crab cavities sps cryogenics progress and requirements
play

Crab Cavities SPS cryogenics progress and requirements Fermilab - PowerPoint PPT Presentation

Crab Cavities SPS cryogenics progress and requirements Fermilab visit at CERN 02 August 2013 Krzysztof Brodzinski (on behalf of CERN cryogenic team) 1 Contents Cryogenics for Crab Cavities project technical aspects and status


  1. Crab Cavities SPS cryogenics – progress and requirements Fermilab visit at CERN 02 August 2013 Krzysztof Brodzinski (on behalf of CERN cryogenic team) 1

  2. Contents • Cryogenics for Crab Cavities project – technical aspects and status • Circuits • Heat load • Capacity limitations with existing infrastructure + possible solutions • BA4 work progress • 2 K pumping units test • Available space – integration brief • Cryogenics for SPS cryostat design • Process and instrumentation • Safety devices • Pumping collector sizing • Superfluid helium layer • Conclusions 2 K. Brodzinski - Fermilab visit_2013.08.02

  3. Cryogenic circuits Regarding 2 K refrigeration Additional He source Buffer tank R EH Service module TT LN2 JT CC cryostat Screen PT LT Coupler intercept CTW CC x 2 CTW black – > existing 4.5 K Screen red – > to be constructed 2 K EH TT 3 K. Brodzinski - Fermilab visit_2013.08.02

  4. Heat loads and TCF20 capacity The below values are calculated/estimated – no exact calculation is available yet depending on design Equipment Heat load Source of capacity cryostat Static HL @ 2K ~ 8-10W TCF20 -> 0.4-0.5 g/s Dynamic @ 2 K ~ 5-10 W TCF20/Buffer tank HL @80 K ~40-60 W LN2 Service module ~2.5 W @ 2K TCF20 -> 0.13 g/s ~30 W @ 80 K LN2 Buffer tank* ~1.5 W @ 4.5 K TCF20 -> 0.08 g/s ~ 19 W@ 80 K LN2 V. Parma and colleagues Transfer lines ~3.4 W @ 4.5 K TCF20 -> 0.17 g/s ~26 W @ 80 K LN2 Flash at 2 K ~20% of liquefaction flow TCF20 -> 0.2 g/s Total net value: 0.98-1.08 g/s Total with 1.5 safety factor: ~ 1.5 g/s 4 K. Brodzinski - Fermilab visit_2013.08.02

  5. TCF20 cold box capacity discussion Static heat load -> 0.98-1.08 *1.5 =~1.5 g/s CERN isentropic equiv. recalculated with measured refrigeration capacity (120 W) CERN isentropic equiv. recalculated with guaranteed refrigeration capacity (85 W) CERN isentropic equiv. recalculated (20 l/h) Liquefaction capacity line [g/s] 0.7 0.85 1.2 0.76 1.56 LEGNARO guaranteed liquefaction capacity (22 l/h) LEGNARO guaranteed liquefaction capacity with LN2 (45 l/h) Conclusions: • Existing TCF20 without LN2 boost is not sufficient to cover requirements (even upgraded as liquefier) • Plan B: LN2 boost to be installed and liquefaction capacity tested • Plan C: install new TCF20 liquefier + install LN2 boost (difficult because of safety and a lot of work – transfer lines to be installed, possible problems with instabilities of LN2 flow – info from G. Passardi) • Plan D: on the surface: Install a 10000 L dewar with link to 200 L buffer as an “emergency boost” Target: The cold box should cover at least the static heat load, the buffer tank dynamic operation of the cavity. 5 K. Brodzinski - Fermilab visit_2013.08.02

  6. Work done in BA4 • Inventory list, GMAO new naming definition list and PID update done by ~15.09.2012 • All SVs re-qualified and installed – done by ~15.09.2012 • Electrical motor and compressor maintenance – done by ~30.09.2012 • Oil separation refurbished (coalescers cartridge replaced, ADS charcoal replaced) – done by ~30.09.2012 • Storage – He tank re-qualified as pressure recipient – done on 12.09.2012 • All other pressure recipients re-qualified – done by ~15.10.2012 • Purging system on compressor station refurbished • Cooling water and air ventilation installations for compressor station – refurbished • Cold box vacuum system revised and partially refurbished • Compressor station and cold box (partially) instrumentation revised • Compressor station new electrical supply system with documentation done and tested by ~15.11.2012 • Control system well advanced (partially ready) • He tightness test done on compressor station • First run of compressor station done by 30.11.2012 – milestone (OK operational, HP@6 bara) • First helium flow through the cold box done on 18.12.2012 – milestone (OK, no leak into the vac) 6 K. Brodzinski - Fermilab visit_2013.08.02

