SLIDE 1 9/17/2015 1
Stakeholder Advisory Committee Meeting September 3, 2015
Environmental Assessment Updates & Belfountain Concept Plans
Introductions
SLIDE 2 9/17/2015 2
Agenda
- Belfountain Dam and Headpond Class Environmental
Assessment Update
- Belfountain Complex Concept Plans
– Themes – Phase I – Phase II
Environmental Assessment Belfountain dam & headpond
SLIDE 3 9/17/2015 3
Review
- Class Environmental Assessment Process, Purpose and
Approach
- Objectives and Evaluation Criteria
- Evaluation Process
- Evaluation Alternatives
- Mitigation Measures & Ideas
Initiate Class EA Are Impacts Acceptable? Prepare ESR Evaluate & Select Alt. Inventory Prepare Baseline Inventory Analysis Conduct Impact Analysis Can All Environmental Impacts be Avoided? Establish CLC Prepare Project Plan Initiate Class EA Prepare and file notice All Concerns Addressed? Project Approval Filing Publish Notice of Filing Prepare Individual Environmental Assessment Minister of Environment Reviews Part II Order Request Yes No Uncertain No Request Denied
SLIDE 4 9/17/2015 4
Class EA - Objectives
- 1. Maintain a Fisheries Barrier between upstream Brook Trout
and downstream non-native and invasive species
- 2. Reduce/minimize risk to visitors, staff, affected property and
downstream dams
- 3. Maintain or improve the visitor experience
- 4. Conserve and enhance cultural heritage attributes
Class EA - Objectives
- 5. Promote natural stream function
- 6. Strive for long-term sustainability including economic viability
- 7. Conserve and enhance natural heritage attributes
SLIDE 5 9/17/2015 5
Baseline Inventory Report
- Cultural Heritage Assessment and Stage 1 Archaeological
Report
- Topographic Survey
- Stream Morphology Study (physical properties of the WCR)
- Sediment Quality & Quantity Analysis
- Structural Analysis of Dam
- Geotechnical Study of Retaining Wall
Cultural Heritage Assessment
- Cultural Heritage Landscape
- Mack Park and Willoughby Industrial Heritage Site are
registered archaeological sites
- Importance of both the dam and the headpond
- If the features are altered, thorough documentation must take
place
- New interventions must be visually and physically compatible
SLIDE 6 9/17/2015 6
Sediment Analysis
- Estimated sediment volume is 2500m3
- Sediment is intermittent layers of silt, fine sand and organic
matter
- Quality does not pose implications for disposal or remediation
(remediation and use could take place onsite)
- Quality does not pose threat to downstream transport
Stream Morphology
- Change in geology at Dam (bedrock to shale) – as such
general downstream characteristics are not only a result of the dam (but also of the geology)
- Channel widening is major geomorphic process
- Headpond associated with accumulation of sediment and
- verwidening of upstream section
- Lack of fine sediments located downstream could be attributed
to high velocity flows (absence of dam may not improve downstream sediment quality)
SLIDE 7 9/17/2015 7
Ecology
- High quality woodland and valleyland environments
- Several Species at Risk (terrestrial and aquatic) in the area
(measures need to be taken if any construction is required)
- Pond has limited value to wildlife and is warming the water
throughout the reach
Structural Analysis of Dam
- Overall, dam structure is in good condition but does not meet
current safety factors – mitigation will be required if the dam remains
- North retaining wall is unstable during flood or flood-earthquake
conditions and will require mitigation if dam remains
SLIDE 8 9/17/2015 8
Next Steps
– Review of Purpose and Process – Review baseline information and objectives – Opportunity to provide comment
- Evaluation of all alternatives and recommendation for preferred
alternative in November
Belfountain Complex Management Plan
SLIDE 9
9/17/2015 9
Process Review
Background Report Strategic Directions Report (Phase I: Directions) Strategic Directions Report (Phase II: Recommendations) Strategic Directions Report (Phase III: Decisions) Final Management Plan Advisory Committees
Themes
SLIDE 10 9/17/2015 10
Main Themes
- Parking & Traffic
- Capacity
- Working with our Partners
- Aesthetics
Parking & Traffic
- Traffic congestion during the Fall Colours Season
- Parking within the community and walking to BCA
- Connectivity between the Hamlet and BCA
SLIDE 11 9/17/2015 11
Parking & Traffic – Proposed Policies
- Increased parking capacity on-site
- Off-site parking with shuttle service during fall colours
- Exploring walking connections
Capacity – Proposed Policies
- Exploring programs to promote weekday visitation, and off-
peak visitation
- Limit picnic reservation sizes; promote other conservation
areas
- Require reservations for larger group picnics
- Ongoing environmental and property monitoring
SLIDE 12 9/17/2015 12
Capacity - Events
- Size of events will be limited
- Event season will likely be limited
- Length of events will be limited
Working with our Partners
- Working with the Region and Town to address traffic
congestion issues
- Several solutions are possible (parking, signage, travel routes,
etc.): 2015 focus on data collection related to local tourism
- Working with agency partners to develop plans and strategies
cohesively (Tourism, Active Transportation, etc.)
