BATHURST QUAY NEIGHBOURHOOD PLAN (BQNP) IMPLEMENTATION YQNA Update: Design, Construction & Consultation Bryan Bowen City Planning Waterfront Secretariat May 2020 CANADA MALTING PROPERTY: TRANSFERRED FOR PUBLIC PURPOSES VIA


slide-1
SLIDE 1

BATHURST QUAY NEIGHBOURHOOD PLAN (BQNP) IMPLEMENTATION

YQNA Update: Design, Construction & Consultation

Bryan Bowen City Planning –Waterfront Secretariat May 2020

slide-2
SLIDE 2

CANADA MALTING PROPERTY: TRANSFERRED FOR “PUBLIC PURPOSES” VIA 1992 HARBOURFRONT IMPLEMENTATION AGREEMENT

Canada Malting Site = 1.8ha HTO Park = 1.6ha 2

slide-3
SLIDE 3

TODAY: NEGLECTED BUILT HERITAGE, OPEN SPACE AND CULTURAL ASSETS

3

slide-4
SLIDE 4

ARTIST’S RENDERING OF PROPOSED IMPROVEMENTS

1 2 3 6 4 5 JULY 2017 BQNP. ONE ACTION-ORIENTED PLAN. SEVEN PROJECTS IN PARTNERSHIP. 7

4

slide-5
SLIDE 5

1: NEW WATERFRONT PROMENADE

After: Continuation of Portland Slip Before 5

slide-6
SLIDE 6

Oct 2019 Ground-breaking ceremony Nov 2019

1: NEW WATERFRONT PROMENADE

6

slide-7
SLIDE 7

May 2020

1: NEW WATERFRONT PROMENADE

7

slide-8
SLIDE 8

Public & Open Space (34% to 66%) Parking & Transportation (22% to 17%) Underutilized Space (27% to 0%)

EXISTING PROPOSED

Buildings (17%)

2: TRANSPORTATION IMPROVEMENTS

8

slide-9
SLIDE 9

2: TRANSPORTATION IMPROVEMENTS

DILLON CONSULTING & MONTGOMERY SISAM ARCHITECTS 9

slide-10
SLIDE 10

2: TRANSPORTATION IMPROVEMENTS

10 May 2020

slide-11
SLIDE 11

3: IRELAND PARK INTERPRETIVE & CULTURAL CENTRE

KEARNS MANCINI ARCHITECTS 11

slide-12
SLIDE 12

3: IRELAND PARK INTERPRETIVE & CULTURAL CENTRE

KEARNS MANCINI ARCHITECTS 12

slide-13
SLIDE 13

3: IRELAND PARK INTERPRETIVE & CULTURAL CENTRE

KEARNS MANCINI ARCHITECTS 13

slide-14
SLIDE 14

4: NEW WATERFRONT PLAZA & EVENT SPACE

New community and event space on the waterfront 14

slide-15
SLIDE 15

EXISTING PROPOSED

4: NEW WATERFRONT PLAZA & EVENT SPACE

15

slide-16
SLIDE 16

5: TDSB SPORTS FIELD ENHANCEMENTS & 6: STREETSCAPE IMPROVEMENTS

16

slide-17
SLIDE 17

17

7: CANADA MALTING SILOS REHABILITATION

slide-18
SLIDE 18

7: CANADA MALTING SILOS REHABILITATION

18

slide-19
SLIDE 19

Two-Part Strategy: 1: Repair 2: Re-purpose

19

slide-20
SLIDE 20

Why Two Parts?

  • Learn from past efforts.
  • Undertake needed repairs.
  • Utilize available site access.
  • Wait for the right partner(s).

20

slide-21
SLIDE 21

Part 1: Repair 2019: Updated condition assessment 2020: Detailed engineering work 2021/2022: Exterior SOGR work Part 2: Repurpose 2020: Develop EOI 2020/2021: Launch EOI/RFP Process TBD: Select Re-use Partner(s)

7: CANADA MALTING SILOS REHABILITATION

21

slide-22
SLIDE 22

Part 1: Repair Scope of Work Design, Tender Docs, Contract Admin & Construction Management for:

  • New roofing system
  • Power supply and roof anchor

system

  • Exterior wall repairs
  • Heritage Conservation Plan
  • Removal of perimeter fence
  • Water and sanitary service

investigation (co-ordinated with plaza design and construction)

  • Exploring new connections

between the buildings

7: CANADA MALTING SILOS REHABILITATION

22

slide-23
SLIDE 23

Part 1: Repair 2019: Updated condition assessment 2020: Detailed engineering work 2021/2022: Exterior SOGR work Part 2: Repurpose 2020: Develop EOI 2020/2021: Launch EOI/RFP Process TBD: Select Re-use Partner(s)

7: CANADA MALTING SILOS REHABILITATION

23

slide-24
SLIDE 24

PRELIMINARY IDEAS

24

slide-25
SLIDE 25

Overview of key dates

  • 1. Promenade: Fall 2020 completion.
  • 2. Transportation: April 2020 construction start.

2020 completion.

  • 3. Corleck Building: Summer 2020
  • Consultation. Summer 2020 construction start.

Summer 2021 Phase 1 opening.

  • 4. Plaza: Fall 2020 consultation. 2020 Design.

2021 construction start. Phased opening 2021 and 2022.

  • 5. Play field: 2020 Design. 2021 construction.

Opening 2021.

  • 6. Streetscape: Fall 2020 consultation. 2020
  • Design. 2021 construction. Opening 2021.
  • 7. Silos rehabilitation:

Part 1: 2020 Design. 2021 construction start. Part 2: EOI/RFP late 2020/early 2021.

1 2 2 3 6 7 6 4 4 5

25

slide-26
SLIDE 26

BATHURST QUAY NEIGHBOURHOOD PLAN IMPLEMENTATION DISCUSSION

Bryan Bowen City Planning –Waterfront Secretariat bryan.bowen@toronto.ca 416-338-4842