SR 9/I-95 at PGA Boulevard/ Central Boulevard PD&E Study Financial Project Number: 413265-1-22-01 ETDM Number: 13748 Public Kick-Off Meeting Presented to: Presented by: Public Kickoff Meeting Florida Department of Transportation


slide-1
SLIDE 1

Presented to:

Public Kickoff Meeting

Presented by:

Florida Department of Transportation District 4

  • Ms. Bing Wang

Public Kick-Off Meeting

PD&E

SR 9/I-95

Study

at PGA Boulevard/ Central Boulevard

Financial Project Number: 413265-1-22-01 ETDM Number: 13748

slide-2
SLIDE 2

PD&E

SR 9/I-95

Study

at PGA Boulevard/ Central Boulevard

Financial Project Number: 413265-1-22-01 ETDM Number: 13748

Introduction What is a PD&E Description of Project Interchange Justification Report Process & Initial Results Project Development & Environment (PD&E) Process PD&E Study Schedule Closing

slide-3
SLIDE 3

PD&E

SR 9/I-95

Study

at PGA Boulevard/ Central Boulevard

Financial Project Number: 413265-1-22-01 ETDM Number: 13748

The Florida Department of Transportation is required to comply with various non-discrimination laws and regulations, including Title VI of the Civil Rights Act of 1964. Public participation is solicited without regard to race, color, national origin, age, sex, religion, disability or family status. Persons wishing to express their concerns about Title VI may do so by contacting either:

Title VI

District Four Florida Department of Transportation

District Four Title VI Coordinator Adrienne Brown 3400 West Commercial Boulevard Fort Lauderdale, Florida 33309-3421 (954) 777-4190 or Toll free at (866) 336-8435, ext. 4190 martha.anderson@dot.state.fm.us

Tallahassee Offjce Florida Department of Transportation

State Title VI Coordinator Jacqueline Paramore Equal Opportunity Offjce 605 Suwannee Street, MS 65 Tallahassee, Florida 32399-0450 (850) 414-4753 Jacqueline.paramore@dot.state.fm.us

All inquiries or complaints will be handled according to FDOT procedure and in a prompt and courteous manner.

slide-4
SLIDE 4

PD&E

SR 9/I-95

Study

at PGA Boulevard/ Central Boulevard

Financial Project Number: 413265-1-22-01 ETDM Number: 13748

Poten&al ¡I-­‑95/ Central ¡Blvd. ¡ Interchange ¡ Study ¡ Interchange ¡

slide-5
SLIDE 5

PD&E

SR 9/I-95

Study

at PGA Boulevard/ Central Boulevard

Financial Project Number: 413265-1-22-01 ETDM Number: 13748

PROJECT PURPOSE The purpose of the project is to improve operational capacity and overall traffjc operations by providing improvements at the existing interchange of SR 9 (I-95) and SR 786 (PGA Boulevard) in order to achieve acceptable Levels of Service (LOS) at the interchange in the future condition. Conditions at PGA Boulevard are anticipated to deteriorate below acceptable LOS standards if no improvements occur by 2035; the interchange will have insuffjcient capacity to accommodate the projected travel demand. PROJECT NEED Improvements in the area of the I-95 / PGA Boulevard Interchange are needed in order to:

  • Improve Operational Capacity and Overall Traffjc Operations

(Level of Service)

  • Accommodate Future Population and Employment Growth
  • Enhance Freight Mobility
  • Enhance Emergency Evacuation and Response Times
slide-6
SLIDE 6

PD&E

SR 9/I-95

Study

at PGA Boulevard/ Central Boulevard

Financial Project Number: 413265-1-22-01 ETDM Number: 13748

Transportation Process

Phase 1

Planning

Phase 3

Final Design & Engineering

Phase 4

Right of Way Acquisition

Phase 5

Construction

Phase 6

Maintenance

Phase 2

Project Development & Environment (PD&E) Study

Tier 1 Range of Considerations 26 Concepts Identifjed Fatal Flaw Analysis 10 Concepts Selected Present Two Best Alternatives in Interchange Justifjcation Report Tier 3 Selection of Preferred Traffjc Operational Analysis Performed

  • n 6 Alternatives

Comparative Evaluation of 6 Alternatives Selection of 2 Alternatives Tier 2 Develop Alternatives 10 Alternatives Developed Traffjc Projections Conducted 6 Best Performing Alternatives Selected

Phase 1 – Interchange Justifjcation Report Process

Public Involvement

slide-7
SLIDE 7

PD&E

SR 9/I-95

Study

at PGA Boulevard/ Central Boulevard

Financial Project Number: 413265-1-22-01 ETDM Number: 13748

Existing (2013) Traffjc Conditions

Intersection and Link Level of Service (LOS)

slide-8
SLIDE 8

PD&E

SR 9/I-95

Study

at PGA Boulevard/ Central Boulevard

Financial Project Number: 413265-1-22-01 ETDM Number: 13748

slide-9
SLIDE 9

PD&E

SR 9/I-95

Study

at PGA Boulevard/ Central Boulevard

Financial Project Number: 413265-1-22-01 ETDM Number: 13748

Poten&al ¡I-­‑95/ Central ¡Blvd. ¡ Interchange ¡

slide-10
SLIDE 10

PD&E

SR 9/I-95

Study

at PGA Boulevard/ Central Boulevard

Financial Project Number: 413265-1-22-01 ETDM Number: 13748

971 670 116 45

  • 2.2%
  • 6.9%

480 474 3 57 6.2% 18.3% 11.5%

12.9%

417 305 540 276 124 57 13.9% 18.1% 20.4%

17.7%

127 113 13.5%

PGA Boulevard Interchange 12.9% Decrease in Peak Hour Traffjc Donald Ross Road Interchange 17.7% Decrease in Peak Hour Traffjc

Reduction in 2040 Volumes No-Build to Build LEGEND

% Reduction % Increase AM AM PM PM

Increase in 2040 Volumes No-Build to Build

Traffic Impacts on Adjacent Interchanges

slide-11
SLIDE 11

PD&E

SR 9/I-95

Study

at PGA Boulevard/ Central Boulevard

Financial Project Number: 413265-1-22-01 ETDM Number: 13748

Poten&al ¡I-­‑95/ Central ¡Blvd. ¡ Interchange ¡

slide-12
SLIDE 12

PD&E

SR 9/I-95

Study

at PGA Boulevard/ Central Boulevard

Financial Project Number: 413265-1-22-01 ETDM Number: 13748

Transportation Process

Phase 1

Planning

Phase 3

Final Design & Engineering

Phase 4

Right of Way Acquisition

Phase 5

Construction

Phase 6

Maintenance

Phase 2

Project Development & Environment (PD&E) Study Data Collection Engineering Input Other Information Environmental Input Engineering Analysis & Design Engineering Analysis Preliminary Engineering Screening Preliminary Concept Analysis Needs Analysis Initial Concept Developments Preliminary Concept Screening Environmental Analysis Environmental Studies Environmental Documents Value Engineering Final Documents Project Engineering Report Categorical Exclusion Type II FHWA Review of Final Document FHWA Issues the Location & Design Concept Acceptance (LDCA)

Phase 2 – Project Development & Environmental (PD&E) Study

Public Involvement

slide-13
SLIDE 13

PD&E

SR 9/I-95

Study

at PGA Boulevard/ Central Boulevard

Financial Project Number: 413265-1-22-01 ETDM Number: 13748

No-Build Transportation System Management (TSM) Improvements to PGA Boulevard Interchange New Interchange at Central Boulevard Improvements to Arterial Street Intersections

slide-14
SLIDE 14

PD&E

SR 9/I-95

Study

at PGA Boulevard/ Central Boulevard

Financial Project Number: 413265-1-22-01 ETDM Number: 13748

  • Efficient Transportation Decision Making (ETDM) #13748
  • Effective/timely decision making without compromising environmental quality
  • Enables agencies and public to provide early input about the potential effects of proposed

transportation projects

  • Class of Action – Categorical Exclusion Type II
  • For more ETDM information regarding this project please visit:

