395 Express Lanes Project Update October 2, 2018 Susan Shaw, VDOT - - PowerPoint PPT Presentation

395 express lanes project update
SMART_READER_LITE
LIVE PREVIEW

395 Express Lanes Project Update October 2, 2018 Susan Shaw, VDOT - - PowerPoint PPT Presentation

395 Express Lanes Project Update October 2, 2018 Susan Shaw, VDOT MegaProjects Director Project Overview Expansion and conversion of 2 High Occupancy Vehicle (HOV) lanes to 3 Express Lanes Addition of fourth regular southbound lane on


slide-1
SLIDE 1

395 Express Lanes Project Update

October 2, 2018 Susan Shaw, VDOT MegaProjects Director

slide-2
SLIDE 2

2

Project Overview

395 Express Lanes Project Update

  • Expansion and conversion of 2 High Occupancy

Vehicle (HOV) lanes to 3 Express Lanes

  • Addition of fourth regular southbound lane on

395 between Duke Street and Edsall Road

  • Improvements to Eads Street Interchange and

carpool access at the Pentagon

  • Sound walls
  • Rehabilitation bridges
  • Annual transit revenue

Typical Project Cross Section

slide-3
SLIDE 3

3

Key Dates

395 Express Lanes Project Update

Milestone Date Groundbreaking August 2017 Cordon off eastern HOV shoulder Late 2017 Cordon off western HOV shoulder Fall 2018 Pentagon Parking Improvements Completion Spring 2019 Service Commencement Late Fall 2019 Final Completion Summer 2020

slide-4
SLIDE 4

4

Construction Status – Express Lanes

  • Work continues to progress, with two of five construction phases completed
  • Milling and paving
  • Storm drainage installation
  • Light pole foundations, ductbank, and overhead sign foundations
  • 395 project remains on schedule for service commencement in late Fall 2019,

within budget

slide-5
SLIDE 5

5

Widen I-395 Southbound Duke Street to Edsall Road

395 Express Lanes Project Update

Edsall Road Interchange

  • Replace existing Edsall Westbound to

I-395 Southbound Loop Ramp with new signalized intersection Duke Street Interchange

  • Replace existing I-395 Southbound to

Duke Eastbound Loop Ramp with new signalized intersection

slide-6
SLIDE 6

6

Pentagon parking and Eads Street interchange improvements

Reconfigure a portion of the South Parking Area to enhance circulation for transit buses and carpools

Map of Eads Street Interchange and Pentagon Multimodal Improvements

slide-7
SLIDE 7

7

Edsall Walkway

  • Add walkway on North side of Edsall Road, including

bridge over I-395

  • Final design plans sent in September 2018 to Fairfax

County for review, Comments received

  • Construction Change Order to be negotiated and issued
  • Construction planned to begin Spring 2019, planned

completion in 2020

  • Fairfax County funding construction cost

395 Express Lanes Project Update

slide-8
SLIDE 8

8

Sound Wall Voting Outcomes: Fairfax County

395 Express Lanes Project Update

slide-9
SLIDE 9
  • Virginia State Police supplemental support
  • WMATA and PRTC supplemental transit service
  • Teleworking implementation incentives
  • Pentagon Commuter Store
  • Vanpool incentives
  • Carpool incentives

9

Traffic Management Plan Update

slide-10
SLIDE 10

10

Thank you

For more information and to sign up for updates, please visit www.395expresslanes.com

  • r find us on Facebook at

www.facebook.com/395expresslanes

395 Express Lanes Project Update

Questions or concerns should be directed to: Michelle Holland, VDOT, michelle.holland@vdot.virgina.gov, 703-259-3378 Brent McKenzie, 95 Express Lanes, bmckenzie@transurban.com, 571-326-5609