SLIDE 1 PRESENTATION FOR FTAC
April 10, 2013
PRESENTED BY Robert Bostian, PE FDOT District 4 Judy Solaun-Gonzalez, PE FDOT District 6
I-75 and Palmetto Express Lanes
SLIDE 2
Regional Managed Lanes Network
2
SLIDE 3 Project Limits
- SR 826 from W Flagler St. to
I-75 and I-75 from SR 826 to I-595 (Total 28 miles)
W Flagler St. to NW 154th St. and I-75 from SR 826 to NW 170th St. (13 miles)
- D4 Segment - I-75 from NW
170th St. to I-595 (15 miles)
SLIDE 4 75 Express Typical Section
- I-75 Express Lanes in median from SR 826 to I-595
(18 miles)
- Barrier separated typical section
- 1 to 2 lanes in each direction
SLIDE 5 Palmetto Express Typical Section
- Palmetto Express Lanes in median from W Flagler St. to
NW 154th St. (10 miles)
- Tubular delineator separation between EL and GP lanes
- 1 to 2 lanes in each direction
SLIDE 6 ITS/Tolling
- All electronic tolling – 13 gantry locations
- Congestion pricing / Variable tolling
- Three destination toll rate signing
- Integrated ITS and tolling
SLIDE 7
Express Lanes Configuration
SLIDE 8
Tolling Strategy
SLIDE 9 I75 / Palmetto Express Lanes Assumptions
- Express Lanes along the Palmetto Express Lanes
have reduced lane and shoulder widths
SLIDE 10
I-75 SEGMENTS
SLIDE 11
Project Segmentation
SLIDE 12 Construction Segment FPID# I-75 Limits Approx. Length (mi.) Additional Information Segment A 421707-2 From NW 170th St. to South of HEFT Mainline 1.3 Includes 2 toll gantries. Segment B 421707-3 421707-8 From South of HEFT Mainline to South of Miramar Pkwy. 1.7 Includes I-75 Express Lanes (EL) Bridge over HEFT Mainline; NB I-75 (widening), EL’s & NB HEFT Ramp Bridge (3) over C-9 Canal; and NB & SB EL Ramps over I-75 (2) Segment C 421707-4 From South of Miramar Pkwy. to South of Sheridan St. 3.6 Includes I-75 EL Bridge over C-4 Canal and 2 toll gantries. Segment D 421707-5 From South of Sheridan St. to North of Griffin Road 3.7 Includes I-75 EL Bridge over C-11 Canal and 2 toll gantries. Segment E 421707-6 From North of Griffin Road to I-595 4.7 Includes Reversible Ramp Bridge for I-75 to I-595 EL connection; Ramps R-1, R-2 and R-4 connections to I-595; and 1 toll gantry. Corridor-Wide ITS/Tolls Integration 421707-7 421707-9 From NW 170th St. to I-595 15.0 Includes corridor-wide installation of the fiber optics for the ITS backbone and toll systems integration with the Traffic Management Center (TMC) central control software and ITS and toll systems testing. TOTALS 15.0
Segment Limits/Scope Elements
- Logical project limits established per segment
- Prescriptive RFP criteria for corridor continuity
SLIDE 13
PALMETTO EXPRESS SEGMENT
SLIDE 14 Palmetto Express Lanes Project Overview
- Project Limits: SR 826 from W Flagler St. to NW 154th St.
and I-75 from SR 826 to NW 170th St. (FM 432687-1)
- Project Length: 13 miles
- Delivery Method: 1 Design Build Contract
- Estimated Maximum Construction Cost: $275 million
- Currently under procurement process
SLIDE 15 Palmetto Express Lanes Project Scope
- Single and dual Express Lanes
- Category II structure connecting I-75 EL to SR 826 EL
- Widening along SR 826 where public R/W is available
- Toll gantries, housing and increase in ITS backbone capacity
- Ramp signaling along SR 826
- New Sound barrier walls along I-75
- Lighting along the I-75 Express Lanes
SLIDE 16 Additional Scope
- Additional overbuild, milling and resurfacing along SR 826
- NB: 0.212 miles
SB: 1.053 miles
- Estimated cost: $2.8M
- 7 RRR Projects and 1 Safety Project
- Estimated cost: $1.6M
SLIDE 17
Project Video
SLIDE 18
PROCUREMENT PROCESS AND SCHEDULE
SLIDE 19
I-75 Procurement Schedule
Segment E
Procurement Activity Date Advertisement January 28, 2013 Expanded Letters of Interest Due February 15, 2013 Shortlist Posting March 21, 2013 Final RFP Provided to D-B Firms March 27, 2013 Technical Proposals Due June 3, 2013 Price Proposals Due July 24, 2013 Anticipated Award Date August 8, 2013 Anticipated Execution Date August 28, 2013
SLIDE 20 I-75 Procurement/ Construction Schedule
Segments A-D & ITS/Tolls Integration
- To be advertised on 7 to 13 week intervals
- ITS/Tolls Integration advertisement follows ITS Final Plans
(Segment A) – tentative February 2015
SLIDE 21
Palmetto Express Lanes Procurement Schedule
Palmetto Expressway Segment
Procurement Activity Date Advertisement March 15, 2013 Expanded Letters of Interest Due April 5, 2013 Shortlist Posting April 24, 2013 Final RFP Provided to D-B Firms April 25, 2013 Technical Proposals Due September 9, 2013 Price Proposals Due November 8, 2013 Anticipated Award Date November 27, 2013 Anticipated Execution Date December 4, 2013
SLIDE 22 Palmetto Expressway Procurement/ Construction Schedule
- Palmetto Expressway D-B contract includes ITS/Tolls
Integration
- Corridor opening 2018 – based on maximum allowable
construction time
- D6 programmed a $5.25 million incentive to open facility
to users as soon as possible
SLIDE 23 Project Websites
- I-75 Express Lanes D-B website: www.75-express.com
- Palmetto Expressway D-B website:
www.palmettoexpresslanes.com
SLIDE 24 Project Contacts
Robert Bostian, Jr., PE Project Manager
e-mail: Robert.Bostian@dot.state.fl.us
- For Palmetto Expressway Project
Judy Solaun-Gonzalez, PE Senior Project Manager
e-mail: Judy.solaun@dot.state.fl.us
SLIDE 25
QUESTIONS?