PILOT TESTING AND FULL-SCALE ISCO REMEDY DESIGN FOR DEEP BEDROCK - - PowerPoint PPT Presentation

pilot testing and full scale
SMART_READER_LITE
LIVE PREVIEW

PILOT TESTING AND FULL-SCALE ISCO REMEDY DESIGN FOR DEEP BEDROCK - - PowerPoint PPT Presentation

PILOT TESTING AND FULL-SCALE ISCO REMEDY DESIGN FOR DEEP BEDROCK AQUIFER Second Annual RE 3 Conference January 27-29, 2014, Philadelphia, PA Presented By: Omer Uppal, Brian Blum, C.P.G., LSRP, Stewart Abrams, P.E., Erica Sterzinar, Annie Lee,


slide-1
SLIDE 1

PILOT TESTING AND FULL-SCALE ISCO REMEDY DESIGN FOR DEEP BEDROCK AQUIFER

Second Annual RE3 Conference January 27-29, 2014, Philadelphia, PA Presented By: Omer Uppal, Brian Blum, C.P.G., LSRP, Stewart Abrams, P.E., Erica Sterzinar, Annie Lee, and Matthew Ambrusch

slide-2
SLIDE 2

PRESENTATION OUTLINE

  • Site Background
  • Remedial Approach
  • Phase I Pilot Test
  • Injection Implementation
  • Testing Results
  • Phase II Pilot Test
  • Hydraulic Fracturing
  • Injection Implementation
  • Testing Results Synopsis
  • Conclusions
  • Proposed Full-Scale ISCO Remedy Design
slide-3
SLIDE 3

SITE BACKGROUND

  • 98 Acre Former

Industrial R&D Facility

  • Trichloroethene (TCE)

impacts in soil and groundwater

  • Groundwater

concentrations of TCE up to 59,000 ppb (PIW-1B, Nov 2011)

  • Bulk of TCE impacts in

the intermediate bedrock zone

  • 155 tons of source area

soil removed in 2006

Extent of TCE Plume (1 ppb)

Groundwater Flow Direction

slide-4
SLIDE 4
  • Unstratified Glacial Deposits
  • Bedrock (Diorite)

SITE GEOLOGY

Photographer: Siim Sepp, 2005, Source: Wikipedia Diorite fragments from well drilling

slide-5
SLIDE 5

REMEDIAL APPROACH

Why Potassium Permanganate?

  • Bedrock expected to have low SOD

(0.1-0.65 g/kg), enabling chemical

  • xidation to be more cost effective
  • Known to be effective for removal of

chlorinated ethenes

  • Relatively short remedial timeframe
  • MnO4
  • Relatively long subsurface

half-life (months to years)

2KMnO4 + C2HCl3  2CO2 + 2MnO2 + 3Cl- + H+ + 2K+

Permanganate MnO4

  • + 4H+ + 3e- → MnO2(s) + 2H2O

E° = 1.70 V

slide-6
SLIDE 6

PHASE I ISCO PILOT TEST

3 Injection Wells:

  • Shallow bedrock
  • Intermediate bedrock
  • deep bedrock
slide-7
SLIDE 7

FIELD IMPLEMENTATION

Automated Portable Bulk Feed System (Vironex)

slide-8
SLIDE 8

INJECTION VOLUMES

* 97% of solution injected into the deep bedrock zone

slide-9
SLIDE 9

INJECTION SUMMARY

  • 6,081 gallons of 2.5% potassium permanganate
  • 1,260 lbs of oxidant
  • Three day operation
slide-10
SLIDE 10

INJECTION OBSERVATIONS

  • Shallow and Intermediate

Bedrock: No measureable flow at injection pressures up to 100 psi

  • Deep Bedrock: Able to inject at

flow rates ranging from 5 to 22 gpm at a pressure up to 60 psi

slide-11
SLIDE 11

RADIUS OF INFLUENCE

Color (Permanganate = Purple)

  • Observed pink water at MW-12C

Groundwater Mounding

  • Observed groundwater mounding at MW-12C, MW-

16B, MW-17B and MW-12D. *Radius of influence for the deep zone is at least 25 feet

slide-12
SLIDE 12

PHASE I TESTING RESULTS

Analytical Results:

  • 99% reduction in TCE at PIW-1C, where the majority
  • f the solution was injected
  • 62% reduction in TCE at MW-12C, the directly

downgradient deep monitoring well

slide-13
SLIDE 13

PHASE I TESTING RESULTS

Geochemical Parameters:

ORP pH

slide-14
SLIDE 14

PHASE I TESTING RESULTS

  • ISCO is a feasible remedial

technology for the site.