  7. Work done in BA4 At SPS BA4 there is a 4.5 K cryogenic infrastructure used last time about 8 years ago for COLDEX experiment. It is foreseen to test its capacity and upgrade it for 2 K refrigeration – refurbishment is underway Renovated compressor + elec. motor – run test done Revised, labeled and qualified pressure control system / oil removal system Cold box TCF20 New power supply panel for compressor station 2 K pumping groups recovered from AMS SPS LS1 time frames: Open Access : 25/03/13 TCF20 Cold box 7 K. Brodzinski - Fermilab visit_2013.08.02 Close Access : 27/06/14

  8. 2 K pumping units performance test PT TT PSV PT PI HV HV 01 01 01 02 03 02 03 PI 02 FT PI Recuperation line 01 HV 2 stage pumping towards liquifier 04 HV 01 group 2 stage pumping group (Leybold: RUVAG WS2001 and SV630) 2 batteries of He gas bottles PT01: pressure transmitter, Rosemount, 0 … 2000 mbara <200 bar TT01: Pt100 FT: flow transmitter, Brooks, 0 … 1.5 g/s PT02: pressure transmitter, GE, 0 … 100 mbara Both pumps were run to check their capacity – probably 2 pumps will have to be integrated in the tunnel – analysis underway. 8 K. Brodzinski - Fermilab visit_2013.08.02

  9. Cryo integration in SPS Pump heater SM Buffer TCF20 Very tight integration if going behind the beam line (more details in Th. Renaglia presentation). 9 K. Brodzinski - Fermilab visit_2013.08.02

  10. Tentative SPS CC cryogenic schedule Work planned for 2013: - 2 K pumping group to be transported and integrated in the SPS tunnel in Autumn 2013 – AMS groups will be used - Low pressure He recovery heating system to be transported and integrated in the SPS tunnel in Autumn 2013 – probably AMS elements could be adapted - Electrical and control systems for 2 K cryogenics to be done (cables pulling included) – underway - Refurbishment of the cold box 4.5 K – vacuum system and turbine circuits – done - Cold box control system to be completed – done - Cold box instrumentation revision/update to be completed – underway - Cold run of the cold box – in September May 2013 – milestone – almost ready, conditioning done, waiting for cooling water circuit ON - Liquefaction test of 4.5 K cold box (potentially with boost at 80 K stage, if yes, this boosting system is to be developed and bought/constructed), some hardware modifications are required as preparation for this test – to be done by 15.10.2013 – milestone - Refurbishment of the supply/recovery system between BA4 and North Area is to be done or procurement of additional buffer tank to fulfil requirements of helium availability for CC testing – to be analysed and confirmed – spring/autumn 2013 – milestone - LN2 system for cooling of screen circuits to be developed and bought – to be defined - Buffer tank to be designed and bought - 2 K cryogenics: transfer line system to be designed and ordered (installation in 2014) - 2 K cryogenics: Service module to be to be designed and ordered (installation in 2014) Main task for 2013/2014 is the distribution system development and installation 10 K. Brodzinski - Fermilab visit_2013.08.02

  11. Process & instrumentation 1/2 The cryostat will house 2 crab cavities and will be operated at 2 K (saturated helium bath  ~30 mbar). The design should be done in the way to minimize the static heat load at 2 K (important!) It will be equipped with two circuits 2 K and 80 K. The main interface should be provided from the top with 4 main lines (LHe IN, GHe pumping, LN2 80 K IN and 80 K OUT). - Proposed piping should cover nominal operation and transients (cool down and warm up), - Interface to the cryostat: internal pipes welded, external envelope bolted (allowing opening of the jacket by means of sliding it up or down). Power couplers and Cold/Warm Transitions will be intercepted with LN2 at 80 K. cryostat interface thermal screen at ~80 K common pumping collector helium tank CWT crab cavity CWT Power coupler intercept 11 K. Brodzinski - Fermilab visit_2013.08.02

  12. Process & instrumentation 2/2 The cryostat should be equipped with the following instrumentation: • Helium level measurement – each helium tank should be equipped with a level gauge allowing for helium level measurement from the bottom through the phase separator (LT x 2, each gauge should allow for helium level regulation in the phase separator collector), • Pressure measurement on the saturated helium bath is to be provided (PT x 1), • Temperature measurement on each cavity helium tank is to be provided, installed on the bottom of each helium tank (suggested CERNOX type transducer, TT x 2), • Electrical heaters of 50 W are to be installed on each helium tank (EH x 2) • Temperature measurement on 80 K screen line is to be provided (TT x 2 on inlet and outlet) • JT valve and sub-cooling HX are foreseen to be installed out of the cryostat • (instrumentation for 80 K intercept circuits – definition underway) All sub atmospheric instrumentation/safety devices with ambient air interface will have to be equipped with appropriated helium guard. cryostat interface thermal screen at ~80 K common pumping collector TT TT LT LT PT helium tank CWT crab cavity TT TT EH EH CWT Power coupler intercept 12 K. Brodzinski - Fermilab visit_2013.08.02

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend