Ice Quay and Breakwater Quay Extensions 7pm 5 th November 2020 - - PowerPoint PPT Presentation

ice quay and breakwater quay extensions
SMART_READER_LITE
LIVE PREVIEW

Ice Quay and Breakwater Quay Extensions 7pm 5 th November 2020 - - PowerPoint PPT Presentation

Ice Quay and Breakwater Quay Extensions 7pm 5 th November 2020 Welcome Please turn-off your camera and mute your microphone. This meeting is being recorded so that it can be placed on the website after the event. If you would like


slide-1
SLIDE 1

Ice Quay and Breakwater Quay Extensions

7pm – 5th November 2020

slide-2
SLIDE 2

Welcome

  • Please turn-off your camera and mute your

microphone.

  • This meeting is being recorded so that it can

be placed on the website after the event.

  • If you would like to ask a question please

‘raise your hand’, or use the ‘chat’ function.

  • If you would prefer for your question not to

be recorded then there will be an opportunity at the end, when recording has been stopped.

slide-3
SLIDE 3

Meet the Team

  • Jacqueline McDonell - Mallaig Harbour

Authority

  • Ed Carrick – Wallace Stone
  • Fiona Henderson – Affric Limited
slide-4
SLIDE 4

Agenda

  • Purpose of the Event
  • Mallaig Harbour Master Plan
  • Outer Harbour Development Proposals
  • Consenting
  • Environmental Considerations
  • Questions
  • Questionnaire
  • What Next
slide-5
SLIDE 5

Purpose of the Event

  • MHA wish to carry out development in the

Outer Harbour Area, and we are seeking comment on the proposals.

– Questions will be highlighted through the presentation for discussion at the end.

  • The Marine Licensing (Pre-application

Consultation (PAC)) (Scotland) Regulations 2013.

slide-6
SLIDE 6

Mallaig Harbour Master Plan

  • The Master Plan was produced in 2016.
  • It identified the need to create a new north

breakwater and harbour area primarily for the ferry. This fed into a STAG appraisal, completed April 2020.

  • Multiple smaller projects identified,

including the development of the ‘Slot’ in the Outer Harbour.

slide-7
SLIDE 7
slide-8
SLIDE 8

Mallaig Harbour Master Plan

  • Works completed to date include:

– Passenger Access Pontoon. – New Ice Plant – West Bay Road Improvement – Clearance of area behind Prawn Hall. – Site Investigation, Preliminary Design & Planning Permission for West Highland College building (by others).

slide-9
SLIDE 9

Outer Harbour Development Proposals

Make use of the ‘Slot’.

slide-10
SLIDE 10

Outer Harbour Development Proposals

  • Provide

additional sheltered berthing.

  • Provide

additional laydown/ development space.

slide-11
SLIDE 11

Outer Harbour Development Proposals

  • Various options and layouts considered.
  • Initial thought was to extend both the Ice

and Outer Breakwater Quay.

slide-12
SLIDE 12

Extend Ice and Outer breakwater Quay Option

slide-13
SLIDE 13

Outer Harbour Development Proposals

  • Issues with regard to rockhead levels

beneath the approach road and inner end

  • f the existing breakwater quay.
  • Hence splay berth option to avoid the

need to disturb this area.

slide-14
SLIDE 14

Splay Berth Option

slide-15
SLIDE 15

Splay Berth Option

slide-16
SLIDE 16

Outer Harbour Development Proposals

  • The Splay Berth design:

– Provides 60m of additional quay length capable of taking boats of up to 500 tonnes. – Provides 4000m2 of additional laydown. – Services

Any comments on the Splay Berth design proposed and what services would you like included?

slide-17
SLIDE 17

Outer Harbour Development Proposals

  • Current water depths in the outer harbour are
  • 4mCD, however the existing infrastructure

could facilitate water depths of -6m CD.

  • It would however, require dredging, including

blasting of rock and clearly that would have cost and environmental implications. Do you think there is a need/ benefit of increasing the water depths?

slide-18
SLIDE 18

Proposed Dredge Area

slide-19
SLIDE 19

Consenting Route

  • The construction works and dredge (if

required) will need a Marine Licence from Marine Scotland under the Marine Scotland Act 2010.

  • As previously mention Pre-Application

Consultation is required due to the scale of the development.

  • It is yet to be determined if an Environmental

Impact Assessment (EIA) will be required under the Marine Works (EIA) (Scotland ) Regulations 2017.

slide-20
SLIDE 20

Environmental Considerations

  • EIA Screening Report being drafted for

submission to Marine Scotland.

  • Sensitive Environmental Receptors have been

identified and potential effects on them identified for both construction and

  • perational stages.
  • Early identification of potential issues allows

them to be taken account of in the design process such that effects are avoided, or mitigated by design.

slide-21
SLIDE 21

Environmental Considerations

  • Potential effects include:

– Local Community with regard to construction noise, traffic and economic benefits (job creation). – Marine Mammals impacts of underwater noise will be determined by pile design and installation and dredge techniques. – Birds (including Manx Shearwaters), construction and operational light design considerations.

slide-22
SLIDE 22

Environmental Considerations

  • Potential effects include (cont.):

– Knoydart National Scenic Area low lying development shouldn’t affect it. – Vessel access to Outer Harbour during construction and navigation effects. – Water and air quality effects of construction, potential need for dust management and pollution prevention techniques.

Any other environmental issues or concerns?

slide-23
SLIDE 23

Questions

  • Any comments on the Splay Berth design

proposed?

  • Do you think there is a need/ benefit of

increasing the water depths?

  • Any other environmental issues or

concerns?

  • Any questions for us?
slide-24
SLIDE 24

Questionnaire

  • Encourage all of you to complete a

questionnaire.

  • The link to which can be found at:

– www.Mallaig-harbour.com/news or – www.affriclimited/News/Consultaions.php (Recording of this event will also be there).

  • Or email consultation@affriclimited.co.uk

for a copy.

slide-25
SLIDE 25

What’s Next

  • If you wish to make representations on the proposed

development, please contact Fiona Henderson at Affric Limited, Lochview Office, Loch Duntelchaig, Farr, IV2 6AW or by email, consultation@affriclimited.co.uk. by the 20th of November 2020.

  • Please note, comments made are not representations

to the Scottish Ministers. Once the Marine Licence Application has been submitted there will be an

  • pportunity for representations to be made to the

Scottish Ministers on the application.

  • Following consultation, a Marine Licence Application

will be submitted to Marine Scotland for consent to construct the laydown area through a land reclamation.

slide-26
SLIDE 26

Thank You

  • If you would like to be added to our

mailing list for updates, then please fill in a questionnaire or email: Consultation@affriclimited.co.uk

  • Thank you for your time this evening.