jack creek park capital improvement project
play

Jack Creek Park Capital Improvement Project Public Information - PowerPoint PPT Presentation

Jack Creek Park Capital Improvement Project Public Information Meeting October 2, 2017 Consultants & Designers, Inc. Integrating Engineering and Environment 7455 New Ridge Road, Suite T Phone: (410) 694-9401 Hanover, Maryland


  1. Jack Creek Park Capital Improvement Project Public Information Meeting October 2, 2017 Consultants & Designers, Inc. “Integrating Engineering and Environment” 7455 New Ridge Road, Suite T Phone: (410) 694-9401 Hanover, Maryland 21076 Fax: (410) 694-9405 1

  2. Introduction Office of County Executive Steven R. Schuh  • Michelle Corkadel, Constituent Services Officer Anne Arundel County Department of Public Works  • Masoud Ghatineh, P.E., Project Manager Design Consultant – BayLand Consultants & Designers, Inc.  • Sepehr Baharlou, P.E., Project Manager Meeting Purpose  • Increase Community Awareness of the Project • Provide Project Overview and Status Update • Respond to Questions 2

  3. Project Goals Protect park from shoreline erosion  Enhance water quality of the Chesapeake Bay  Address County MS4/TMDL permit requirements  Improve public access to the waterway  Support recreational boating dredging program  3

  4. Project Overview Shoreline Protection  • Living shoreline Waterway Access  • Soft (natural) canoe/kayak launch Dredged Material Placement  • Place dry material from Idlewilde DMP Site 4

  5. Jack Creek Park 58 acres 5

  6. Shoreline Protection 1994 Aerial Photo  6

  7. Shoreline Protection 2014 Aerial Photo  7

  8. Shoreline Protection 2014 VS 1994 Aerial Photo  • 6 acres lost due to erosion 8

  9. Shoreline Protection Existing shoreline conditions  Bay Front Jack Creek 9 Along the Point

  10. Shoreline Protection Living Shorelines  • Controls shoreline erosion • Provides a productive, natural shoreline • Strategic placement of plants, stone, sand fill and other structural and organic materials • Implemented through a variety of shoreline protection methods 10

  11. Shoreline Protection Stone structures provide erosion protection  Sand fill provides planting terrace  Marsh plantings provide flood protection and habitat  enhancement 11

  12. Shoreline Protection Protects 1,488 LF of  shoreline Restores 58,811 SF of  tidal marsh Preliminary Concept Plan 12

  13. Waterway Access Parking Launch Area Access Road    Preliminary Concept Plan 13

  14. Waterway Access Launch Area  • Soft (natural) canoe/kayak launch • Natural shoreline 14

  15. Waterway Access Access shoreline through existing trail  Provide ADA compliant surface  Incorporate launch area into living shoreline design  15

  16. Waterway Access Parking  • 20 car parking spots (no trailers) • Permeable grass paving 16

  17. Waterway Access Access Road  • Follow existing gravel road • Gravel surface to the parking area • Trail to water will be permeable gravel (ADA compliant) • Controlled access (gate) will remain 17

  18. Dredged Material Placement Place dry material from Idlewilde DMP Site  18

  19. Dredged Material Placement Idlewilde DMP Site primarily used for South County  recreational dredging projects such as: • Parish Creek (Federal and County channels) • Rockhold Creek Jetty • Broadwater Creek • Church Creek • West River, etc… All materials are tested before dredging  • Metals • Pesticides & PCBs • Priority pollutants volatiles & semi-volatiles • Total of 149 parameters 19

  20. Dredged Material Placement Jack Creek Park placement area  20

  21. Dredged Material Placement Place dry material from Idlewilde DMP Site  • 14,000 cubic yards • 3-acre area • Amend soil with lime and fertilizer • Cover with 6 inches of topsoil • Shape to form natural land features • Re-seed with meadow mix Create small wetlands (rain garden)  Restore to existing use and vegetative cover  21

  22. Dredged Material Placement Truck Route  • Idlewilde Road to Snug Harbor Road – ½ mile 22

  23. Dredged Material Placement Example  During Placement After 23

  24. Schedule Project has been split into two phases  Phase 1: Dredged Material Placement  • Under construction – to be completed in 2 months Phase 2: Living Shoreline & Waterway Access  • Design completed • Federal, State and County permitting underway • To be constructed in 12 to 18 months 24

  25. Discussion 25

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend