Internal Cryogenics & Ullage David Montanari LBNC Review 18-21 - - PowerPoint PPT Presentation

internal cryogenics ullage
SMART_READER_LITE
LIVE PREVIEW

Internal Cryogenics & Ullage David Montanari LBNC Review 18-21 - - PowerPoint PPT Presentation

LBNF Long-Baseline Neutrino Facility Internal Cryogenics & Ullage David Montanari LBNC Review 18-21 February 2018 Thanks to Mark Adamowski (Fermilab). Jean-Baptiste Mayolini (CERN). Aurlien Diaz (CERN). Jack Fowler (Duke


slide-1
SLIDE 1

Long-Baseline Neutrino Facility LBNF

Internal Cryogenics & Ullage

David Montanari LBNC Review 18-21 February 2018

slide-2
SLIDE 2

LBNF

Thanks to

02.20.18 David Montanari | Internal Cryogenics & Ullage 2

  • Mark Adamowski (Fermilab).
  • Jean-Baptiste Mayolini (CERN).
  • Aurélien Diaz (CERN).
  • Jack Fowler (Duke University).
  • Kevin Haaf (Fermilab).
  • Adrien Parchet (CERN).
  • Erik Voirin (Fermilab).
slide-3
SLIDE 3

LBNF

Outline

02.20.18 David Montanari | Internal Cryogenics & Ullage 3

  • Internal Piping.
  • Ullage considerations.
  • Next Steps.
slide-4
SLIDE 4

LBNF

Internal Cryogenics Layout

02.20.18 David Montanari | Internal Cryogenics & Ullage 4

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 a b c d e f g h i k l m n
  • p
q REF.CERN OBSERVATIONS MAT. POS QUA S.ENS/S.ASS DESCRIPTION ENS/ASS ST0899069_02 CAD Document Number 2017-11-03
  • J. Mayolini
1:50
  • LBNF ASSY Internal pipes cryostat
CONTROLLED DRAWN RELEASED APPROVED REPLACES SIZE IND. NOT VALID FOR EXECUTION NON VALABLE POUR EXECUTION QAC CERN SCALE NORMES ISO ISO STANDARDS PROJECTION DESSIN, RUGOSITE, TOLERANCES SELON DRAWING, RUGOSITY, TOLERANCES ACCORDING TO GENEVE CERN Ce dessin ne peut etre utilise a des fins commerciales sans autorisation ecrite This drawing may not be used for commercial purposes without written authorisation ORGANISATION EUROPEENNE POUR LA RECHERCHE NUCLEAIRE EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH 1 1 14000

B C D

920 1600 2960 4320 6020 7380 9080 10780 12140 13500 14180 15100 580 1120 1590 61000 62000 5417 6932 8619

E F Isometric view 1:200 B 1:10

70 65.55 180 580

C 1:25

340 340 410 370 370 340 410 340

D 1:25

400 340 340 410

E 1:25

410 340 400 340

F 1:25

Elevation from floor (axis): 180 mm (may grow) GAr Purge: 2 in NPS (DN50) LAr Distribution: 3 in NPS (DN80)

slide-5
SLIDE 5

LBNF

Iso View

02.20.18 David Montanari | Internal Cryogenics & Ullage 5

slide-6
SLIDE 6

LBNF

Internal Cryogenics occupied space (current) – Top & Side

02.20.18 David Montanari | Internal Cryogenics & Ullage 6

Top clearance:

  • 560 mm (top of DDS beam to membrane)

Side clearance:

  • 546 mm (pipe to detector)
slide-7
SLIDE 7

LBNF

Internal Cryogenics occupied space (current) – Bottom

02.20.18 David Montanari | Internal Cryogenics & Ullage 7

Bottom clearance:

  • 244 mm (CL pipe to cold electronics)
  • 425 mm (cold electronics to membrane)
  • 180 mm (CL pipe to membrane)
slide-8
SLIDE 8

LBNF

Internal Cryogenics Considerations

02.20.18 David Montanari | Internal Cryogenics & Ullage 8

  • Horizontal and vertical runs are too long for supports ProtoDUNE-style.
  • Horizontal ones would need to jump from one “square” to the other

during cooldown and warmup.

  • Vertical ones need additional features to compensate the thrust force.
  • Kevin H working on options to address these:
  • May (or may not) require more vertical clearance under the detector.
  • May (or may not) use some of the current 560 mm clearance. Is it ok?
  • Pipes not directly under APAs/CPAs, but what about field cage? Can

we get closer to it?

  • Will update the 3D model of the internal cryogenics as needed.
slide-9
SLIDE 9

LBNF

Ullage considerations (at Operating Pressure)

02.20.18 David Montanari | Internal Cryogenics & Ullage 9

  • Current ullage is 5.7%: 800 mm (LAr level 13.2 m).
  • We already agreed to lower it to 5%, which is 700 mm (LAr level 13.3 m).
  • Value is comfortable for operations and meet the minimum safety requirements of

EN 14620. Can we lower it even further?

  • Requirements:
  • Good engineering practice from EN 14620 requires a minimum ullage (freeboard)
  • ver the full pressure range.
  • Need to satisfy the seismic sloshing wave protection.
  • Need stability of operations.
  • We would prefer to keep at least 4% ullage: 560 mm (LAr level 13.44 m).
  • With 700 mm ullage the LAr amount increases by 0.72% and the cost by $150k

(each cryostat).

  • With 550 mm ullage the LAr amount increases by 1.76% and the cost by $365k

(each cryostat).

  • If the pressure decreases (from 130 mBarg), the LAr level decreases, down 40 mm

at atmospheric pressure.

slide-10
SLIDE 10

LBNF

Next Steps

02.20.18 David Montanari | Internal Cryogenics & Ullage 10

  • Continue to work on the thermal compensation of the internal

cryo to verify vertical/horizontal clearance between the pipes and the detector.

  • Identify the correct vertical position of the detector.
  • Update 3D models, drawings, etc. as needed.
slide-11
SLIDE 11

LBNF

Thanks

02.20.18 David Montanari | Internal Cryogenics & Ullage 11

slide-12
SLIDE 12

LBNF

Backup slides

02.20.18 David Montanari | Internal Cryogenics & Ullage 12

slide-13
SLIDE 13

LBNF

Details calcs

02.20.18 David Montanari | Internal Cryogenics & Ullage 13

Current situation (Feb 16, 2018) Prepared by: David Montanari Date: 16-Feb-18 Revision: 1 17,165,040 Kg LAr each cryostat (from LN2 Refrigeration table) 20,605,500 $ LAr First cryostat (from schedule) LAr level LAr Increase Cost Increase LAr Increase Cost Increase % LAr Increase Cost Increase m m % mBarg m % % USD m % % USD m % USD 13.163 0.837 5.98% Fill P 50 0.742 0.523 0.602 13.204 0.796 5.69% Operating P 130 0.700 5% 0.72% 148,638 $ 0.480 3% 2.34% 481,196 $ 0.560 4% 1.76% 361,730 $ 13.136 0.864 6.17% P_Atm 0.769 0.55 s Input values (h-ullage_2)*rho_2=(h-ullage_1)*rho_1 Ullage Option 1 Ullage Option 3 Ullage Option 2 Pressure Ullage Ullage Ullage Ullage

slide-14
SLIDE 14

LBNF

Details calcs (from Mark A)

02.20.18 David Montanari | Internal Cryogenics & Ullage 14 LBNF LAr Expansion Analysis to Determine Minimum Ullage

Temp. LAr density LAr depth change in Ullage Ullage

(MPa-g) MPa-abs (K)

kg/m3 (m) % (mm)

0.0000 0.10066 87.2 1395.8 13.450

  • 5.0%

550

Min Ullage

0.0050 0.10566 87.7 1392.9 13.477 0.0% 523

Fill Pressure

0.0100 0.11066 88.1 1390.2 13.504 4.8% 496 0.0130 0.11366 88.4 1388.6 13.519 7.7% 481

Operating Pressure

0.0150 0.11566 88.6 1387.5 13.530 9.6% 470 0.0200 0.12066 89.0 1384.9 13.555 14.1% 445 0.0250 0.12566 89.4 1382.4 13.579 18.6% 421 0.0300 0.13066 89.8 1380.0 13.603 23.0% 397 0.0350 0.13566 90.2 1377.6 13.627 27.2% 373

Design Pressure

0.0385 0.13916 90.4 1376.0 13.643 30.2% 357

Max Over Pressure - all relief scenarios

Prepared by: Mark Adamowski rev: 2018-02-14

Pressure

Good engineering practice from EN-14620 requires a minimum of 300 mm of ullage (freeboard) space. This 300 mm can be counted as being part of the ullage space needed for seismic sloshing wave protection. This 300 mm satisfies the seismic sloshing wave protection needed for LBNF. Ref: "Structural assessment of the LBNF warm structure", presented at the LBNF Cryostat design review, August 21-22, 2017, EDMS: 183257. This table starts with the liquid fill at 50 mbarg operating pressure and looks at the LAr expansion over the cryostat

  • perating pressure range and calculates the change in ullage space. The fill LAr was set to a value that provides the 300

mm design safety cushion with an instrument error allowance (0.5% of range, 70 mm) over the whole operating pressure range. Above the design pressure the ullage could be below 300 mm due to instrument error. Since this occurs

  • utside of the dessign pressure range , it is not a concern.

Based on this analysis the minimum design ullage is 550 mm and the target LAr fill level at 50 mbarg is 13.478 m. Smaller ullage space is only allowed due to LAr expansion as indicated in the above table.

slide-15
SLIDE 15

LBNF

CFD update

02.20.18 David Montanari | Internal Cryogenics & Ullage 15

  • Several CFD simulations have been performed to identify the optimal

location of the LAr return pipes in the cryostat. Goal was to identify the configuration that optimizes the uniformity of the LAr inside the cryostat.

  • Highlights:
  • LAr pumps not needed at each end of cryostat. One side only enough.
  • LAr suction line can be at any height (currently as low as possible to start

the purification of the bulk of the LAr as soon as the NPSH is reached and the removal of the LAr at the end of the life of the experiment.

  • Can use two LAr return pipes, as long as the LAr is distributed through

several points along the length of the cryostat (from 24 to 124 points).

  • Must support 1-4 LAr circulation pumps running.
slide-16
SLIDE 16

LBNF 02.20.18 David Montanari | Internal Cryogenics & Ullage 16

Results Comparison (Arbitrary normalized value)

10/22/17 Erik Voirin | DUNE Impurity Homogeneity 18

Compare to Discharge Flow at only 1 end: 35x higher Standard Deviation

Discharge Flow Location # of Pumps Circulating Minimum Normalized Impurities Maximum Normalized Impurities Range of Impurities (Max-Min) STD DEV Normalized Impurities Ave Velocity Minimum Lifetime Maximum Lifetime Lifetime Range Suction Lifetime Average Lifetime [ - ] [ - ] [ % ] [ % ] [ mm/s ] [ us ] [ us ] [ us ] [ us ] [ us ] 24 points 1 0.98615 1.0097 2.4% 0.14% 6.77413 2974 3045 71 3000 3003 124 points 1 0.993725 1.0084 1.5% 0.12% 6.73984 2976 3020 44 3000 3001 Discharge Flow Location # of Pumps Circulating Minimum Normalized Impurities Maximum Normalized Impurities Range of Impurities (Max-Min) STD DEV Normalized Impurities Ave Velocity Minimum Lifetime Maximum Lifetime Lifetime Range Suction Lifetime Average Lifetime [ - ] [ - ] [ % ] [ % ] [ mm/s ] [ us ] [ us ] [ us ] [ us ] [ us ] Far End 1 0.9356 1.0574 12.2% 4.24% 7.6674 2967 3354 386 3000 3138