932,836 ❖ consultants have completed 60% to Begin This Year design and submitted to ARDOT for Low Bid: $2,333,296.55 ❖ approval Cost share: 80% fed., 18% State, ❖ & 2% County Awarded $1.5M STBGP-A Grant from ❖ NWARPC for Construction in 2021 Estimated cost: $1.5 M (80% ❖ Fed/20% local) Benton County

  10. COLUMBIA ROBINSON HOLLOW BRIDGE Planned for Construction in 2021 Currently being designed in-house for ❖ ❖ construction in 2021 Estimated Cost $800,000 ❖ Benton County

  11. 2020 PROJECT BUDGET OFFSETTING ROAD DEPT. BRIDGE PROJECTS: CAPITAL STATUS: PHASE: TOTAL: REVENUE: REQUEST ROBINSON ROAD BRIDGE CONST. $800,000.00 $0.00 $800,000.00 OSAGE CREEK BRIDGE CONST. $4,000,000.00 $3,920,000.00 $80,000.00 STATE AID 98/2 COON HOLLOW BRIDGE DESIGN $15,000.00 $0.00 $15,000.00 STATE AID WAGON WHEEL BRIDGE ROW $40,000.00 $0.00 $40,000.00 COLUMBIA HOLLOW BRIDGE DESIGN $225,000.00 $0.00 $225,000.00 2020 PROJECT GRAND TOTALS: $5,080,000 $3,920,000 $1,160,000 Benton County

  12. ❖ IN 2017 THERE WERE 14 STRUCTURALLY DEFICIENT BRIDGES ❖ TODAY THERE ARE ONLY 7 ▪ 2 HAVE BEEN REPAIRED BUT NOT REINSPECTED ▪ 1 TO BEGIN CONSTRUCTION THIS YEAR ▪ 2 TO BEGIN CONSTRUCTION NEXT YEAR ❖ 5 YEAR PLAN TO BEGIN INCLUDING MORE MAJOR REPAIR & REHAB PROJECTS IN COMING YEARS Benton County

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.