2015 Operations Stay Treat CHL2 4K Cold Box Modifications SC1 2K - - PowerPoint PPT Presentation

2015 operations stay treat
SMART_READER_LITE
LIVE PREVIEW

2015 Operations Stay Treat CHL2 4K Cold Box Modifications SC1 2K - - PowerPoint PPT Presentation

2015 Operations Stay Treat CHL2 4K Cold Box Modifications SC1 2K Cold Box CC4 Failure Helium and LN2 Losses Contamination 2015 Operations Stay Treat 1 CHL2 4K Cold Box Modifications New 4K cold box designed and built for 12GeV


slide-1
SLIDE 1

2015 Operations Stay Treat

  • CHL2 4K Cold Box Modifications
  • SC1 2K Cold Box CC4 Failure
  • Helium and LN2 Losses
  • Contamination

1

2015 Operations Stay Treat

slide-2
SLIDE 2

CHL2 4K Cold Box Modifications

  • New 4K cold box designed and built for 12GeV
  • Designed for reduced utility consumption compared to CHL1
  • 3-4.5MW for CHL2 verses 5-6.5MW for CHL1
  • 60 gal/hour CHL2 verses 200 gal/hr for CHL1
  • Testing indicated power usage was on estimates
  • Testing indicated 200 gal/hour or 70% more LN2 than design
  • Linde proposed repair
  • Disconnect and abandon large internal heat exchanger
  • Add new external cold box with new heat exchanger
  • Hope to recover to original design goal 60 gal/hr ($300K/yr)

2

2015 Operations Stay Treat

slide-3
SLIDE 3

CHL2 4K Cold Box Modifications

3

2015 Operations Stay Treat

slide-4
SLIDE 4

CHL2 Nitrogen Heat Exchanger

4

2015 Operations Stay Treat

  • Plan forward
  • Pressure tests
  • Leak checks
  • I&C
  • Clean up
  • Cooldown
  • Testing
slide-5
SLIDE 5

SC1 2 Kelvin Cold Box Repair

5

2015 Operations Stay Treat

slide-6
SLIDE 6

Typical Cold Compressor

6

2015 Operations Stay Treat

slide-7
SLIDE 7

Cold Compressor Bearing Controls

  • Cold compressors
  • Multi-axis magnetic bearing
  • Each cold compressor has a magnetic bearing control cabinet
  • Each cabinet has UPS for protection during power outages
  • Electronics monitors speed to determine when required

7

2015 Operations Stay Treat

  • UPS holds bearings until speed ramps

down then turns off

  • UPS has a test button which is used

when system is prepared for operation at the end of an extended down

slide-8
SLIDE 8

Power Outage

  • Site wide power outage
  • CHL1, CHL2, ESR, and Hall D plants shutdown
  • Systems were secured and prepared for restart
  • SC2 brought online first
  • SC1 pumpdown started two days later
  • Magnetic bearing cabinet reported normal conditions
  • Two hours into pumpdown the compressor failed

8

2015 Operations Stay Treat

slide-9
SLIDE 9

SC1 CC4 Failure

9

2015 Operations Stay Treat

Start of pumpdown Mag Bearing Trip

slide-10
SLIDE 10

SC1 CC4 Failure

10

2015 Operations Stay Treat

slide-11
SLIDE 11

SC1 CC4 Findings

3

2015 Operations Stay Treat

  • Backup ball bearing failure
  • When rotor fell bearing 0 to 35,000 RPM instantly
  • Inner and outer races shattered
  • Balls damaged
  • Shaft scored
  • Position sensors damaged
  • Air Liquid and S2M working on estimates
  • CC4 repair
  • Balancing spare wheels
  • List of recommended future spare parts
slide-12
SLIDE 12

Post UPS Failure Investigation

  • Investigation
  • UPS test function
  • Applies a high wattage resistor across batteries and measures

voltage drop over time

  • Does not test actual detection and switching functionality
  • New UPS test designed by JLAB
  • With compressor at zero speed
  • Simulate speed input with function generator
  • Turn off circuit breaker
  • Time 5 minutes
  • Turn down speed until UPS turns off
  • Perform at start of operation and after any power outages

12

2015 Operations Stay Treat

slide-13
SLIDE 13

SC1 Repair Using SNS Compressor

  • Moved our wheel and backplate to the SNS compressor
  • JLAB modified SNS compressor
  • LN2 supply and LN2 return connections
  • Magnetic bearing power and controls feedthroughs (x4)

4

2015 Operations Stay Treat

slide-14
SLIDE 14

SC1 CC4 Plan Forward

  • Estimate about 1 months of work remaining
  • Pull a vacuum on process piping
  • Check bearing controls
  • Test run compressor (balance and bearing control)
  • Visit from AL/S2M to certify bearings ready
  • Install vacuum shell and establish vacuum
  • Clean up system
  • Utubes and cooldown
  • Test by pumping down

14

2015 Operations Stay Treat

slide-15
SLIDE 15

Helium Losses

  • Three major losses found and repaired
  • CHL1 C6 (~110 liquid liters per day)
  • ESR utility piping (outside) (~110 liquid liters per day)
  • CHL1 bearing gas (basement of CHL1) (~110 liquid liters per

day)

15

2015 Operations Stay Treat

slide-16
SLIDE 16

Contamination

  • Following the power outage we had two episodes of

contamination problems

  • SC1 CC2 froze in place
  • SC2 primary heat exchanger plugged

16

2015 Operations Stay Treat

  • Likely causes
  • Large number of utube
  • perations performed during

down

  • Subatmosperic relief valves

leaking