I-39/US 10 Bridge Public Involvement Meeting

Wisconsin Department of Transportation

Portage County Library Stevens Point

August 22, 2019 4:30 p.m. to 6 p.m.

slide-2
SLIDE 2

Project Location

Begin Project End Project

slide-3
SLIDE 3

Need for a Project

  • 278 crashes from Country Club Drive to

Maple Bluff Road

  • Bridge is in need of repair
slide-4
SLIDE 4

Bridge Needs

slide-5
SLIDE 5

Bridge Needs

slide-6
SLIDE 6

Project Goals

  • Improve Safety
  • Extend life of bridge
  • Maintain the integrity of existing roadway
slide-7
SLIDE 7

Proposed Bridge Improvements

  • Replace bridge deck and approaches
  • Repair support structure
  • Paint steel components of the bridge
  • Provide improved wider pedestrian

accommodations

slide-8
SLIDE 8

I‐39 & US 10 Stevens Point

slide-9
SLIDE 9

Example Picture I‐35W & 96W Arden Hills, MN

slide-10
SLIDE 10
slide-11
SLIDE 11

Proposed Intersection Improvements

  • Shift left turn lanes
  • Extend US 10 WB auxiliary lane 500 feet
  • Change US 10 EB to I-39 NB to free flow
  • Signalize I-39 NB ramp intersection
  • Install a traffic signal head over each lane
  • Update curb ramps
  • Proposed Work
slide-12
SLIDE 12

Traffic Impacts

  • Stage 1
  • Off peak lane closures
  • WIS 66 EB to I-39 SB turn lane
  • Nighttime ramp closures
slide-13
SLIDE 13

Traffic Impacts

  • Stage 2 & Stage 3
  • I-39: Periodic lane closures
  • US 10/WIS 66
  • Three lanes; two EB, one WB
  • Temporary signals
  • Stage 2
  • Stage 3
slide-14
SLIDE 14
slide-15
SLIDE 15

Traffic Impacts

  • Stage 4
  • Off peak lane closures
  • Nighttime ramp closures
slide-16
SLIDE 16

Traffic Impacts

  • Ramp Closures
  • I-39 NB to US 10 EB ramp closed during bridge

construction

  • Access to I-39 restricted to right turns
  • Detour will use adjacent interchanges
slide-17
SLIDE 17
slide-18
SLIDE 18

Construction Timeframe

  • Construction is currently scheduled to begin

spring 2022

  • Bridge painting may occur fall 2022 or

spring 2023

slide-19
SLIDE 19

Where to find project information?

Wisconsindot.gov/pages/projects/by-region

slide-20
SLIDE 20

Questions?