  • Concentrations did not

decrease significantly due to the inability to inject in the intermediate bedrock zone.

  • Hydraulic fracturing needed

to achieve reasonable injection rates in the intermediate bedrock zone (Phase II)

slide-15
SLIDE 15

PHASE II ISCO PILOT TEST

Objectives:

  • Obtain injection flow-pressure relationships for full-

scale remedial design

  • Evaluate strategies to increase chemical distribution
  • Evaluate effectiveness of hydraulic fracturing to

facilitate injection in the intermediate bedrock zone

slide-16
SLIDE 16

FIELD IMPLEMENTATION

Methodology and Operation:

  • Installed an additional

intermediate injection well (PIW- 2B)

  • Hydro-fractured PIW-2B
  • Injected 2,000 gallons of 2.5%

KMnO4 (452 lbs) in PIW-2B

slide-17
SLIDE 17

HYDRAULIC FRACTURING

  • Fracturing of rock by a pressurized liquid
  • Increases connectivity of aquifer and well yield
  • Performed at PIW-2B at 100-150 bgs, where highest TCE concentrations observed,

by Northeast Water Production, Inc.

  • Direct hydraulic connection was observed, as a function of water level fluctuations,

between PIW-2B and PIW-1C following hydro-fracturing.

OVERBURDEN OVERBURDEN WEATHERED BEDROCK WEATHERED BEDROCK DIORITE DIORITE

slide-18
SLIDE 18

INJECTION OBSERVATIONS

  • Hydraulic fracturing can achieve flow rates of up to 15

gpm at pressures less than 50 psi.

  • Hydraulic influence was observed at distances up to

125 feet during injection.

  • Groundwater daylighting was observed at PIW-1C.

Visual evidence of permanganate solution in PIW-1A

slide-19
SLIDE 19

PHASE II TESTING RESULTS

  • Oxidant distribution

at distances up to 125 feet downgradient

  • Oxidant was

present at several wells during the post injection sampling round

  • No indication of

rebound at PIW-1B

Notes: ‒

  • - = Sample not collected

‒ Sampled via passive diffusion bag (PDB) samplers ‒ NJDEP GWQS for TCE = 1 ppb

slide-20
SLIDE 20

PHASE II TESTING RESULTS

  • ISCO is feasible for the intermediate

bedrock zone.

  • Hydro-fracturing can significantly

enhance oxidant injection rates and distribution in the subsurface.

  • A larger scale injection well network

will be more effective in distributing

  • xidant and reducing TCE

concentrations.

slide-21
SLIDE 21

FULL-SCALE ISCO REMEDY DESIGN

Remedial Strategy:

  • Installation of six

additional intermediate bedrock zone injection wells, one extraction well

  • Hydraulic fracturing of

select injection wells

  • ISCO with NaMnO4
  • Groundwater extraction at select monitoring wells along

the downgradient site boundary while injecting oxidant “Push-Pull ISCO Approach”

slide-22
SLIDE 22

PUMP/WELL YIELD TESTING

Performed in April 2013 at seven monitoring wells to verify achievable extraction rates that can be sustained during ISCO

  • injection. Tests Performed:
  • 1. Specific capacity (step-drawdown) aquifer pumping

tests

  • Flow rates at individual wells ranged from 0.15 to 1.5 gpm
  • 2. Constant-rate aquifer pumping test
  • Conducted at seven wells simultaneously at 5 gpm (combined

pumping flow rate)

slide-23
SLIDE 23

PUMP/WELL YIELD TESTING RESULTS

slide-24
SLIDE 24
  • Total mass of 40%

NaMnO4 = 61,100 lbs

  • Target NaMnO4 injection

solution concentration = 7.5% to 10%

  • Total injection volume =

27,400 to 37,200 gallons

  • Design injection rate = 10

gpm (over 6 hours/day)

  • Design extraction rate = 3

gpm (over 8 hours/day) Implementation Planned for Summer 2014

FULL-SCALE ISCO DESIGN

slide-25
SLIDE 25

FULL-SCALE ISCO DESIGN

slide-26
SLIDE 26

ISCO EQUIPMENT AND MANIFOLD LAYOUT

slide-27
SLIDE 27

Source: Google Maps

QUESTIONS?