isco of tce impacted groundwater in bedrock through an
play

ISCO of TCE-Impacted Groundwater in Bedrock through an Enhanced - PowerPoint PPT Presentation

ISCO of TCE-Impacted Groundwater in Bedrock through an Enhanced Fracture Network Omer J. U Uppa ppal , , Bria ian B Blum, P , P.G., K ., Kyle yle W War arren, , Erica S a Sterzin inar ar, S , Stewar art A Abram ams, s, P P.E.


  1. ISCO of TCE-Impacted Groundwater in Bedrock through an Enhanced Fracture Network Omer J. U Uppa ppal , , Bria ian B Blum, P , P.G., K ., Kyle yle W War arren, , Erica S a Sterzin inar ar, S , Stewar art A Abram ams, s, P P.E.

  2. PRESENTATION OUTLINE • Site Background • COCs, geology/hydrogeology, remedial objective previous ISCO remedial actions/timeline • ISCO Implementation - 2011 • Enhanced Fracture Network • Permanganate Injections • Post-Remediation Results • Next Steps • Technical Impracticability

  3. SITE BACKGROUND • 200-Acre Industrial R&D Facility since the 1940s • Trichloroethene (TCE) plume 200-Acr 200 cre S e Site w e withi hin the identified in the early 1980s New ewar ark B k Basi sin` n` • The plume occupies an area of approximately 3 million square feet. • ISRA triggered in 1996 Chatham, New Jersey U.S.G.S. Topographic Quadrangle

  4. INTERMEDIATE ZONE TCE PLUME SOURCE ZONE “B” SOURCE ZONE “A” G:Data9\1734904\Cadd Data\Dwg\Powerpoint\Langan Env Wkshp\TCE Contours-Intermediate2.dwg

  5. INTERMEDIATE ZONE TCE PLUME SOURCE ZONE “B” This image cannot currently be displayed. SOURCE ZONE “A” G:Data9\1734904\Cadd Data\Dwg\Powerpoint\Langan Env Wkshp\TCE Contours-Int Oct 2003.dwg

  6. SITE GEOLOGY • Four stratigraphic units • Glacial Till • Saprolite Columnar Basalt – Target Formation • • Feltville Formation • Vertical faults and columnar nature of joints likely facilitated vertical migration of contaminants. • Poorly connected fractures form a complex network with low hydraulic connectivity.

  7. SITE CONCEPTUAL MODEL

  8. PREVIOUS REMEDIAL ACTIVITIES INTERMEDIATE ZONE TCE PLUME • DNAPL Source Zone Pilot Tests • Implementation of SVE Pilot Test – 2003 • Implementation of ISCO Pilot Test – 2003 • Blast fracture trenches NOVEMBER 2005 installation – 2006 • 51,024 gallons (31,320 lbs.) 2.5% Potassium Permanganate & 10% Sodium Permanganate solution injected from 2003 to 2009 JANUARY 2008

  9. REMEDIAL ACTIVITIES INTERMEDIATE ZONE TCE PLUME • 9 Blast fracture trenches totaling approximately 21,400 linear feet were installed onsite to facilitate chemical oxidant injections. • 327 blast and injection boreholes JANUARY 2008 SEPTEMBER 2011

  10. TRENCH CROSS SECTION KMnO 4 /NaMnO 4

  11. TRENCH LAYOUT

  12. ISCO INJECTION - 2011 INTERMEDIATE ZONE TCE PLUME • Additional Injections October through November 2011 • The objective was to mitigate the residual “source” of TCE groundwater plume with concentrations greater than 1,000 ppb. SEPTEMBER 2011

  13. ISCO INJECTION - 2011 • 43,200 gallons (9,151 lbs.) 2.5% Potassium Permanganate solution injected into 32 intermediate injection wells and 8 deep injection wells • Hydraulic fracturing • Injection pressures were up to 100 PSI.

  14. ISCO INJECTION - 2011 • Techniques used to facilitate oxidant delivery • Specially designed oxidant distribution manifolds • High pressure wellhead assemblies • Overnight gravity feed injection scheme

  15. BEDROCK INJECTION STRATEGY • Six deep injection wells and 1 Intermediate injection well were hydro-fractured to facilitate chemical oxidant injections. • Overnight gravity feed to facilitate improved injection rates. • The project scope was finished several weeks ahead of schedule and under budget due to these aggressive injection strategies .

  16. HYDRAULIC FRACTURING OVERBURDEN OVERBURDEN WEATHERED BEDROCK WEATHERED BEDROCK BASALT BASALT • Fracturing of rock by a pressurized liquid • Increases connectivity of aquifer and well yield Performed by Northeast Water Production, Inc. • • Direct hydraulic connection was observed at several injection wells, as a function of water level fluctuations, water table mounding in well casings, and limited daylighting (surfacing) following hydro-fracturing.

  17. ISCO ACTIVITIES TOTAL OF ALL ISCO ACTIVITIES Potassium Sodium 10% Modified Permanganate Permanganate Fenton's Reagent (lbs.) (KMnO 4 equiv. lbs.) 1 (gallons) Pilot Test 4,320 -- -- October 2003 to December 2003 Interim Remedial Measure 5,870 18,480 1,270 June 2006 to November 2007 DNAPL Entry Zone Oxidant Placement 1,600 200 -- October 2007 Supplemental Injections 850 -- -- October to November 2009 Additional Injections 9,150 -- -- October to November 2011 Totals 21,790 18,680 1,270 GRAND TOTAL 40,470 pounds

  18. REMEDIAL ACTION RESULTS INTERMEDIATE ZONE

  19. REMEDIAL ACTION RESULTS DEEP 1 ZONE

  20. REMEDIAL ACTION RESULTS

  21. REMEDIAL ACTION RESULTS • Reduction in size of groundwater plume • 71% reduction in intermediate bedrock zone • 21% reduction in deep 1 bedrock zone • Reduction in average TCE concentrations by 88% • Elimination of DNAPL Source Zones • Remaining plume TCE concentrations are expected to decrease over time

  22. TECHNICAL IMPRACTABILITY WAIVER • Groundwater contamination depth extends up to 585 feet bgs. • Fracture diameter, spacing, orientation, vertical extent, and connectivity within and between formations cannot be accurately determined. • Dissolved TCE contamination has diffused into interstitial spaces, dead-end fractures and solution voids along contaminated fracture flow paths. • Approximately 1.6 million square feet of the plume underlies a developed residential area. • Limitations of subsurface remediation technologies

  23. ONGOING ACTIVITIES • Polishing Injection – August 2014 • Injected 2,711 gallons of 5% sodium permanganate • 16 IW’s • Two rounds of post-injection sampling • Concentrations up to 30,000 ppb remaining in limited areas approximately 100 feet into the bedrock

  24. ONGOING ACTIVITIES… • Planned Polishing Injection • Scheduled for October 2014 • Injection of 8,650 gallons of 5% sodium permanganate • 8 converted MW’s and 21 IW’s • Gravity feed injection • Post-injection sampling

  25. VIDEO

  26. QUESTIONS?

  27. THANK YOU

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend