Arlandria Action Plan Implementation Status of Implementation Activities Tuesday, September 11, 2012 Implementation Approach Citizen Advisory Group (AG)) Arlandria Development Non-Profit Action Plan & Business Community


  1. Arlandria Action Plan Implementation Status of Implementation Activities Tuesday, September 11, 2012

  2. Implementation Approach Citizen Advisory Group (AG)) Arlandria Development Non-Profit Action Plan & Business Community Implementation Community City Staff Team Arlandria Action Plan Implementation 2 09.11.2012

  3. 2011-2012 Work Program • Public Investment • Development Projects • Retail and Small Businesses • Community Engagement and Community-Led Quality of Life Projects • Communication with City Council Arlandria Action Plan Implementation 3 09.11.2012

  4. 2011-2012 Activities • Public Investment – Mt. Vernon Ave/W. Reed Ave Intersection Improvements – Four Mile Run Park Expansion Arlandria Action Plan Implementation 4 09.11.2012

  5. 2011-2012 Activities • Development Projects Mt. Vernon Village Center E. Reed Townhomes Four Mile Run Pump Station Improvements Arlandria Action Plan Implementation 5 09.11.2012

  6. 2011-2012 Activities • Retail and Small Businesses Façade Improvement Grant Improvements Mt. Vernon Avenue Commercial Corridor Arlandria Action Plan Implementation 6 09.11.2012

  7. 2011-2012 Activities • Community Engagement and Community-Led Quality of Life Projects Neighborhood Beautification Projects Four Mile Run Farmers & Code Compliance Artisans Market Walks Arlandria Action Plan Implementation 7 09.11.2012

  8. Recommendations for FY13 Implementation Activities • Public Investment – Four Mile Run Park Expansion - $200,000 ( unfunded estimate) – Four Mile Run Park Community Building - $180,000 ( unfunded estimate) – Safe Routes to School - $50,000 (funded) – Pedestrian and Bicycle Improvements - $100,000 (funded) – Bike Lanes, Sharrows, Bike Parking - $30,000 (funded) – Bus Shelters - $68,000 (funded) Arlandria Action Plan Implementation 8 09.11.2012

  9. Recommendations for FY13 Implementation Activities • Initiatives to Support Planned Redevelopment and Spur Economic Development – Work with the existing property owners within CDD #12 – Create a coordinated streetscape improvement program – Initiate an “Arts in Arlandria” demonstration project – Explore Neighborhood-wide branding and marketing strategies Arlandria Action Plan Implementation 9 09.11.2012

  10. Recommendations for FY13 Implementation Activities • Retail and Small Businesses – Provide technical assistance to Arlandria businesses – Host seminars targeted to business owners/operators – Link eligible businesses to available local funding sources to improve operations – Support the Arlandria-Chirilagua Business Association – Actively recruit businesses to fill gaps in the market – Prepare existing businesses for new tourism traffic Arlandria Action Plan Implementation 10 09.11.2012

  11. Recommendations for FY13 Implementation Activities • Community Engagement and Community-Led Quality of Life Projects – Support community engagement – Support the Four Mile Run Park Farmers & Artisans Market – Host events at Four Mile Run Park Community Building – Support additional community-led activities Arlandria Action Plan Implementation 11 09.11.2012

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.