SLIDE 13 9/17/2015 13
Aesthetics
- Gardens (demonstration, native, formal)
- Signage (subtle, discrete, minimal)
- Interpretive Methods (Online, Audio, Tours)
- Ancillary Features (benches, picnic tables, rest areas)
Concept Plans
SLIDE 14 9/17/2015 14
Concept Plan Development
- Consultant hired to create concept plans: Brook McIlroy
– Comments consolidated and forwarded – Initial meetings and site visits – Development of concepts and architectural sketches
Project Area #3: Forecourt
- Entry Experience
- Pedestrian access
- Accessible access & drop-off
- Def ine picnic area
- Formalize water access
- Naturalization
SLIDE 15
9/17/2015 15
Option 1
SLIDE 16
9/17/2015 16
Option 2 Option 3
SLIDE 17 9/17/2015 17
PRECEDENTS Project Area #1: Parking Lot and Visitor Centre
- Visitor centre as g ateway
- Park ing capacity
- Saf ety
- Optimize Operations
- Views
- Def ine Picnic Areas
- Restore Slope
SLIDE 18
9/17/2015 18
Option 1
SLIDE 19
9/17/2015 19
Option 2 Option 3
SLIDE 20 9/17/2015 20
PRECEDENTS Project Area #2: Hillside Garden
- Restore Slope
- Views
- Naturalization
- Def ine Picnic Areas
SLIDE 21
9/17/2015 21
Option 1
SLIDE 22
9/17/2015 22
Option 2 Option 3
SLIDE 23 9/17/2015 23
Project Area #4: Bridgehead & Portico
- Prominent Gateway Site
- Visual Connection
- Interpretive Node
- Enhance Pumphouse
- Activate River Crossing
This area will not be presented during the first consultation – the preliminary concepts are awaiting the outcome of the Class EA.
SLIDE 24
9/17/2015 24
Option 2 Option 3
SLIDE 25
9/17/2015 25
SLIDE 26 9/17/2015 26
Project Area #5: Heritage Gardens
- “Follies”
- Improve natural heritage f eatures
- Return to the swimming pool
- Enhance views
- Def ine circulation
- Improve Boardwalk
- Address Railing s
T h is T h is T h is T h is a r ea will n o t b e p resented d uring t he f irst a r ea will n o t b e p resented d uring t he f irst a r ea will n o t b e p resented d uring t he f irst a r ea will n o t b e p resented d uring t he f irst c onsultation c onsultation c onsultation c onsultation – – – – t he p reliminary c oncepts a re t he p reliminary c oncepts a re t he p reliminary c oncepts a re t he p reliminary c oncepts a re a waiting t h e o utcome o f t he Class EA. a waiting t h e o utcome o f t he Class EA. a waiting t h e o utcome o f t he Class EA. a waiting t h e o utcome o f t he Class EA.
SLIDE 27
9/17/2015 27
Option 1
SLIDE 28
9/17/2015 28
Option 2 Option 3
SLIDE 29 9/17/2015 29
PRECEDENTS Trails & Restoration (Project Areas 6,7)
- Trail plan is in development
– Pond Loop trail is awaiting outcome of the Class EA – Minor trail improvements (re-routes, boardwalks) proposed
- Restoration Plan is underway
– Planting plans for areas identified in Strategic Directions Report I
SLIDE 30 9/17/2015 30
Feedback & Consultation
Feedback on Concept Plans
- Online survey to scope and record comments
- Broad comments or stakeholder positions are welcome
SLIDE 31 9/17/2015 31
Consultation Schedule
- September 22nd 2015: Public Information Centre for the
Environmental Assessment and Management Plan – Includes a presentation and opportunity to talk with staff and consultants working on the project – Opportunity to review poster boards and provide input – 6pm – 9pm at the Caledon Ski Club
Consultation Schedule
- September 26th, 27th,October 2nd and 3rd: Outreach and
Consultation in the Conservation Area – Visitors to the conservation area and members of the community will be invited to discuss both projects with CVC staff – Opportunity to provide input – 11am – 4pm in Belfountain Conservation Area
SLIDE 32
9/17/2015 32
Questions