In-Canal Phosphorus Treatment Study for Barr Lake
Project Kick-off Meeting
Harvey H. Harper, Ph.D., P.E. Environmental Research & Design, Inc.
In-Canal Phosphorus Treatment Study for Barr Lake Project Kick-off - - PowerPoint PPT Presentation
In-Canal Phosphorus Treatment Study for Barr Lake Project Kick-off Meeting Barr Lake/Milton Reservoir Watershed Association January 28, 2014 Harvey H. Harper, Ph.D., P.E. Environmental Research & Design, Inc. Uses for Alum in Lake
Harvey H. Harper, Ph.D., P.E. Environmental Research & Design, Inc.
phosphorus
phosphorus
yellow solution, depending on Fe content
aluminum sulfate by wt.
loads of 4500 gallons each Alum is made by dissolving aluminum ore (bauxite) in sulfuric acid
Alum is used to make many common items, such as:
Colloidal Runoff Sample After 12 Hours Immediately Following Alum Addition Initial Experiments (1980)
Initial testing evaluated salts of:
Alum was most effective Alum Reacts Quickly to Remove Both Particulate and Dissolved Pollutants
Treatment efficiency improves with increasing alum dose up to the “optimum” dose at which no significant improvement in effectiveness occurs
+3
2
3(ppt)
3
+
+3
n
4 n-3
4(ppt)
+
applied
Initial research on chemical coagulation conducted in the late 1970s – Evaluated salts of Al, Fe, and Ca Chemical coagulation evaluated for several stormwater retrofit projects in the early 1980s First system constructed at Lake Ella in Tallahassee in 1986 Currently, 60 systems have been designed and constructed in Florida with 4-5 in other states Systems have been designed to treat a wide variety of inflow types
Parameter Settled Without Alum (24 hrs) Alum Dose (mg Al/liter) 5 7.5 10
Ammonia ~ 0 ~ 0 ~ 0 ~ 0 NOx ~ 0 ~ 0 ~ 0 ~ 0
20 51 62 65 Particulate N 57 88 94 96 Total N 15 ~ 20 ~ 30 ~ 40
17 96 98 98 Particulate P 61 82 94 95 Total P 45 86 94 96 Turbidity 82 98 99 99 TSS 70 95 97 98 BOD 20 61 63 64 Fecal Coliform 61 96 99 99
acres (11.7 ha)
eastern and western lobes by 6 lane road
watershed
inflows contribute 95% of annual runoff
ft (3 m)
TP conc. > 100 µg/l
Lake Lucerne – Orlando Southern Gateway
Lake Lucerne (21.0 ac.)
Mechanical components for the Lake Lucerne alum treatment system are housed in an underground vault beneath an elevated expressway
Chemical metering pumps Pump control panels Flow meter control panels
20 40 60 80 100 120 140 160 180
Total Phosphorus (µg/l)
1990 1991 1992 1993 1994 1995 1996
Date Total Phosphorus
Before Alum Testing / Startup During System Operation During System Operation System Offline
Pre-treatment Water Quality 108 inch Stormsewer Post Treatment Water Quality
Lake Dot – Orlando
5 ac. Lake Receiving Runoff from 305 ac. Urban Watershed
Newspaper Cartoon
Equipment Building Alum Injection Equipment Underground Alum Storage Tank
Floc Discharge to Lake
Equipment Building Floc Disposal System In-line Floc Trap In-line Floc Trap
Floc Pumping Equipment Permeable Fabric
Equipment Building Alum Injection Equipment pH Control Equipment In-line Floc Settling Pond
Regional Flood Control Pond used for Floc Collection
Drivable Drainage Diversion Weir
Largo Regional Alum Treatment System
Treated Watershed Area = 1500 acres
Alum Injection Building Canal Flow Diverted Into Box Culvert Flow
Floc Settling Pond Elevated Wooden Boardwalk Floating Dock Paved Walking Path 15 Acre Hardwood Wetland Enhancement Wetland Enhancement
Largo Regional Alum Treatment System Components
Inflow Outflow
Particulate P Total P
Phophorus Concentration (µg/l)
50 100 150 200 250 Inflow Outflow
NH3-N NOx
Particulate N Total N
Nitrogen Concentration (µg/l)
500 1000 1500 2000 2500 Inflow Outflow
Lake Apopka (12,000 ha) Apopka-Beauclair Canal Lock & Dam Lake Beauclair Lake Dora NuRF Site
Pond 2
Area = 8.2 ac. Depth = 20 ft.
