For Muswell Hill Primary School Phase 2 Conditions Works Introductions ! 1. Introductions Presented by: Senior Contracts Manager John Wood Conor Cruse-Bowles Project Surveyor 1 1. Introductions For Our Aim and Objective: Is to deliver


slide-1
SLIDE 1

For Muswell Hill Primary School

Phase 2 Conditions Works

Introductions!

slide-2
SLIDE 2

Presented by: John Wood – Senior Contracts Manager Conor Cruse-Bowles – Project Surveyor

  • 1. Introductions

1

slide-3
SLIDE 3
  • 1. Introductions

Our Aim and Objective: Is to deliver safely and securely a high quality product and to minimise any inconvenience for the pupils and staff of Muswell Hill Primary School.

2

For

slide-4
SLIDE 4

The Phase 2 Condition Works Contract – in a Nutshell: Consists of an upgrade of the Mechanical and Electrical services throughout the school, some works to the building internally, and some external structural works.

  • 1. Introductions

3

slide-5
SLIDE 5
  • 1. Introductions

4

 So who are we? Diamond Build PLC, founded in 1977  Approaching £20m Average Annual Turnover  A Chartered Building Company  Quality Assured to OHSAS 18001 and CHAS (for Health and Safety), ISO 9001 (for Quality Management), ISO 14001 (for Environmental Management) and FIRAS (for Fire Safety Installations).

slide-6
SLIDE 6
  • 1. Introductions

5

 Wide and Varied Education Project Experience  And Numerous Very Satisfied Clients, including:

Mulberry Primary School, Haringey Riverside School Haringey Welbourne Primary School, Haringey

slide-7
SLIDE 7
  • 1. Our Project Team

6

slide-8
SLIDE 8
  • 2. Works Approach

7

Overview of Site set Up – will include:  Secure compound  Heras anti-climb fencing, gates  Office and staff welfare Portacabins  Secure, locked Containers

slide-9
SLIDE 9
  • 2. Works Approach

8

Overview of Site set Up

slide-10
SLIDE 10
  • 2. Works Approach

9

Health and Safety and Security  Secure Access Routes, Agreed Emergency Fire Escape  Traffic Marshal for Deliveries  All operatives DBS/CRB checked  CSCS accredited workforce, H&S competency and trained  Bespoke Site Rules and Site Induction for all Operatives  Corporate Clothing and Personal Protection Equipment (PPE)

slide-11
SLIDE 11
  • 2. Works Approach

10

Planned areas of work during each stage

slide-12
SLIDE 12
  • 2. Works Approach

11

Minimising Disruption  Maximum use made of School Holidays  Communications with School – daily briefings with School’s key contacts, co-ordinated, flexible, adaptable approach  Noisy Works – to a minimum, convenient times wherever possible  Deliveries – pre-agreed schedule and timeslots (early and late), also avoiding pre-school and after school club activities

slide-13
SLIDE 13

Any Questions? For Muswell Hill Primary School

Phase 2 Conditions Works