2015 operations stay treat
play

2015 Operations Stay Treat CHL2 4K Cold Box Modifications SC1 2K - PowerPoint PPT Presentation

2015 Operations Stay Treat CHL2 4K Cold Box Modifications SC1 2K Cold Box CC4 Failure Helium and LN2 Losses Contamination 2015 Operations Stay Treat 1 CHL2 4K Cold Box Modifications New 4K cold box designed and built for 12GeV


  1. 2015 Operations Stay Treat • CHL2 4K Cold Box Modifications • SC1 2K Cold Box CC4 Failure • Helium and LN2 Losses • Contamination 2015 Operations Stay Treat 1

  2. CHL2 4K Cold Box Modifications • New 4K cold box designed and built for 12GeV • Designed for reduced utility consumption compared to CHL1 • 3-4.5MW for CHL2 verses 5-6.5MW for CHL1 • 60 gal/hour CHL2 verses 200 gal/hr for CHL1 • Testing indicated power usage was on estimates • Testing indicated 200 gal/hour or 70% more LN2 than design • Linde proposed repair • Disconnect and abandon large internal heat exchanger • Add new external cold box with new heat exchanger • Hope to recover to original design goal 60 gal/hr ($300K/yr) 2015 Operations Stay Treat 2

  3. CHL2 4K Cold Box Modifications 2015 Operations Stay Treat 3

  4. CHL2 Nitrogen Heat Exchanger • Plan forward • Pressure tests • Leak checks • I&C • Clean up • Cooldown • Testing 2015 Operations Stay Treat 4

  5. SC1 2 Kelvin Cold Box Repair 2015 Operations Stay Treat 5

  6. Typical Cold Compressor 2015 Operations Stay Treat 6

  7. Cold Compressor Bearing Controls • Cold compressors • Multi-axis magnetic bearing • Each cold compressor has a magnetic bearing control cabinet • Each cabinet has UPS for protection during power outages • Electronics monitors speed to determine when required • UPS holds bearings until speed ramps down then turns off • UPS has a test button which is used when system is prepared for operation at the end of an extended down 2015 Operations Stay Treat 7

  8. Power Outage • Site wide power outage • CHL1, CHL2, ESR, and Hall D plants shutdown • Systems were secured and prepared for restart • SC2 brought online first • SC1 pumpdown started two days later • Magnetic bearing cabinet reported normal conditions • Two hours into pumpdown the compressor failed 2015 Operations Stay Treat 8

  9. SC1 CC4 Failure Start of pumpdown Mag Bearing Trip 2015 Operations Stay Treat 9

  10. SC1 CC4 Failure 2015 Operations Stay Treat 10

  11. SC1 CC4 Findings • Backup ball bearing failure • When rotor fell bearing 0 to 35,000 RPM instantly • Inner and outer races shattered • Balls damaged • Shaft scored • Position sensors damaged • Air Liquid and S2M working on estimates • CC4 repair • Balancing spare wheels • List of recommended future spare parts 2015 Operations Stay Treat 3

  12. Post UPS Failure Investigation • Investigation • UPS test function • Applies a high wattage resistor across batteries and measures voltage drop over time • Does not test actual detection and switching functionality • New UPS test designed by JLAB • With compressor at zero speed • Simulate speed input with function generator • Turn off circuit breaker • Time 5 minutes • Turn down speed until UPS turns off • Perform at start of operation and after any power outages 2015 Operations Stay Treat 12

  13. SC1 Repair Using SNS Compressor • Moved our wheel and backplate to the SNS compressor • JLAB modified SNS compressor • LN2 supply and LN2 return connections • Magnetic bearing power and controls feedthroughs (x4) 2015 Operations Stay Treat 4

  14. SC1 CC4 Plan Forward • Estimate about 1 months of work remaining • Pull a vacuum on process piping • Check bearing controls • Test run compressor (balance and bearing control) • Visit from AL/S2M to certify bearings ready • Install vacuum shell and establish vacuum • Clean up system • Utubes and cooldown • Test by pumping down 2015 Operations Stay Treat 14

  15. Helium Losses • Three major losses found and repaired • CHL1 C6 (~110 liquid liters per day) • ESR utility piping (outside) (~110 liquid liters per day) • CHL1 bearing gas (basement of CHL1) (~110 liquid liters per day) 2015 Operations Stay Treat 15

  16. Contamination • Following the power outage we had two episodes of contamination problems • SC1 CC2 froze in place • SC2 primary heat exchanger plugged • Likely causes • Large number of utube operations performed during down • Subatmosperic relief valves leaking 2015 Operations Stay Treat 16

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend