ANALYSIS OF THE MERCATOR POLICY OPTIONS
I-77
EXPRESS LANES
August 15, 2018
I-77 EXPRESS LANES August 15, 2018 I-77 Express Lanes | August - - PowerPoint PPT Presentation
ANALYSIS OF THE MERCATOR POLICY OPTIONS I-77 EXPRESS LANES August 15, 2018 I-77 Express Lanes | August 15, 2018 Agenda Meeting #8 Introductions Review of options Secretarys update Technical review Closing
ANALYSIS OF THE MERCATOR POLICY OPTIONS
EXPRESS LANES
August 15, 2018
Agenda – Meeting #8
▪ Introductions ▪ Review of options ▪ Secretary’s update ▪ Technical review ▪ Closing
2
Local Advisory Group
▪ Established in December 2017 with 12 members
– Advise and provide input for the NCDOT Secretary
▪ Seven meetings to date
– January 2018 through May 2018
▪ Discussion topics
– Project history and overview – Mercator options and associated pros and cons – Member feedback – Additional options for consideration
3
Mercator Policy Options
▪ Option A: Terminate the CA and complete the express lanes project using public funding or financing as it becomes available ▪ Option B: Terminate the CA and allow CRTPO to determine whether express lanes should remain in the transportation plan or be replaced or supplemented with other improvements based on available resources ▪ Option C: Negotiate modifications to the project scope and/or the terms of the CA, such as:
▪ Option D: Work with CRTPO to identify and advance additional improvements to address mobility issues in the corridor ▪ Option E: Develop preliminary plans to negotiate and finance the purchase of the express lanes project after completion ▪ Option F: Complete and delete
4Options Currently Under Evaluation
5
Options Discussed Summary of Local Advisory Group Input Option C-1 Negotiate contract modification - defer or eliminate tolling of certain lanes Evaluate costs to convert to 3 GP lanes and 1 EL between exits 23 and 28. Option C-2 Negotiate contract modification - frequent user discounts or toll credits Potential benefits and costs of discounts can be better evaluated after initial operating data is available. Option C-3 Negotiate contract modification - allow medium trucks Consider modifications to truck restrictions based on project performance. Evaluate potential toll rates and revenue impact. Option C-5 Negotiate contract modification - change compensation provision for unplanned revenue impacting facilities Determine what potential improvements within the airspace are desirable and feasible*Additional Options Suggested by LAG
Note: Information presented here is a summary of feedback provided by LAG. These comments do not necessarily represent the opinions or policies of NCDOT or NCTA.Based on input from the May 10, 2018 Local Advisory Group meeting, the following options are not being evaluated at this time
6
Options Discussed Summary of Local Advisory Group Input Option A Terminate the CA and complete the express lanes project using public funding or financing as it becomes available Significant cost and schedule impacts; similar outcome can be pursued after completionSecretary Jim Trogdon
7
Options Evaluated with Hypothetical STI Statewide Scores
8
Option Estimated Cost Impacts Hypothetical Score+
C-1 Convert 1 EL to GP lane (change from 2+2 to 3+1) exit 23 to 28 and convert 1 EL to GP lane (change from 2+1 to 3+0) exit 28 to 36 $400M 50-55 E Purchase the contract and keep express lanes as planned $392M-$623M* 45-50 F Purchase the contract and convert all EL to GP lane $540M-$771M** 45-50 H Add 1 GP lane (change from 2+1 to 3+1) exit 28 to 36 $350M-$600M 70-75 I Convert 1 EL to GP lane (change from 2+2 to 3+1) exit 23 to 28 and add 1 GP lane (change from 2+1 to 3+1) exit 28 to 36 $550M-$800M 70-75 J Add auxiliary lane exit 23 to 25; exit 25-28; or exit 33-35 (scored by segment) $40M (each segment) 60-65
+Actual score is dependent on competition against other projects and availability of funding at the time of prioritization/ranking. *Does not include demobilization costs, breakage costs, or additional allowable costs. **Includes $86M of BA Payback. Note: P5.0 score for I-77 South is 89 and for I-77 North is 85.Main Objective Ultimately, the State of North Carolina will Operate this Facility
9
How Do We Get There?