Pond 1
Area = 8.2 ac. Depth = 20 ft.
Lock and Dam Structure Inflow Canal Outflow Canal Apopka- Beauclair Canal Pump and Control Building 6 – 12,000 gal Storage Tanks Dried Floc Storage Area Dewatering Building Storage/Mixing Tank Alum/Air Addition
Specifications
Condition Annual Canal Discharge (ac-ft/yr) Estimated Annual Mass Load (kg/yr) Total N Total P TSS BOD Existing 1959-2000 54,092 193,972 13,328 2,465,472 339,836 Post Treatment1 54,092 137,002 (-29%) 3,838 (-71%) 591,713 (-76%) 209,781 (-38%)
Bypass Canal Basin 1 Canal
Pump and Control Building Treated Water Discharges to Floc Settling Trough Pumped Inflow ~ 10 cfs Alum Added Treated Water Discharge
Lake Seminole
In-Lake Floc Settling Area Alum/Air Addition Floc Pumped to Sanitary Pump Station
Seminole Bypass Canal Alum pumping and control bldg. Treatment System Inflow 10 cfs Treated Discharge
Lake Seminole
Cross-section of Treatment System
Floc collection system – discharge to sanitary sewer
25 ft.
Lake Seminole Bypass Canal Treatment System
First system which is totally automated
Pumped Inflow Pump/Control Building Water Level Control Weir
Inflow Portion of Floc Collection Trough Floc Collection System
Floc Collection Piping
PLC Pump and System Controller Floc collection Control Valve
Floc Pumped to Sanitary Sewer
After addition of alum, the concentration of dissolved aluminum is regulated by the pH of the treated water
– Minimum solubility of dissolved aluminum occurs in the pH range of 5.5 – 7.0 – If the pH of the treated water is in this range, dissolved aluminum will be minimal – Diss. Al concentrations generally decrease after treatment
5.7 7.2 Area of solubility < 100 ppb
Solid phase
Typical dissolved aluminum concentrations:
– Alum treated water ~ 50 -100 ppb – Most stringent EPA recommendation for most sensitive species in U.S. ~ 87 ppb (cold water fish in Washington) – Drinking water ~ 200 ppb; Milk ~ 700 ppb – Steeped tea ~ 4600 ppb, strong coffee ~ up to 10,000 ppb
Numerous fish and zooplankton bioassays have been conducted on alum treated water with 100% survival in all tests
Alum floc Pond sediments
Alum floc settles onto the pond bottom and begins to consolidate
Alum Dose (mg/l as Al) Sludge Production1 As Percent of Treated Flow Per ac-ft of Runoff Treated 5 0.16 70 ft3 7.5 0.20 87 ft3 10 0.28 122 ft3
[Al6(OH)12(H20)12]6+ [Al10(OH)22(H20)16]8+ [Al13(OH)30(H20)18]9+ OH Al = 0.3-2.1
Aluminum trihydroxide solid phase (Gibbsite) [Al13(OH)30(H20)18]9+ [Al24(OH)60(H20)24]12+ [Al54(OH)144(H20)36]18+ [Aln(OH)3n
Conclusions: 1. Aged alum floc is exceptionally stable under a wide range of pH and redox conditions
OH Al = 2.2-2.7 OH Al = 3.0-3.3
Impacts of alum addition to sediments was evaluated using a sediment incubation apparatus Allows sediment slurry to be incubated under a variety of pH and redox conditions Testing was conducted using both pre and post treatment sediments Redox conditions varied from highly reduced to oxidized conditions Redox potential controlled automatically using a relay to inject either air or nitrogen as needed After desired conditions were reached, the sediments were incubated for 7-10 days and a sub- sample collected for lab analysis
0.0 0.3 0.5 0.8 1.0 5.0 6.5 5.0 6.0 7.0 pH Cadmium Release (µg/g Dry Wt.)
0 mV 200 mV 400 mV
Pre Post
Lake Ella Sediment Metal Release in Treated an Untreated Sediments
0.00 0.25 0.50 0.75 1.00 1.25 5.0 6.5 5.0 6.0 7.0 pH Chromium Release (µg/g Dry Wt.)
0 mV 200 mV 400 mV 0.00 0.25 0.50 0.75 1.00 1.25 5.0 6.5 5.0 6.0 7.0 pH Copper Release (µg/g Dry Wt.)
0 mV 200 mV 400 mV 2 4 6 8 10 12 14 5.0 6.5 5.0 6.0 7.0 pH Lead Release (µg/g Dry Wt.)
0 mV 200 mV 400 mV
Release (µg/g dry wt.)
Lead
Release (µg/g dry wt.)
Copper Chromium Cadmium
Release (µg/g dry wt.) Release (µg/g dry wt.)
Post Pre Post Pre Pre Post
5 10 15 20 25 5.0 6.5 5.0 6.0 7.0 pH Aluminum Release (µg/g Dry Wt.)
0 mV 200 mV 400 mV 0.00 0.50 1.00 1.50 2.00 5.0 6.5 5.0 6.0 7.0 pH Zinc Release (µg/g Dry Wt.)
0 mV 200 mV 400 mV 0.0 0.2 0.4 0.6 0.8 1.0 1.2 5.0 6.5 5.0 6.0 7.0 pH Nickel Release (µg/g Dry Wt.)
0 mV 200 mV 400 mV
Pre Post
Lake Ella Sediment Metal Release in Treated an Untreated Sediments
Release (µg/g dry wt.)
Aluminum Zinc Nickel
Release (µg/g dry wt.) Release (µg/g dry wt.)
Post Pre Post Pre
Parameter Units Pre-Treatment (12/92) Post Treatment (3/96) Percent Change (%) Total N µg/l 9978 9765
Total Al µg/l 417 242
Total Cu µg/l 21 8
Total Fe µg/l 1389 467
Total Ni µg/l 17 2
Total Mn µg/l 314 77
Total Zn µg/l 80 30
Comparison Of Dominant Pre-treatment And Post-treatment Macroinvertebrate Assemblage At Site 1 In Lake Mizell
TAXA 1/28/97 1/29/98 1/27/99 1/31/00 MEAN (#/m2) % MEAN (#/m2) % MEAN (#/m2) % MEAN (#/m2) % Chaoborus punctipennis 4664 77.9 253 41.7 30 2.0 4502 66.3 Chironomus sp. 647 10.8 74 12.2 1095 73.2 119 1.7 Limnodrilus hoffmeisteri 396 6.6
4.9 592 8.7 Procladius bellus 15 0.2 148 24.4
3.7 Tanytarsus sp. 30 0.5 58 9.6
7.2
2.2
0.4 Hyalella azteca 57 0.9 15 2.2
4.4 Dero Nivea
15.8 74 1.1 Dero Trifida
1.0 30 0.4
2.0 15 0.2 Thienemanniella sp.
1.0
10.7 Pristina sp.
0.9 Cryptochironomus sp.
0.9 Ablabesmyia peleensis
0.2 Chaetogastor diaphanus
0.2
Lake Mizell received alum floc from treatment of runoff and a whole lake alum treatment
After 4-7 days After 30 days
Once completely dried, the floc forms into a rock hard material that will not re- dissolve
Floc after initial water decanting
Floc color is a function
removed from the treated water
Chemical Characteristics of Dried Alum Residual from the NuRF Pilot Studies1
Parameter Units Value Clean Soil Criteria2 (Chap. 62-777 FAC)
Aluminum μg/g 51,096 72,000 Antimony μg/g < 6.3 26 Barium μg/g < 21 110 Beryllium μg/g < 0.53 120 Cadmium μg/g 0.5 75 Calcium μg/g 1,564 None Chromium μg/g 65.0 210 Copper μg/g 31.6 110 Iron μg/g 764 23,000 Lead μg/g 0.7 400 Magnesium μg/g 96.8 None Manganese μg/g 12.3 1,600 Mercury μg/g < 0.091 3.4 Nickel μg/g 2.3 110 Zinc μg/g 50.6 23,000 NOx μg/g 0.773 120,000 Total N μg/g 2,054 None SRP μg/g < 1 None Total P μg/g 166 None pH s.u. 6.17 None
Alum residual easily meets the clean soil criteria
Parameter Units Measured Value EPA Regulated Level Class III Criteria (Ch. 62-302 FAC) Arsenic µg/l < 1 < 5000 < 50 Cadmium µg/l < 0.3 < 1000 < 0.3 Chromium µg/l 11 < 5000 < 86 Lead µg/l < 2 < 5000 < 3 Mercury µg/l < 0.01 < 200 < 0.01 Selenium µg/l < 5 < 1000 < 5 Silver µg/l < 007 < 5000 < 0.07 Leaching testing conducted under acid conditions at pH of 4.93
Project 20–Year Life Cycle Cost ($) Cost per Mass Pollutant Removed ($/kg) TP TN TSS
Alum Treatment Largo Regional STF Lake Maggiore STF Gore Street Outfall STF East Lake Outfall TF LCWA NuRF Facility Mean 2,044,780 4,086,060 1,825,280 1,223,600 34,254,861 253 200 87 135 198 164 65 71 12 17 30 31 4 2 1 1 2 2 Wet Detention Melburne Blvd. STF Clear Lake Ponds STF Mean 1,069,000 1,091,600 371 658 494 125 237 172 2 22 2
* Does not consider land cost
which eliminates sediment P release
become soluble under anoxic conditions (< 0 mV)
Ferric iron Oxidized State Insoluble Ferrous iron Reduced State Soluble
Floc initially settles onto the surface of the sediments
Alum floc layer Consolidated organic sediments Unconsolidated organic sediments (muck) Floc migrates downward over time Alum floc layer
the top of the loose surficial layer
time into unconsolidated sediment layer
re-suspends as a result of wind
quickly settle back
effectiveness since the sediment P will be adsorbed onto the floc
maintains effectiveness, floc re- suspension may adsorb and remove additional P from the water column
ρ ~ 1.05 ρ ~ 1.02 ρ ~ 1.1-1.2
Identify and evaluate passive and active treatment options that will reduce inflow TP by 75%.
Provide cost estimates for each in-canal treatment
Provide a comprehensive report that summarizes Tasks 1 and 2 and provides recommendations
taken in implementing an in-canal phosphorus treatment system
Imagery Date: October 2012
50 100 150 200 250 300 350 400 Number of Days Interval (cfs)
150 60
2006 2007 2008 2009 2010 2011 2012 2013
pH
7.0 7.5 8.0 8.5 9.0 9.5 2006 2007 2008 2009 2010 2011 2012 2013
Alkalinity (mg/l)
50 100 150 200 250 300 350
inflow pH to 6 - 7 range
treatment
sulfate for every 1 mg/L Al added
Al/L will add 30 mg/L sulfate
floc formation
simulate low temps
2006 2007 2008 2009 2010 2011 2012 2013
Sulfate (mg/l)
100 200 300 400 500 600
Conductiviy (µmho/cm)
2006 2007 2008 2009 2010 2011 2012 2013
Temperature (°C)
5 10 15 20 25 30
but produces a slow settling floc
does remove portions of TKN
2006 2007 2008 2009 2010 2011 2012 2013
Nitrogen (mg/l)
2 4 6 8 10 12 14 16 18 NOx TKN Total N 2006 2007 2008 2009 2010 2011 2012 2013
Phosphorus (mg/l)
0.0 0.5 1.0 1.5 2.0 2.5 3.0 SRP Total P
80% by alum
an assumed discharge rate until a removal of 75% was achieved
100 200 300 400 500 600 700 800 900 1,000 01/01/06 01/01/07 01/01/08 01/01/09 Phosphorus (kg/day) Treated Load (kg/day) Untreated (kg/day)
Baker Creek Inflow Constructed Wetland Treatment Area Flow Diversion
Option evaluated to divert alum treated water into the wetland treatment area However, several concerns led to elimination of this
– Wetland is a permitted mitigation site – Wetland was shallow, and concern raised over filling of wetland with floc – Difficulty in floc removal – Floc removal would damage wetland – Concerns over wetland area negatively impacting treatment efficiency