https://etdmpub.fla-etat.org/

slide-15
SLIDE 15

PD&E

SR 9/I-95

Study

at PGA Boulevard/ Central Boulevard

Financial Project Number: 413265-1-22-01 ETDM Number: 13748

Natural Resources

  • Natural Wetlands outside of current R/W
  • Drainage features with wetland

vegetation within R/W

  • Other Surface Waters - Drainage District

Canal

  • Lake Worth Lagoon – Palm Beach

Coast impaired watershed

  • Threatened and Endangered Species
slide-16
SLIDE 16

PD&E

SR 9/I-95

Study

at PGA Boulevard/ Central Boulevard

Financial Project Number: 413265-1-22-01 ETDM Number: 13748

Socio-economic Benefits

  • No relocations anticipated
  • No impacts to community facilities
  • Increase mobility and access

Planned ¡DRI’s ¡ Future ¡Land ¡Use ¡ ¡

slide-17
SLIDE 17

PD&E

SR 9/I-95

Study

at PGA Boulevard/ Central Boulevard

Financial Project Number: 413265-1-22-01 ETDM Number: 13748

Noise

  • Potential noise sensitive receptors will be identified.
  • A Noise Study Report will be prepared.
  • Noise abatement will be considered if reasonable and feasible.
slide-18
SLIDE 18

PD&E

SR 9/I-95

Study

at PGA Boulevard/ Central Boulevard

Financial Project Number: 413265-1-22-01 ETDM Number: 13748

Cultural Resources

  • No National Register-listed sites
  • One potential historic site
  • No known archaeological sites

Recreational Sites

  • Palm Beach Gardens District Nature Park
  • City of Palm Beach Gardens Tennis Center
slide-19
SLIDE 19

PD&E

SR 9/I-95

Study

at PGA Boulevard/ Central Boulevard

Financial Project Number: 413265-1-22-01 ETDM Number: 13748

  • Additional Environmental

Analysis will be completed

  • Anticipate minor or no impacts to:
  • Water Quality/Floodplains
  • Contamination
  • Air Quality
  • Construction Impacts
  • Aesthetics
slide-20
SLIDE 20

PD&E

SR 9/I-95

Study

at PGA Boulevard/ Central Boulevard

Financial Project Number: 413265-1-22-01 ETDM Number: 13748

PHASE 2

PD&E Study

2015 2016

January February March April May June July August September October November December January February March April

Notice to Proceed Project Kick-Ofg Meeting Public Kick-Ofg Meeting Engineering Analysis Environmental Analysis Alternatives Public Meeting Public Hearing Federal Highway Administration Review Location Design Concept Acceptance

Public Involvement

PHASE I

Interchange Justifjcation Process

2015 2016

January February March April May June July August September October November December January February March April

Interchange Justifjcation FHWA Review Interchange Justifjcation FHWA Approval

Meetings IJR Process Analysis LDCA

slide-21
SLIDE 21

PD&E

SR 9/I-95

Study

at PGA Boulevard/ Central Boulevard

Financial Project Number: 413265-1-22-01 ETDM Number: 13748

Public Meetings

  • Project Kick Off (January 29, 2015)
  • Alternatives Workshop (Summer 2015)
  • Public Hearing (Fall 2015)

Newsletters

  • Project Status Update after the

Alternatives Workshop

Comment Cards are available here tonight!

slide-22
SLIDE 22

PD&E

SR 9/I-95

Study

at PGA Boulevard/ Central Boulevard

Financial Project Number: 413265-1-22-01 ETDM Number: 13748

Bing Wang, PE Project Manager Florida Department of Transportation District Four 3400 West Commercial Boulevard Fort Lauderdale, FL 33309 (954) 777-4406 Toll free at (866) 336-8435, ext. 4406 Bing.Wang@dot.state.fm.us

For more information, please call, email or write to:

slide-23
SLIDE 23

PD&E

SR 9/I-95

Study

at PGA Boulevard/ Central Boulevard

Financial Project Number: 413265-1-22-01 ETDM Number: 13748

Public Comments