Improve, Expand and Protect
Improve
– Toll caps (option C-2-2) – Frequent user discounts (option C-2-1) – Allow medium size trucks use of express lanes capacity (option C-3)
10
Improve, Expand and Protect Plan
Expand
– Harden shoulders during peak periods (option G) – Convert one express lane to a general purpose lane (3+1) exit 23-28 and add one general purpose lane (3+1) exit 28-36 (option I) – Develop and implement a process to continually evaluate contract purchase under Strategic Transportation Investments (required process to reach goal of operating facility) (option E) – Add auxiliary lanes exit 23-25, 25-28 and 33-35 (option J)
11
Improve, Expand and Protect Plan
Protect
North Carolinians have an opportunity to participate BEFORE decisions are final
effective and efficient solution is completed to ensure results
regarding this plan
12
Improve, Expand and Protect Plan
Constraints
– Requires projects be scored based on data and then be prioritized for funding
– Requires NCDOT to report any proposed contract modifications or cancellations to the NC General Assembly at least 60 days in advance – Defines impacts to funding for other projects as it relates to the bonus allocation and project (corridor) cap
– New or modified construction will require design time/possible permitting – Contract modifications must be negotiated
13
Summary
– Negotiate better terms for drivers
– Work to expand non-toll capacity options being pursued
– Continue to engage the public in an open and transparent manner
14
TECHNICAL REVIEW
Negotiate Better Terms for Drivers
▪ Frequent user discounts
– Typically, presented as discount or credit to users who meet a given criteria – Actual discount amount, timeframe for discount and specific criteria for potential discount are subject to negotiation with the Developer
▪ Toll caps
– Limits the maximum toll a user would pay to travel the corridor – Initial toll cap and annual increase of toll cap are subject to negotiation with the Developer
▪ Allow medium trucks
– Current contract does not allow vehicles with more than two axles – Type and length of allowed trucks as well as toll rate differential are subject to negotiation with the Developer
16
Improve
Option G - Hardened Shoulder: Exit 23 to Exit 35
▪ Harden outside shoulder for use during peak periods ▪ Intended to help local travel between interchanges ▪ Considered to be a mid-term implementation ▪ Can be implemented in phases ▪ Used in cities across US
– I-405 in Washington, I-66 in Virginia, etc
17 SOUTHBOUND NORTHBOUND Gilead Rd Catawba Ave Williamson Rd / Charlotte HwyEXIT 19 EXIT 28 EXIT 33 EXIT 36 EXIT 23 EXIT 25 EXIT 35
Brawley School Rd Westmoreland RdEXIT 31 EXIT 30
Griffith St Langtree Rd LakeExpand
Hardened Shoulder: Examples
18 I-66, Virginia (Source: Goodman Realtors) I-405, Washington (Source: HeraldNet)Expand
Option I - Three GP Lanes: Exit 23 to Exit 36
▪ Considered to be a long-term implementation ▪ Convert one express lane to general purpose lane between exit 23 and 28 ▪ Add a new general purpose lane between exit 28 and 36
– Requires Federal Energy Regulatory Commission (FERC) permit to cross the 760’ elevation – Other environmental permits may be required
19 SOUTHBOUND NORTHBOUND Gilead Rd Catawba Ave Williamson Rd / Charlotte HwyEXIT 19 EXIT 28 EXIT 33 EXIT 36 EXIT 23 EXIT 25 EXIT 35
Brawley School Rd Westmoreland RdEXIT 31 EXIT 30
Griffith St Langtree Rd LakeExpand
I-77 Over Causeway – As Currently Designed
20 Notes:Expand
EXPRESS EXPRESSWidening through moment slab Widening through sheet piles Widening through earthen fill
▪ Reviewed various possibilities to widen over the causeway including, but not limited to, the following three concepts:
Widening Over the Causeway
Expand
EXPRESS EXPRESS EXPRESSOption J - Add Auxiliary Lanes North of Exit 23
▪ New option developed based on feedback from the Local Advisory Group ▪ Considered to be a long-term implementation ▪ Add auxiliary lanes where they do not exist
– Between exit 23 and 25 – Between exit 25 and 28 – Between exit 33 and 35
▪ Intended to help local traffic between interchanges
22
SOUTHBOUND NORTHBOUND Gilead Rd Catawba Ave Williamson Rd / Charlotte HwyEXIT 19 EXIT 28 EXIT 33 EXIT 36 EXIT 23 EXIT 25 EXIT 35
Brawley School Rd Westmoreland RdEXIT 31 EXIT 30
Griffith St Langtree Rd LakeExpand
Closing
Group members
available
needs in the region
23
THANK YOU!